Title: UK Radioactive Waste Conditioning and Long Term Management
1UK Radioactive Waste Conditioning and Long Term
Management Some Challenges
by Gregg Butler Professor of Science in
Sustainable Development, Sustainable Environment
Policy Programme, University of Manchester Grace
McGlynn Head of Corporate Social Responsibility,
BNFL, and Associate, SEPP, University of
Manchester
2Starting Points NDA
- On 1 April 2005, the Nuclear Decommissioning
Authority (NDA) takes ownership of 50B of
liabilities on the 20 sites formerly owned by
BNFL and UKAEA - The NDAs mission is to clean up these sites,
putting into a passive form the untreated waste
and returning the sites to a green or brown
endpoint mainly yet to be decided
3Starting Points - CoRWM
- In July 2006, the Committee on Radioactive Waste
Management (CoRWM) will make recommendations to
Ministers on the option, or combination of
options, that can provide a long-term solution,
inspiring public confidence and providing
protection for people and the environment - Whatever the option is success will require
not only that the option(s) is/are accepted, but
that the option(s) are acted on and funded - The overall NDA plus CoRWM field of activity
can be visualised as
4Managing the Nuclear Legacy Scoping the Job
Hazard Potential
5Managing the Nuclear Legacy Scoping the Job
Hazard Potential
6Challenges
- If a 50B Government Funded Project went without
a hitch it would indeed be a matter of note! - The rest of this presentation poses a few
challenges, and hopes in some small way to help
stimulate the successful surmounting of these
challenges
7The Stakeholder Acceptability Challenge
The NDA mission is to progressively clean up
sites which will mean either waste storage at
many, or a concentration on fewer, sites. The
CoRWM mission is to provide a long-term solution,
inspiring public confidence Both of these
missions will need enough stakeholder buy-in to
make decisions and actions politically
deliverable this is the acceptability challenge.
8The Stakeholder Acceptability Challenge
- From the BNFL National Stakeholder Dialogue there
is good stakeholder agreement that - Wastes should be made increasingly passive
- The creation of wastes should be minimised
- Environmental, societal and economic benefits and
detriments have to be balanced - Decision making processes, underlying assumptions
and data collection must be transparent - Stakeholder views must be both sought and
respected
9The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
10The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
11The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
12The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
13The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
14The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
15The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
16The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
17The Stakeholder Acceptability Challenge
- Every move in this direction would have
- Sites where waste conditioning has finished and
jobs are lost - Sites reaching a brown or green end state
- Areas affected by transport movements
- Sites having to accept other peoples wastes
- Relevant experience with proposed transfer of LLW
from Dounreay and commercial bids for ISOLUS
both to West Cumbria
18The Resources Challenge
NDA is a Non-Departmental Public Body disbursing
2B in a year to contractors, and being
accountable to Government, with surveillance by
the National Audit Office and various Select
Committees Its planned staffing of around 200
for the whole NDA looks very small against the
need to also make sure that the right things are
done in the right order, and that the strategy
(rather than the administration) of spend is
effective.
19The Funding Challenge
- The White Paper Managing the Nuclear Legacy
tasked the NDA with systematically and
progressively driving forward clean up of the
nuclear legacy - As long as nothing major goes wrong on nuclear
sites, there are many more vote-winning things a
Chancellor could spend money on than clean-up - Funding cleanup is likely to be a challenge in
both the long and the short term
20The Funding Challenge
- This challenge was recognised in the White Paper,
which stated (in Section 6.1) that - Managing nuclear liabilities cost effectively
requires financial flexibility and competent long
term planning. There is some flexibility within
the budgetary settlements agreed with funding
departments as part of the Spending Review
process, but three-year settlements are, almost
always, shorter than the timescale for major
decommissioning projects. In the past, nuclear
clean up has also been seen as a low priority for
funding purposes relative to other programmes
21The Funding Challenge
- And continued that
- Experience to date with UKAEA has therefore been
that settlements have tended to be the minimum
necessary to address safety and environmental
needs and that limited funding has been available
for other projects
22The Funding Challenge
- Nuclear site cleanup is about reducing the
hazard potential of the site while maintaining
safety and environmental protection
- Nuclear sites cost money to run for maintaining
safety, environmental protection, security and
the like - The first tranche of money given to a site will
go on these activities - Money above this level can be spent on cleanup
and progress in cleanup thus varies with funding
one can envisage various funding patterns
23Site Cleanup Spend Patterns
Doing the job
M per annum
Playing at the job
Playing with fire
Time
24Current value
Time - Years
25The Funding Challenge
- Raising discount rate gives large incentive to
delay cleanup - Actually experienced by UKAEA
- The discount rate essentially defines what
concepts such as inter-generational equity mean
in practice - Cleanup (NDA) and Long Term Waste Management
(CoRWM) surely need to run on financing
assumptions which are either explicitly the same
or explicitly different - A suitable subject for stakeholder engagement!
