UK Radioactive Waste Conditioning and Long Term Management

1 / 35
About This Presentation
Title:

UK Radioactive Waste Conditioning and Long Term Management

Description:

On 1 April 2005, the Nuclear Decommissioning Authority (NDA) ... and Emplacement) Surface Storage - Conditioned Waste. B. Disposal or Other. Long Term Management ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 36
Provided by: rwin7

less

Transcript and Presenter's Notes

Title: UK Radioactive Waste Conditioning and Long Term Management


1
UK Radioactive Waste Conditioning and Long Term
Management Some Challenges
by Gregg Butler Professor of Science in
Sustainable Development, Sustainable Environment
Policy Programme, University of Manchester Grace
McGlynn Head of Corporate Social Responsibility,
BNFL, and Associate, SEPP, University of
Manchester
2
Starting Points NDA
  • On 1 April 2005, the Nuclear Decommissioning
    Authority (NDA) takes ownership of 50B of
    liabilities on the 20 sites formerly owned by
    BNFL and UKAEA
  • The NDAs mission is to clean up these sites,
    putting into a passive form the untreated waste
    and returning the sites to a green or brown
    endpoint mainly yet to be decided

3
Starting Points - CoRWM
  • In July 2006, the Committee on Radioactive Waste
    Management (CoRWM) will make recommendations to
    Ministers on the option, or combination of
    options, that can provide a long-term solution,
    inspiring public confidence and providing
    protection for people and the environment
  • Whatever the option is success will require
    not only that the option(s) is/are accepted, but
    that the option(s) are acted on and funded
  • The overall NDA plus CoRWM field of activity
    can be visualised as

4
Managing the Nuclear Legacy Scoping the Job
Hazard Potential
5
Managing the Nuclear Legacy Scoping the Job
Hazard Potential
6
Challenges
  • If a 50B Government Funded Project went without
    a hitch it would indeed be a matter of note!
  • The rest of this presentation poses a few
    challenges, and hopes in some small way to help
    stimulate the successful surmounting of these
    challenges

7
The Stakeholder Acceptability Challenge
The NDA mission is to progressively clean up
sites which will mean either waste storage at
many, or a concentration on fewer, sites. The
CoRWM mission is to provide a long-term solution,
inspiring public confidence Both of these
missions will need enough stakeholder buy-in to
make decisions and actions politically
deliverable this is the acceptability challenge.
8
The Stakeholder Acceptability Challenge
  • From the BNFL National Stakeholder Dialogue there
    is good stakeholder agreement that
  • Wastes should be made increasingly passive
  • The creation of wastes should be minimised
  • Environmental, societal and economic benefits and
    detriments have to be balanced
  • Decision making processes, underlying assumptions
    and data collection must be transparent
  • Stakeholder views must be both sought and
    respected

9
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
10
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
11
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
12
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
13
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
14
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
15
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
16
The Stakeholder Acceptability Challenge
This has real implications for a future moving
from 20 NDA sites to a much smaller number as
waste is retrieved, conditioned, and potentially
transported to regional or national management
options
17
The Stakeholder Acceptability Challenge
  • Every move in this direction would have
  • Sites where waste conditioning has finished and
    jobs are lost
  • Sites reaching a brown or green end state
  • Areas affected by transport movements
  • Sites having to accept other peoples wastes
  • Relevant experience with proposed transfer of LLW
    from Dounreay and commercial bids for ISOLUS
    both to West Cumbria

18
The Resources Challenge
NDA is a Non-Departmental Public Body disbursing
2B in a year to contractors, and being
accountable to Government, with surveillance by
the National Audit Office and various Select
Committees Its planned staffing of around 200
for the whole NDA looks very small against the
need to also make sure that the right things are
done in the right order, and that the strategy
(rather than the administration) of spend is
effective.
19
The Funding Challenge
  • The White Paper Managing the Nuclear Legacy
    tasked the NDA with systematically and
    progressively driving forward clean up of the
    nuclear legacy
  • As long as nothing major goes wrong on nuclear
    sites, there are many more vote-winning things a
    Chancellor could spend money on than clean-up
  • Funding cleanup is likely to be a challenge in
    both the long and the short term

20
The Funding Challenge
  • This challenge was recognised in the White Paper,
    which stated (in Section 6.1) that
  • Managing nuclear liabilities cost effectively
    requires financial flexibility and competent long
    term planning. There is some flexibility within
    the budgetary settlements agreed with funding
    departments as part of the Spending Review
    process, but three-year settlements are, almost
    always, shorter than the timescale for major
    decommissioning projects. In the past, nuclear
    clean up has also been seen as a low priority for
    funding purposes relative to other programmes

21
The Funding Challenge
  • And continued that
  • Experience to date with UKAEA has therefore been
    that settlements have tended to be the minimum
    necessary to address safety and environmental
    needs and that limited funding has been available
    for other projects

