Upcoming Changes in State - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Upcoming Changes in State

Description:

Crossing Within 140-ft of Intersection. Traffic Volumes Alone ... Locomotive Horn. FRA Approved Quiet Zone. Wayside Horn. Constant Warning Time Train Detection ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 16
Provided by: varoujanj
Category:

less

Transcript and Presenter's Notes

Title: Upcoming Changes in State


1
Upcoming Changes in State Federal
RulesPertaining to Highway-Rail Xings
  • Presented by
  • Varoujan Jinbachian, PE

2
  • CPUC General Orders
  • GO 75
  • GO 164
  • MUTCD
  • Warrant 9
  • Wayside Horns
  • Quiet Zones
  • New Definitions

3
CPUC Rail Crossings
  • Jurisdiction over Rail Crossings
  • RCES/ROSS/RTSS
  • Public Utilities Code
  • General Orders

4
Proposed CPUC Rule Changes
  • GO 75-D
  • Policy Statement
  • AREMA as Standards
  • Traffic Signal Interconnection
  • Crossings Required to be Gates
  • Elimination of Tracks

5
Proposed CPUC Rule Changes (Cont)
  • GO 164-D
  • New Procedure for Approving light rail crossings
  • Hazard Analysis Report

6
(No Transcript)
7
NCUTCD
  • 21 Sponsoring Organizations
  • Recommends to FHWA
  • 8 Technical Committee
  • Task Forces
  • 2 Meetings per Year

8
Proposed MUTCD Changes
  • Warrant 9 for Signalizing Intersections Near
    Highway-Rail Crossings
  • Wayside Horn Section
  • Quiet Zone Section
  • New Definitions

9
Proposed Warrant 9
  • Warrant applies only If
  • Crossing Within 140-ft of Intersection
  • Traffic Volumes Alone Do Not Justify a Signal
  • If Distance is Less Than 40-ft Signal Always
    Warranted, Unless Opportunity of Evasive Maneuver
    is Provided

10
(No Transcript)
11
Paramount Blvd Rosecrans Ave, City of Paramount
12
Proposed Wayside Horn Section in MUTCD
  • Description of Wayside Horn
  • Fail-Safe Design
  • Xings with Wayside Horn must Have FLS and Gates
  • Confirmation Indicator
  • Simulate a Train Horn
  • Directed Towards Approaching Road

13
Proposed Quiet Zone Section in MUTCD
  • Follows Structure Horn Rule (49CFR222)
  • Temporary Closure
  • Four-Quadrant Gate System
  • Gates with Raised Medians
  • One Way Streets with FLS
  • and Gates
  • Permanent Closure

14
Proposed New Definitions in MUTCD
  • Diagnostic Team
  • Locomotive Horn
  • FRA Approved Quiet Zone
  • Wayside Horn
  • Constant Warning Time Train Detection

15
Contact Info
  • Varoujan Jinbachian
  • vsj_at_cpuc.ca.gov
  • 213-576-7081
  • http//www.cpuc.ca.gov/crossings
Write a Comment