1
Capacity Planning
  • Chapter 14

2
Capacity Planning
  • Capacity planning decisions involve trade-offs
    between the cost of providing a service (i.e.,
    increasing the number of servers) and the cost or
    inconvenience to the customer
  • Involves determining the appropriate level of
    service capacity by specifying the proper mix of
    facilities, equipment, and labor required to meet
    anticipated demand

3
Classification of Queuing Models
4
Single Server M/M/1
  • ? OOOO
  • ? arrivals per time period
  • O customer
  • server

5
M/M/1 Boat Launch Example
  • If ? 6 boats arrive per hour
  • µ 10 boats launched per hour
  • p ? / µ
  • Then
  • probability that the customer must wait is
  • p 6 / 10 0.6 or 60
  • probability that the customer does not have to
    wait is
  • p0 1- 0.6 0.4 (40)

6
M/M/1 Boat Launch Example
  • Mean number of boats in the system
  • Ls ? / (µ ?)
  • Ls 6 / (10 6) 6/4 1.5 boats
  • Mean number of boats in the queue
  • Lq (p?) / ((µ ?)
  • Lq (.6 x 6) / (10 6) 3.6 / 4 .9 boats

7
M/M/1 Boat Launch Example
  • Mean time in the system
  • Ws 1 / (µ ?) 1 / (10 6) ¼ hour
  • Mean time in queue
  • Wq p / (µ ?) 0.6 / (10 6) .15 hour

8
Multiple Servers M/M/c
  • ? OOOO
  • ? arrivals per time period
  • O customer
  • servers

9
M/M/4 Secretarial Pool Example
  • If ? 9 requests per hour
  • c 4 servers
  • p ? / c (used to calculate the value of p0)
  • Then
  • probability that a faculty member does not have
    to wait for secretarial work is
  • P0 1
  • (9/4)0 (9/4)1 (9/4)2 (9/4)3 (9/4)4
  • 0! 1! 2! 3!
    4!(1-9/16)
  • P0 0.098

10
M/M/4 Secretarial Pool Example
  • Mean number of jobs in the system
  • p c1
  • Ls (P0 p)
  • (c-1)!(c-p)2
  • (9/4)5
  • Ls
    (0.098) 9/4
  • (4-1)!(4-9/4)2
  • Ls 2.56

11
M/M/4 Secretarial Pool Example
  • Mean time for each secretarial job in the system
  • Ls
  • Ws
  • ?
  • 2.56
  • Ws 0.28 or 17 minutes per job