22
The Funding Challenge
  • Nuclear site cleanup is about reducing the
    hazard potential of the site while maintaining
    safety and environmental protection
  • Nuclear sites cost money to run for maintaining
    safety, environmental protection, security and
    the like
  • The first tranche of money given to a site will
    go on these activities
  • Money above this level can be spent on cleanup
    and progress in cleanup thus varies with funding
    one can envisage various funding patterns

23
Site Cleanup Spend Patterns
Doing the job
M per annum
Playing at the job
Playing with fire
Time
24
Current value
Time - Years
25
The Funding Challenge
  • Raising discount rate gives large incentive to
    delay cleanup
  • Actually experienced by UKAEA
  • The discount rate essentially defines what
    concepts such as inter-generational equity mean
    in practice
  • Cleanup (NDA) and Long Term Waste Management
    (CoRWM) surely need to run on financing
    assumptions which are either explicitly the same
    or explicitly different
  • A suitable subject for stakeholder engagement!

26
The Funding Challenge
  • Managing the Nuclear Legacy consulted on
    funding via a Segregated Fund or a Segregated
    Account,
  • to avoid the funding problems
    already noted for UKAEA
  • Virtually all respondents wanted the Fund
  • What weve got for the 05-06 budget is the
    Spending Review with all the pitfalls which
    were so well expressed in the White Paper

27
The Funding and Resource Challenge - CoRWM
  • Last time the UK had a failure in its radwaste
    policy was the Nirex debacle in 1997 it cost us
    around 500M
  • CoRWM has a limited budget for public and
    stakeholder engagement before making its
    recommendations for future options in 2006
  • The resources the Canadians are putting in to one
    waste at nine sites can be judged at
    http//www.nwmo.ca/ as compared to
    www.corwm.org.uk. for six categories of waste and
    20 sites

28
The Regulatory Challenge
  • The NDA is set up to achieve progress in cleanup
    while balancing societal, environmental and
    economic factors.
  • We have some processes to achieve these balances
    one of them is called BPEO
  • If we were to use this process sensibly, giving a
    transparent balance of all factors on a UK basis
    then limited resources would be most effectively
    used
  • BUT the current trend is to more and more BPEOs
    which can lead to stakeholder fatigue and the
    absence of UK optimisation

29
The Regulatory Challenge
  • In the old days, at least UKAEA and BNFL owned
    the problems and tried to optimise their
    respective bits of the programme
  • Now only the 200 brave souls in the NDA will give
    an Australian Lager for the overall optimum NDA
    are the only people who own the problem
  • NDA therefore have a real job on and must hold
    the ring against licensees, Treasury and
    regulators, all of which will, left to their own
    devices, act as single-interest groups.

30
The Regulatory Challenge
Stakeholder scenarios and alignment
From a presentation by Peter Wylie, British
Nuclear Group, October 2004
31
The NDA Mission
  • What exactly are the NDA being tasked to do?
  • The NDA mission from MNL (reflected in the Energy
    Act) is developing coherent strategy for clean
    up which makes best use of available skills and
    resources. Its focus on delivery of that
    strategy will also ensure that the job gets done
    in a manner which enhances safety and
    environmental performance whilst delivering best
    value for money. It will match the response to
    the scale of the task and the timescales involved
    and make the whole process more open and more
    transparent.
  • But it needs a strategy and plan to deliver this
    mission

32
So What is Needed?
  • Ongoing stakeholder engagement about UK policy
    issues preferably in ways which enable balances
    between different factors to be much more
    explicitly examined and defined
  • A current bad example the new DTI policy on
    decommissioning encourages examination of
    different site end points with local stakeholder
    involvement
  • meanwhile the HSE
    consultation on delicensing recommends a one in a
    million risk to the maximally exposed individual
    and emphasises ALARA
  • So whatever end point is reached on most sites -
    itll be a licensed end point!!

33
So What is Needed?
  • Many things that the NDA are committed to by MNL
    and the Act but more importantly things that
    seem to be in line with the approach to date of
    the Chairman and CEO
  • Put measures, including discount rates, into the
    mission to reduce the UKs nuclear liabilities so
    that overall success or failure can be judged
  • Make sure the NDAs strategy puts specific
    methodologies in place to attain the balance of
    factors sought both for cleanup and for the
    continuation of plant operation

34
So What is Needed?
  • Consult on what the methodologies and balances
    should be, say what is adopted, and tell how the
    methodologies are to be used
  • Make transparent what is NDAs strategy, and also
    make transparent where the ability to deliver
    this is put at risk by external considerations
  • Report regularly (both NDA and site contractors)
    on progress being made and hazard potential
    reduction being achieved

35
And are we going to get it??
  • BNFL and UKAEA had limited ability to resist
    political and regulatory pressure
  • The money NDA is spending is now clearly OUR
    money so getting value for money into the
    balance can be seen to benefit everyone
  • NDA occupies the position, and can acquire the
    power, to hold the ring and transparently
    manage a success story
Write a Comment
User Comments (0)