Resource Allocation - PowerPoint PPT Presentation

About This Presentation
Title:

Resource Allocation

Description:

IT Project Management Lecture 7 – PowerPoint PPT presentation

Number of Views:2021
Slides: 25
Provided by: inam12
Tags:

less

Transcript and Presenter's Notes

Title: Resource Allocation


1
Resource Allocation
  • Lecture 7
  • Software project management

2
Lecture Overview
  • Resource Identification
  • Resource Distribution
  • Resource Scheduling

3
What is Resource Allocation
  • After the activities have been identified using
    various techniques and tabulated into a
    Work-Break-Down the resources need to be
    allocated to complete the identified tasks. This
    process is considered resource allocation.

4
Who allocates resources?
  • Project Manager.
  • Concentrate on resources where there is a
    possibility that, without planning, they might
    not be sufficiently available when required.
  • Senior Software Developers are the hardest to
    find these need to be very carefully planned
    for in advance.
  • Developers do not like to wait for work, they
    prefer to be busy with activities and tasks that
    show clear progress.

5
Result of Resource Allocation
  • Reflected in many schedules,
  • Activity Schedule.
  • Resource Schedule.
  • Cost Schedule.
  • Changes to these schedules are very much
    interrelated and require domain experience to
    get it right.

6
Resource Categories
  • Labour (Even the project manager).
  • Equipment (Coffee Machine?).
  • Materials (Consumed items floppy disks).
  • Space (Rooms, Cubicles).
  • Services (Telecomm, Cleaning services).
  • Time (The most rigid item of all).
  • Money (Secondary resource).
  • Note These are broad categories only.

7
Resource Organisation
  • A program organization chart is essential to
    allocate staff effectively,
  • Develop the hierarchical program organization.
  • Identify Roles and Responsibilities.
  • Plan for number of staff in each role (at a high
    level).
  • Establish Teams.

8
Resource Requirement Identification 1
  • For each activity identify,
  • Work amount required (in work units)
  • Basic skill or experience level required (to even
    undertake the task)
  • Complexity of the task (this will help to
    determine the experience required)
  • Task Category (Unskilled, skilled, leadership,
    expert, management)

9
Resource Requirement Identification 2
  • Example.
  • Activity Install Network Hardware for 20
    computers.
  • Work units - 20.
  • Basic Skill Bachelors Degree in related field.
  • Task Complexity 5.
  • Task Category Skilled (other categories may be
    Management, Leadership, Expert)

10
Resource Scheduling
  • After all the required resources have been
    identified, they need to be scheduled
    effectively.
  • The earliest start dates, last start dates will
    need to be taken into account to schedule
    resources efficiently.
  • Resources should be balanced throughout the
    project.

11
Resource Scheduling 2
  • Human resource scheduling issues,
  • Planned Leave, Public Holidays.
  • Possible sick leave (random, subjective at best
    and hard to predict).
  • General motivation and enthusiasm for the task
    allocated (If they dislike the task, it will flow
    through into the output).
  • Work load and stress in project.
  • Stress outside work.

12
Resource Histograms
  • Commonly used during planning to indicate
    possible problem areas,
  • People (by category) Vs Week Number
  • For each individual estimated number of tasks
    (including complexity) over weeks
  • This helps in reducing work load some times to
    help the individual recover from any heavy load.
  • Category Vs Week

13
External Dependencies
  • When planning any resources that rely on external
    factors, these need to be planned with the
    associated risks involved.
  • Float or slack is the amount of time that a task
    in a project network can be delayed without
    causing a delay to
  • subsequent tasks ("free float")
  • project completion date ("total float")

14
Parallel, Sequential Tasks
  • Tasks run both in parallel and sequentially.
  • Depending on the activity network and critical
    path, resource allocation needs to be planned
    effectively.
  • Competing tasks need to be prioritised with risk
    before resource allocation.

15
Prioritisation Techniques
  • Total Float Priority
  • Ordered List Priority
  • There are many others that refine on top of
    these, but broadly these cover the general cases
    well.

16
Total Float Priority
  • Ordered according to their total float.
  • Smallest total float has highest priority.
  • Activities are allocated resources in ascending
    order of total float.
  • Changes to plan will require re-calculation.

17
Ordered List Priority
  • Activities that can proceed at the same time are
    ordered according to a set of simple criteria.
  • Burmans priority list takes into account
    activity duration as well as total float
  • Shortest critical activity.
  • Critical activities.
  • Shortest non-critical activity.
  • Non-critical activity with least float.
  • Non-critical activities.
  • Note Other ways of ordering are also possible.

18
Critical Paths
  • Resource scheduling will almost always change the
    activity network.
  • The changes often result in changes to the
    critical path.
  • Delaying an activity due to lack of correct
    resources will cause that activity to become
    critical after it uses up all its slack time.
  • These changes are often experienced after the
    project has started which will require adapting
    during the project (this is normally much harder
    in practice).

19
Cost of Resources
  • All projects concentrate on completion in the
    shortest time span with minimum resources (in
    planning stage).
  • However, once the project starts all un-planned
    for issues and any risks will cause some strain
    on the cost.

20
Resource Allocation Issues
  • Availability
  • Criticality
  • Risk
  • Training
  • Team Building

21
Cost Scheduling
  • Broad Categories
  • Staff.
  • Overheads (Office Space, Interest charges, Travel
    Costs, Insurance and so on).
  • Usage charges (for external resources or
    contractors, leased/rental equipment).

22
Scheduling in Practice
  • It should always be in the project planners
    mind, right from the start of the project.
  • During the resource scheduling and allocation
    phase of the planning activity a lot of the plan
    will change.
  • Most of the issues with respect to resource
    allocation and scheduling arise after the project
    starts (normally after about 30 of the
    activities are complete).

23
Summary
  • Identify all resources required.
  • Arrange activity start/end dates to minimise
    variations in resource levels over the duration
    of the project.
  • Allocate resources to competing activities in a
    rational order of priority.
  • Critical/High-Risk activities should be backed up
    by experienced staff.

24
References
  • Hughes. B and Cotterell. M, Software Project
    Management, 2nd Edition, McGraw Hill 1999.
  • Cantor. M. R, Object Oriented Project Planning
    with UML, Wiley 2000.
Write a Comment
User Comments (0)
About PowerShow.com