Title: Work Breakdown Structure WBS Development
1Work Breakdown Structure (WBS) Development
Department of Human ServicesProject Management
Office
2Agenda Items
- What is a Breakdown Structure
- Where does it fit in PM
- Bottom Up Development
- Top Down Development
- Help and References
- Additional Questions
3WBS Introduction
- Training Goal
- To understand the process, its purpose and
benefits. - To learn enough about the process to begin using
it. - To know where you can access the process and any
of the supporting materials.
4(No Transcript)
5WBS Definition
- A deliverable-oriented grouping of project
elements that organizes and defines the total
scope of the project work. - Work not in the WBS is not in scope of the
project. -
- Each descending level represents an
increasinglydetailed description of the project
elements. - Often used to develop or confirm a
commonunderstanding of project scope.
6Where the WBS Fits
7(No Transcript)
8What does a WBS look like?
9Breakdown Structures
10Example - PBS/What?
CAR
- Fenders
- Roof
- Hoods
- Doors
- Windows
-
-
- Carburetor
- Cylinders
- Piston
- Cam
-
-
-
- Front Seats
- Back Seats
- Radio
-
- Steering
- Fuel
- Odometers
- Wipers
- Lights
-
-
11Example - WBS/How?
12Example - OBS/Who?
- Staff1
- Staff2
- Staff3
- Staff4
-
-
-
- Staff1
- Staff2
- Staff3
- Staff4
- Staff5
-
13WBS Diagram
Project
Deliverable 2.0
Deliverable 1.0
Deliverable 3.0
Work Package 2.1
Work Package 1.1
Work Package 3.1
Work Package 1.2
Work Package 3.2
Work Package 2.2
Work Package 3.3
Work Package 1.3
Work Package 2.3
Work Package 2.4
E-1
14Benefits of the WBS
Risk and Contingency Plans
Estimates
Schedule
WBS
Activity List
Progress Reports
Project Plan
15Common Approaches
16Bottom up WBS Development
16
171. Create the to-do list of work
- Review/Discuss WHAT is to be delivered.
- Review no-limitations brainstorming.
- Brainstorm list of work on a ..
- End first meeting.
- Compile list into tool that allows all
participants easy access.
17
18Step 1 - TIPS
- Sit down and participate as a peer.
- Have someone else write on the board.
- Encourage starting with a verb.
- Dont correct or worry about wording.
- Capture all phrases, thoughts.
- Explanation not required.
18
19Useful Brainstorming Verbs
- Assessment
- Review, Research, Collect, Analyze, Assess,
Determine, Identify - Requirements
- Define, Describe, Design, Develop work
activities, Choose, Obtain, Prepare, Approve - Construction
- Construct, Build, Write, Obtain, Create
- Validation
- Validate, Pilot, Check, Test
- Implementation
- Implement, Move, Train, Replace, Evaluate
19
202. Organize the to-do list.
- Back at a desk have someone organize the list.
- Take very detailed, but related steps and group
them into tasks. Name the task. - Take related tasks and group them into
activities. Name the activity. - Group activities into phases.
20
21Step 2 - TIPS
- Do what appears easiest first.
- Go back adjust as you go through it.
- Adjust the wording now, not intent.
- Create a miscellaneous activity.
- For the under-developed tasks or activities leave
space for adding later.
223. Review/adjust structure with group
- Tell the group what has been done.
- Go through structure, fix and confirm groupings.
Adjust names. - Add additional forgotten tasks or activities.
21
23Step 3 - TIPS
- Constrain Level of Detail
- Lowest level should be completedin approximately
1-3 weeks. - Lowest level should contain a definition that
includes the detailed steps.
22
244. Verify Correctness /Completeness
- At the lowest level you should be able to
- Name all the work packages
- e.g. scope definition document,
- code specification 1,
- painted exterior.
- Indicate Dependencies.
- Apply approximate duration.
- Assign a resource role
- e.g. carpenter, tester.
23
254. Common Obstacles
- Discussing or setting requirements.
- Talking about solutions rather than the work.
- Wanting to sequence and assign resources too
early. - Level of detail issues.
- Other issues.
24
261. Choose your model.
Top Down WBS Development
2. Verify highest level Deliverables/Phases.
3. Can adequate ests. be made at this level?
Yes
5. Confirm lowest level.
WBS Complete
No
4. Review, Verify and or modify the next
subsequent level.
25
271. Choose your model
Top Down
- Review various
- life cycle models,
- similar projects WBS, or
- life cycle templates.
- Choose a model closest to your specific
project.
Note Various life cycle templates and examples
from other projects are available on the PMO web
site.
26
2827
292. Verify highest level phases/deliverables
Start at the top of a model - Deliverables
- Verify deliverables represent the major phases
of your project, - Verify purpose/need of each major deliverable or
phase, - Determine if a previous project completed a
major deliverable, e.g. Feasibility. - Choose to eliminate or modify deliverable after
review of previous completed work
28
303. Can adequate estimates be made at this level?
Yes Decisions Guidelines
- Can it be completed within a 2 3 week
period? - Adequate may change over the course of the
project. - Estimating a major work package that will be
produced 6 12 months out may not be
possible.
Note This steps question means - different
levels of decomposition are appropriate for each
of the major deliverables/phases.
29
314. Review, verify and or modify the next
subsequent level.
- Very, from the model, the next subsequent
levels, more specific work detail.
- Choose the appropriate work elements.
- elements should be described in tangible,
verifiable results in order to facilitate the
project progress. - Repeat step 3 for each work element that you have
chosen necessary for the project.
30
325. Confirm lowest level
Are the lower-level items both necessary and
sufficient?
If no, combine items, add to, delete, redefine.
Does the work item description provide a scope?
If no, revise or expand the descriptions
Can the item be scheduled? Budgeted? Assigned to
a specific organizational unit (e.g., department,
team, or person)?
If no, the item must be modified,split, redefined.
31
33Lesson Learned
34Whats Next?
Further decomposition into a WBS Dictionary
- Briefly describe each item
- Reference by number
- List associated activities
- List milestones
- List other information needed to facilitate work
35Closing
The greatest benefit of developing a work
breakdown structure is providing a common
understanding of all the work required to deliver
the product or service.
36(No Transcript)
37Additional Questions?
38Please fill out both sides.