Title: Vehicle Management System
1- Welcome To Our Presentation
Topic VEHICLE MANAGEMENT SYSTEM
Contact us 91 9873725832
2Overview
- Project Requirements
- Use case diagram
- Project Objective
- Project Scope
- Task identify
- PERT chart-Critical path analysis-Gantt chart
- Project Budget
3Requirements
- Introduction
- A Software requirements specification (SRS) is a
comprehensive description of the intended
purpose and environment for software under
development. - SRS defines how an application will interact with
system hardware, other programs human user in
a wide variety of real world situations. - Functional Requirement
- Non-Functional requirement
4Functional Non-Functional Requirements
Functional Requirement
Programming Languages Java (jdk1.5).
Web Technologies Database Server
Html, JavaScript. My_sql Tomcat Apache 5.0
Non-functional Requirement
Processor duel core
Hard Disk 512 MB Ram 256 MB
5Using Tools
The software used in this project is
? OS ? Data Base ?IDE ?Browser
Windows MS-SQL Server NetBeans Google Chrome
6Features
- ADMIN
- View/Edit/Delete Vehicle Details
- View/Edit/Delete Driver Details
- Booking Status Detail
- USER MODULE
- Login/Registration of User
- Take a Car trip (Google Map Integration)
- View Car Details
- Car Booking
7Use case Table (Vehicle System)
Level 0 Level 1 Level 2 Actor
Account Sign in Sign out User Admin
Vehicle System Search Vehicle name Route name Bus stop User Admin
Report About System, route Request for Add vehicle User
Update Add vehicle Add route Add Bus stop Change Location Admin
8Scope Objective For Project
- To register and keep the information about all
vehicles. - To build up a system that provides and generates
the summary - Report from the database records in order to get
the whole view about the vehicles amounts. - Summarize the accidental records and responds for
the further improvements. - A web based tool where user can search for
additional information of the vehicle.
9Task Identity procedure
As we are doing this by ourselves not for a
organization or for a company. So we collect
requirement by ourselves by brainstorming and
questioning other people. Later we discus among
us and fixed our requirement.
10Task Identity procedure
11Task Identity procedure
12Task Identity procedure
User Interface
13Task Identity procedure
- Quality Assurance
- Unit Testing
- Unit testing focuses verification effort on the
smallest unit of software design that is the
module. - Using procedural design description as a guide,
important control paths are tested to uncover
errors within the boundaries of the module. The
unit test is normally white box testing oriented
and the step can be conducted in parallel for
multiple modules. - Integration Testing
- Integration testing is a systematic technique for
constructing the program structure, while
conducting test to uncover errors associated with
the interface. The objective is to take unit
tested methods and build a program structure that
has been dictated by design.
14Task Identity procedure
- System Testing
- System testing is actually a series of different
tests whose primary purpose is to fully exercise
the computer-based system. Although each test has
a different purpose, all work to verify that all
system elements have been properly integrated to
perform allocated functions. - Security Testing
- Attempts to verify the protection mechanisms
built into the system. - Performance Testing
- This method is designed to test runtime
performance of software within the context of an
integrated system.
15FPA
16FPA
- Matrix Used for EO and EQ
17Pert chart
Activity Dependen cy Time Human
Requirme nt gather A _ 5 3
Desgin B A 3 2
Database C _ 8 4
Coding D A,C 6 3
Testing E B,C 4 3
Recovery F D 7 4
Release G E,F 5 2
B5,8
4
2
314,17
G21,26
1
6
7
521,26
D8,14
5
3
68,14
19
18Critical path analysis
TASK Time ES EF LS LF SLACK
A 5 0 5 9 14 9
B 3 5 8 14 17 9
C 8 0 8 0 8 0
D 6 8 14 8 14 0
E 4 8 12 17 21 9
F 7 14 21 14 21 0
G 5 21 26 21 26 0
19Gantt chart
20Budget
Task Cost Total
Buy new equipment 25000 25000
Developer cost 325000 75000
Testing cost 215000 30000
Hired skilled designer 210000 20000
Other cost 10000 10000
Total cost 160000 TK
21Thank you everybody