Title: Production and Operations Management: Manufacturing and Services
1Chapter 3
Project Management
2OBJECTIVES
- Definition of Project Management
- Work Breakdown Structure
- Project Control Charts
- Structuring Projects
- Critical Path Scheduling
3Project Management
- Project is a series of related jobs usually
directed toward some major output and requiring a
significant period of time to perform - Project Management are the management activities
of planning, directing, and controlling resources
(people, equipment, material) to meet the
technical, cost, and time constraints of a project
4Advantages
Structuring Projects Pure Project
A pure project is where a self-contained team
works full-time on the project
- The project manager has full authority over the
project - Team members report to one boss
- Shortened communication lines
- Team pride, motivation, and commitment are high
5Disadvantages
Structuring Projects Pure Project
- Duplication of resources
- Organizational goals and policies are ignored
- Lack of technology transfer
- Team members have no functional area "home"
6Functional Project
A functional project is housed within a
functional division
Example, Project B is in the functional area of
Research and Development.
7Structuring Projects Functional Project
Advantages
- A team member can work on several projects
- Technical expertise is maintained within the
functional area - The functional area is a home after the project
is completed - Critical mass of specialized knowledge
8Structuring Projects Functional Project
Disadvantages
- Aspects of the project that are not directly
related to the functional area get short-changed - Motivation of team members is often weak
- Needs of the client are secondary and are
responded to slowly
9Structuring Projects Matrix Project
Organization Structure
10Structuring Projects Matrix Project
Advantages
- Enhanced communications between functional areas
- Pinpointed responsibility
- Duplication of resources is minimized
- Functional home for team members
- Policies of the parent organization are followed
11Structuring Projects Matrix Project
Disadvantages
- Too many bosses
- Depends on project managers negotiating skills
- Potential for sub-optimization
12Statement of Work (SOW)
- A statement of work contains
- objectives to be achieved
- work to be done
- proposed schedule specifying the start and
completion date - performance measures in terms of budget and
completion steps (milestones) - written report to be supplied
13Work Breakdown Structure
A work breakdown structure defines the hierarchy
of project tasks, subtasks, and work packages
14Gantt Chart
Shows the amount of time involved and the
sequence in which activities can be performed
Vertical Axis Always Activities or
Jobs Activities Pieces of work that consume
time Do not necessarily require the expenditure
of effort by people
Horizontal Axis Always Time
15Network-Planning Models
- A project is made up of a sequence of activities
that form a network representing a project - The sequence of activities that form the longest
chain in terms of their time to complete is the
critical path in a project - The critical path provides a wide range of
scheduling information useful in managing a
project - Critical Path Method (CPM) helps to identify the
critical path(s) in the project networks
16Prerequisites for Critical Path Methodology
- A project must have
- well-defined jobs or tasks whose completion marks
the end of the project - independent jobs or tasks
- and tasks that follow a given sequence.
17Types of Critical Path Methods
- CPM with a Single Time Estimate
- Used when activity times are known with certainty
- Used to determine timing estimates for the
project, each activity in the project, and slack
time for activities - CPM with Three Activity Time Estimates
- Used when activity times are uncertain
- Used to obtain the same information as the Single
Time Estimate model and probability information - Time-Cost Models
- Used when cost trade-off information is a major
consideration in planning - Used to determine the least cost in reducing
total project time
18Steps in the CPM with Single Time Estimate
- Activity Identification
- Activity Sequencing and Network Construction
- Determine the early start/finish and late
start/finish schedule - Determine the Critical Path
- The path with zero slack time
19Steps in the CPM with Single Time Estimate
1. Activity Identification 2. Activity Sequencing
and Network Construction
20Steps in the CPM with Single Time Estimate
3. Determine the early start/finish and late
start/finish schedule
21Steps in the CPM with Single Time Estimate
4. Determine the Critical Path the path with
zero slack time ABD
22Steps in the CPM with Single Time Estimate
1. Activity Identification 2. Activity Sequencing
and Network Construction
23Steps in the CPM with Single Time Estimate
- 3. Determine the early start/finish and late
start/finish schedule - 4. Determine the Critical Path the path with
zero slack time
24Steps in the CPM with Single Time Estimate
Example Page 95, Solved Problem 1
25CPM with Single Time Estimate
More Example Consider the following consulting
project
Develop a critical path diagram and determine the
duration of the critical path and slack times for
all activities.
26First draw the network
Act. Imed. Pred. Time
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
27Determine early starts and early finish times
ES4 EF6
D(2)
ES0 EF2
ES2 EF3
ES3 EF4
ES9 EF14
ES14 EF15
G(1)
A(2)
B(1)
C(1)
F(5)
ES4 EF9
Hint Start with ES0 and go forward in the
network from A to G.
