Title: Rail Model Implementation


1
Rail Model Implementation
  • Presenter Riad Khan
  • Venue Portfolio Committee
  • Date 11 June 2003
  • Time 11h00

2
Introduction
  • The Rail Model
  • The implementation arrangement
  • Government Policy and Planning Processes
  • Rail Model Implementation Status
  • Spoornet Performance Indicators

3
The Rail Model
  • Process
  • Task Team
  • Cabinet Memorandum
  • Distinction between the two
  • Tri-partite Structure
  • Individual Implementation teams
  • Luxrail Employment Issues Task Team
  • NFA Transport Sector
  • Job Loss Mitigation Task Team
  • Light and Low Density Line Network Task Team
  • Spoornet Restructuring Committee(Sub Committee of
    the Transnet Restructuring Committee)

4
The Rail Model cont
  • The Model
  • Integrated General Freight Business(GFB) and
    CoalLink
  • OREX to be shadow incorporated and restructuring
    options to be developed
  • Extended network - 15 800km, that includes a
    selection of light density lines
  • Expanded volumes up to 2020
  • Operating efficiencies and productivity
    improvements supported by the required levels of
    investment
  • Investigation of a two-tier management structure
    for light and low density line network
  • Tri-partite Task Team to investigate status of
    low density line network
  • Government to hold Spoornet accountable for
    performance and turnaround strategies and
    projects

5
The Rail Model cont
  • The Model cont
  • Implementation audit mechanism to be implemented
    by NFA Transport Sector
  • 8 000 employer induced retrenchments to be
    implemented
  • Tri-partite Job-loss Mitigation Task Team to be
    established
  • Appropriate Road to Rail policy initiatives to be
    developed and implemented by NDOT
  • Luxrail to be concessioned
  • Passenger Rail consolidation to be investigated

6
The Implementation Arrangement
  • Spoornet Tripartite Committee
  • Decide on implementation teams and areas of
    responsibility
  • Agree Terms of Reference
  • Agree on processes
  • Steering Committees and Task Teams
  • Government consensus development
  • Implementation Teams
  • Tri-partite consensus on specific restructuring
    projects

7
Government Policy and Planning Processes
  • Rail Policy
  • Rail Plan
  • Integrated Logistics Task Team(Restructuring)
  • Integrated Freight Logistics Strategy
  • BEE Coal Export Forum

8
Rail Model Implementation Status
  • Integration of General Freight Business(GFB) and
    CoalLink
  • Operations and Management have been integrated
    2002
  • Reporting as an accounting entity within Spoornet
    2002/03

9
Rail Model Implementation Status
  • OREX
  • Discussions were held with Anglo-American on the
    optimisation of iron-ore assets and related
    infrastructure in Northern Cape(commenced June
    2002)
  • MOU signed in Dec 2002
  • Anglo-American exits discussions May 2002
  • Process forward
  • Regional Mineral Development strategy to be
    finalised by DME
  • Regional economic development strategies and
    initiatives to be finalised by DTI and Northern
    Cape Province
  • Restructuring Model development
  • Engagement with Labour

10
Rail Model Implementation Status
  • Extended network - 15 800km, that includes a
    selection of light density lines
  • Actual retained operational network may be
    larger, depending on the outcomes of the regional
    assessments

11
Rail Model Implementation Status
  • Expanded volumes up to 2020
  • Volume expansion predicated on recapitalisation
    programme
  • Recapitalisation plan not finalised
  • Impact on funding needs of Transnet
  • Government assessing medium to long term elements
    of recapitalisation
  • Re-capitalisation dependant on locomotive
    delivery schedules (2004)
  • Reversal of trend expected post 2004

12
Rail Model Implementation Status
  • Operating efficiencies and productivity
    improvements supported by the required levels of
    investment
  • Investment case being finalised
  • Low and light density component still being
    finalised
  • Operational efficiency elements still being
    developed(Labour and Spoornet)
  • Spoornet Strategy not finalised as yet

13
Rail Model Implementation Status
  • Investigation of a two-tier management structure
    for light and low density line network
  • Investigation currently being performed in Light
    and Low Density Line Network Task
    Team(Tri-partite)
  • Initial structural elements developed
  • Ring-fenced entity within Spoornet
  • Separate regional strategy and structure
  • Business case and regional network components to
    be finalised
  • International Comparative Business Model Study
    and options being developed

14
Rail Model Implementation Status
  • Tri-partite Task Team to investigate status of
    low density line network
  • Currently being performed in Light and Low
    Density Line Network Task Team(Tri-partite)
  • Initial investigations completed
  • Regional strategies and consultative processes
    commenced June 2003
  • Regional strategy and structure to be developed
    to integrate with Local and Provincial
    Development Strategies and initiatives

15
Rail Model Implementation Status
  • Government to hold Spoornet accountable for
    performance and turnaround strategies and
    projects
  • Spoornet performance monitoring consolidated in
    Transnet performance management by DPE
  • Spoornet operational efficiency monitoring and
    performance management being developed alongside
    recapitalisation plan

16
Rail Model Implementation Status
  • Implementation audit mechanism to be implemented
    by NFA Transport Sector
  • NFA Transport Sector has not commenced the
    performance audit process as yet, as all parties
    are awaiting the finalisation of network,
    operation and financial arrangements
  • Model implementation structures are functioning
    and no significant dissatisfaction exists with
    processes and outcomes
  • Slow progress on all processes is major concern
    for Government

17
Rail Model Implementation Status
  • 8 000 employer induced retrenchments to be
    implemented to 2006
  • Process awaited the establishment of the Transnet
    Restructuring Committee and the establishment of
    the Spoornet Restructuring Sub-committee
  • Reluctance to accelerate retrenchments till
    finalised structures and operations
  • Awaiting finalisation of Job-loss Mitigation
    Process

18
Rail Model Implementation Status
  • Tri-partite Job-loss Mitigation Task Team to be
    established
  • Task Team is operational
  • Team is developing methodologies and structures
    to ensure maximum mitigation
  • Integration with Transnet wide processes being
    developed (Transnet Social Plan)

19
Rail Model Implementation Status
  • Appropriate Road to Rail policy initiatives to be
    developed and implemented by NDOT
  • NDOT developing a range of these initiatives and
    are contextualising these in the Rail Policy and
    Planning processes eg.
  • Investigating impact of GVM on road maintenance
    costs
  • Raising institutional capability to enforce
    existing regulation
  • NDOT driving the integration of Provincial
    development and transport policy and planning
    with the Road to Rail initiatives

20
Rail Model Implementation Status
  • Luxrail to be concessioned
  • Concessioning process was at advanced stage prior
    to fire that destroyed portion of one train set
  • Interest in the concession was registered by
    international hotel and rail companies
  • Three weeks away from public announcements when
    suspended
  • Currently awaiting Transnet decision on timing of
    refurbishment so as to commence revised financial
    modelling and due diligence
  • Agreement reached with Labour on employee issues,
    awaiting signature of Transnet

21
Rail Model Implementation Status
  • Passenger Rail consolidation to be investigated
  • Inter-governmental task team investigated
    consolidation and developed consolidation options
  • Outstanding institutional elements have been
    referred to Principals for resolution
  • Main issues identified
  • Capital subsidy for backlog reversal to be
    finalised and approval sought
  • Operational optimisation to be developed with
    Provincial and Local Transport Authorities
  • Operational subsidy to be finalised and approval
    sought

22
Spoornet Performance Indicators
23
Spoornet Performance Indicators cont
24
Spoornet Performance Indicators cont
25
Spoornet Performance Indicators cont
26
Shosholoza Meyl Performance Indicators