26The Funding Challenge
- Managing the Nuclear Legacy consulted on
funding via a Segregated Fund or a Segregated
Account,
- to avoid the funding problems
already noted for UKAEA - Virtually all respondents wanted the Fund
- What weve got for the 05-06 budget is the
Spending Review with all the pitfalls which
were so well expressed in the White Paper
27The Funding and Resource Challenge - CoRWM
- Last time the UK had a failure in its radwaste
policy was the Nirex debacle in 1997 it cost us
around 500M - CoRWM has a limited budget for public and
stakeholder engagement before making its
recommendations for future options in 2006 - The resources the Canadians are putting in to one
waste at nine sites can be judged at
http//www.nwmo.ca/ as compared to
www.corwm.org.uk. for six categories of waste and
20 sites
28The Regulatory Challenge
- The NDA is set up to achieve progress in cleanup
while balancing societal, environmental and
economic factors. - We have some processes to achieve these balances
one of them is called BPEO - If we were to use this process sensibly, giving a
transparent balance of all factors on a UK basis
then limited resources would be most effectively
used - BUT the current trend is to more and more BPEOs
which can lead to stakeholder fatigue and the
absence of UK optimisation
29The Regulatory Challenge
- In the old days, at least UKAEA and BNFL owned
the problems and tried to optimise their
respective bits of the programme - Now only the 200 brave souls in the NDA will give
an Australian Lager for the overall optimum NDA
are the only people who own the problem
- NDA therefore have a real job on and must hold
the ring against licensees, Treasury and
regulators, all of which will, left to their own
devices, act as single-interest groups.
30The Regulatory Challenge
Stakeholder scenarios and alignment
From a presentation by Peter Wylie, British
Nuclear Group, October 2004
31The NDA Mission
- What exactly are the NDA being tasked to do?
- The NDA mission from MNL (reflected in the Energy
Act) is developing coherent strategy for clean
up which makes best use of available skills and
resources. Its focus on delivery of that
strategy will also ensure that the job gets done
in a manner which enhances safety and
environmental performance whilst delivering best
value for money. It will match the response to
the scale of the task and the timescales involved
and make the whole process more open and more
transparent. - But it needs a strategy and plan to deliver this
mission
32So What is Needed?
- Ongoing stakeholder engagement about UK policy
issues preferably in ways which enable balances
between different factors to be much more
explicitly examined and defined - A current bad example the new DTI policy on
decommissioning encourages examination of
different site end points with local stakeholder
involvement
- meanwhile the HSE
consultation on delicensing recommends a one in a
million risk to the maximally exposed individual
and emphasises ALARA - So whatever end point is reached on most sites -
itll be a licensed end point!! -
33So What is Needed?
- Many things that the NDA are committed to by MNL
and the Act but more importantly things that
seem to be in line with the approach to date of
the Chairman and CEO - Put measures, including discount rates, into the
mission to reduce the UKs nuclear liabilities so
that overall success or failure can be judged - Make sure the NDAs strategy puts specific
methodologies in place to attain the balance of
factors sought both for cleanup and for the
continuation of plant operation
34So What is Needed?
- Consult on what the methodologies and balances
should be, say what is adopted, and tell how the
methodologies are to be used - Make transparent what is NDAs strategy, and also
make transparent where the ability to deliver
this is put at risk by external considerations - Report regularly (both NDA and site contractors)
on progress being made and hazard potential
reduction being achieved
35And are we going to get it??
- BNFL and UKAEA had limited ability to resist
political and regulatory pressure - The money NDA is spending is now clearly OUR
money so getting value for money into the
balance can be seen to benefit everyone - NDA occupies the position, and can acquire the
power, to hold the ring and transparently
manage a success story