Title: Master Calendar


1
Master Calendar The Digital Bridge Trust Fund Act
November 1, 2000
2
Agenda
  • Background on Community Technology Centers
    Program
  • Purpose of Master Calendar
  • Approach
  • Timeline Community Technology Centers
  • Task 1. Staff
  • Task 2. Offices
  • Task 3. Funding
  • Task 4. Program Monitoring Evaluation
  • Conclusion

3
Community Technology Centers
What? Community Technology Centers
(200M). Why? Assist in bridging digital
divide. Where? Underserved rural, urban,
Native American areas. How? Provide
funding to various community based
organizations who are interested in setting up
community technology centers.
4
Purpose of Master Calendar
  • Provide a comprehensive timeline for program
    implementation.
  • Help achieve programmatic goals and objectives in
    consideration of allocated resources.
  • Delineate tasks and sub-tasks to specific
    organizational units and staff members.

5
Approach
  • Draw from organizational and staffing plan,
    budget plan, and performance management/TQM
    analysis.
  • Determine who performs the tasks.
  • Establish dependencies between tasks.
  • Assign appropriate task length.
  • Align tasks with fiscal year.

6
Organizational Chart
7
Timeline Staff
Task 1. Hire Digizone Program Staff - 135 days

Task Name Duration Start Date End Date
1.1 Regional Digizone HQ Staff 1.1.1 Office of the President 1.1.2 Office of the Regional Coordinator 1.1.3 Office of the Financial Officer 1.1.4 Review Board 75 days 11/01/00 02/13/01
1.2 State Digizone Staff (50 statesD.C.) 40 days 01/10/01 03/06/01
1.3 Local Digizone Staff 25 days 04/04/01 05/08/01
8
Timeline Offices
Task 2. Establish Digizone Admin. Offices 125
days

Task Name Duration Start Date End Date
2.1 Establish Regional Digizone HQ 25 days 12/06/00 01/09/01
2.2 Establish State Digizone Offices 25 days 01/10/01 02/13/01
2.3 Establish Local Offices (Proj.Mgrs) 25 days 04/25/01 05/29/01
9
Timeline Funding
Task 3. Funding Allocation for Digizones 153
days

Task Name Duration Start Date End Date
3.1 Needs Assessment Reg. Digizones 40 days 02/07/01 04/03/01
3.2 Application and Review Process 47 days 03/26/01 05/29/01
3.3 Implementation and Support 73 days 05/30/01 09/07/01
10
Timeline Monitoring/Evaluation
Task 4. Program Monitoring Evaluation 83 days

Task Name Duration Start Date End Date
4.1 Follow-up Site Visits 68 days 06/06/01 09/07/01
4.2 Semi-Annual/Concluding Reports 5 days 09/10/01 09/14/01
4.3 Summarize Program Evaluations for Presidents 5 days 09/10/01 09/14/01
4.4 Digizones Present Annual Report to Board of Trustees 5 days 09/17/01 09/21/01
4.5 Board of Trustees Prepare Report to President and Congress 5 days 09/24/01 09/28/01
11