Is It Time To Update Your System Coordination - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Is It Time To Update Your System Coordination

Description:

The Electric Power Research Institute estimates annual outage costs to society ... circuit conditions burns the conductor and may also anneal the steel strand. ... – PowerPoint PPT presentation

Number of Views:82
Avg rating:3.0/5.0
Slides: 33
Provided by: lplea1
Category:

less

Transcript and Presenter's Notes

Title: Is It Time To Update Your System Coordination


1
Is It Time To Update Your System Coordination?
2
The Electric Power Research Institute estimates
annual outage costs to society amount to 119
billion.
3
Unscheduled outages cost the average large
industrial customer approximately 40,000.
4
Some states are beginning to enforce fines for
poor system performance (primarily in
de-regulated states)
5
Is It Time To Update Your System Coordination?
6
Approximately 75 percent of all overhead faults
have a temporary cause
7
Typical causes of temporary faults
  • Lightning
  • Animals Birds cause 25 of all overhead outages
    in the U.S.
  • Trees or debris
  • Vehicles hitting poles (conductors slap
    together)

8
A sustained outage is typically defined as an
outage lasting 5 minutes or longer
9
Reliability Indices
  • Most Common
  • SAIDI System Average Interruption Duration
    Index
  • SAIFI System Average Interruption Frequency
    Index
  • CAIDI Customer Average Interruption Duration
    Index
  • MAIFI Momentary Average Interruption Frequency
    Index
  • Less Common
  • ASAI Average Service Availability Index
  • (8,760-SAIDI)/8,760 x 100
  • CEMI Customers Experiencing Multiple
    Interruptions

10
Typical U.S. Utility Values of
  • SAIDI 110 minutes each year
  • SAIFI 1.4 interruptions per year
  • CAIDI 79 minutes per year
  • ASAI 99.98

11
A well sectionalized system with good
coordination should decrease the SAIFI, SAIDI and
CAIDI, but may increase the MAIFI
12
A well sectionalized system with good
coordination should also decrease your OM costs.
13
How much are you spending on a per outage basis?
14
When designing an economical coordination scheme,
outage data is an invaluable tool.
15
Linemen/Operations staff are the best resource
for determining the locations that could use a
protective device.
16
(No Transcript)
17
(No Transcript)
18
So, how often should you update your system
coordination?
19
Summary of Results, Conclusions and
Recommendations from Conductor Break Tests
20
Equipment Used
  • Line truck with winch and tested high tension
    capacity spring scales.
  • Conductors were attached using a dead-end shoe.

21
introduction
A total of 20 conductor break tests were
preformed, 18 on 4 ACSR and two on 8 CWC. All
conductors were pulled to the point that the
conductor either broke or tension was released
from the wire stretching. All of the damaged
conductors tested were from lines with stretched
conductor which the Engineer recommended to for
either total line replacement or the replacement
of the conductor but were included only for
re-sagging by the FEMA Project Officer.
22
SUMMARY OF TEST RESULTS
23
NOTE All 4 ACSR conductors which were not
previously stretched in the storm, which were
conductors that broke above their rated breaking
strength, would stretch significantly before
breaking and then break at about 1600 pounds.
24
conclusions
  • New and undamaged 4 ACSR conductors take a
    permanent stretch of a few feet between 2500 and
    2600 pounds and then drop in breaking strength to
    about 1600 pounds.

25
  • It is nearly impossible to detect conductor
    damage either from the ground or even up close to
    the conductor. However, some of the best
    indications of conductor damage are
  • Excessive sag. This probably indicates the
    conductor has taken a permanent stretch and has
    lost 30-35 percent of its strength. The damaged
    (stretched) segment will likely be 10-15 feet in
    length.

26
  • Splices. It was found that many of the
    conductors broke at or near a splice. The splice
    did not appear to have failed. It is likely that
    the entire damage segment of the conductor, up to
    ten feet on each side of a break, was not
    replaced after the conductor broke and while
    splicing new a segment. It appeared that the
    aluminum strands broke outside the splice then
    the steel strand pulled out of the splice. This
    was true for both the automatic and compression
    splices tested.
  • Locations were short circuit contacts frayed or
    nicked the conductor. The arc which occurs
    during short circuit conditions burns the
    conductor and may also anneal the steel strand.
    Usually this type of damage is localized to a
    short length.

27
  • The test indicated that when excessive sagging
    occurred, it is likely that the conductor was
    damaged only is short segments, not the entire
    span.

28
  • The armor rod near the support seems to protect
    the conductor from damage due to excessive
    tension.
  • A span of stretched conductor is most likely to
    be weakened just beyond the armor rod at the
    supports.

29
  • Short circuit and the resulting pitting on CWC
    conductors deduces the strength of the conductor.
  • Automatic splices, when properly installed, have
    as much or more strength as the conductor.

30
recommendations
  • If a conductor breakers due to tension loading
    (i.e., breakers not due to burning from current
    at electrical short circuits), a minimum of 5.0
    feet on each side of the break should be cut out
    before repairing the conductor.

31
  • Conductors which incurred increase sag due to ice
    loading should be replaced as the results of
    these tests indicate that there is a high
    probability that there was a significant loss of
    conductor strength.

32
Questions?
Write a Comment
User Comments (0)
About PowerShow.com