E(5)
28Determine late starts and late finish times
Hint Start with LF15 or the total time of the
project and go backward in the network from G to
A.
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C(1)
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
29Critical Path Slack
ES4 EF6
D(2)
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C(1)
ES4 EF9
LS14 LF15
LS9 LF14
E(5)
LS4 LF9
Duration15 weeks
30Steps in the CPM with Three Activity Time
Estimates
- Activity Identification
- Activity Sequencing and Network Construction
- Calculate the expected time for each activity
- Determine the early start/finish and late
start/finish schedule - Determine the Critical Path
- Calculate the variances of the activity times
- Determine the probability of completing the
project on a given date
31Steps in the CPM with Three Activity Time
Estimates
Example 3.2 Page 84
32Steps in the CPM with Three Activity Time
Estimates
33Steps in the CPM with Three Activity Time
Estimates
Example Page 95, Solved Problem 2
34CPM with Three Activity Time Estimates
More Example
35Expected Time Calculations
ET(A) 34(6)15 6
ET(A)42/67
36Expected Time Calculations
ET(B) 24(4)14 6
ET(B)32/65.333
37Expected Time Calculations
ET(C) 64(12)30 6
ET(C)84/614
38Network
39Probability Exercise
What is the probability of finishing this project
in less than 53 days?
p(t t
TE 54
40(Sum the variance along the critical path.)
41TE 54
D53
p(Z There is a 43.8 probability that this project
will be completed in less than 53 weeks.
42Additional Probability Exercise
- What is the probability that the project duration
will exceed 56 weeks?
43Additional Exercise Solution
p(Z .312) .378, or 37.8 (1-NORMSDIST(.312))
44Time-Cost Models
- Basic Assumption Relationship between activity
completion time and project cost - Time Cost Models Determine the optimum point in
time-cost tradeoffs - Activity direct costs expediting activities
- Project indirect costs sustaining the project
- Activity completion times
45Steps in the Time-Cost Models
- Determine the cost per unit of time to expedite
each activity number of days activity may be
shortened given - Normal cost (NC) the lowest expected activity
cost - Normal time (NT) the time associated with each
normal cost - Crash time (CT) the shortest possible activity
time - Crash cost (CC) the cost associated with each
crash time - Determine the critical path
- Shorten the critical path at the least cost
46Steps in the Time-Cost Models
Given CT, NT, NC, CC for each activity
47Steps in the Time-Cost Models
1. Determine the cost per unit of time to
expedite each activity number of days activity
may be shortened given
48Steps in the Time-Cost Models
2. Determine the critical path
Critical Path A B D
49Steps in the Time-Cost Models
3. Shorten the critical path at the least cost
(by one day at a time)
50Steps in the Time-Cost Models
Example Page 96, Solved Problem 3
Exercise Page 100, Problem 8
51CPM Assumptions/Limitations
- Project activities can be identified as entities
(There is a clear beginning and ending point for
each activity.) - Project activity sequence relationships can be
specified and networked - Project control should focus on the critical path
- The activity times follow the beta distribution,
with the variance of the project assumed to equal
the sum of the variances along the critical path - Project control should focus on the critical path
52Question Bowl
- Which of the following are examples of Graphic
Project Charts? - Gantt
- Bar
- Milestone
- All of the above
- None of the above
Answer d. All of the above
53Question Bowl
- Which of the following are one of the three
organizational structures of projects? - Pure
- Functional
- Matrix
- All of the above
- None of the above
Answer d. All of the above
54Question Bowl
- A project starts with a written description of
the objectives to be achieved, with a brief
statement of the work to be done and a proposed
schedule all contained in which of the following?
- SOW
- WBS
- Early Start Schedule
- Late Start Schedule
- None of the above
Answer a. SOW (or Statement of Work)
55Question Bowl
- For some activities in a project there
may be some leeway from when an activity can
start and when it must finish. What is this
period of time called when using the Critical
Path Method? - Early start time
- Late start time
- Slack time
- All of the above
- None of the above
Answer c. Slack time
56Question Bowl
- How much slack time is permitted in the
critical path activity times? - Only one unit of time per activity
- No slack time is permitted
- As much as the maximum activity time in the
network - As much as is necessary to add up to the total
time of the project - None of the above
Answer b. No slack time is permitted (All
critical path activities must have zero slack
time, otherwise they would not be critical to the
project completion time.)
57Question Bowl
- When looking at the Time-Cost Trade Offs in the
Minimum-Cost Scheduling time-cost model, we seek
to reduce the total time of a project by doing
what to the least-cost activity choices? - Crashing them
- Adding slack time
- Subtracting slack time
- Adding project time
- None of the above
Answer a. Crashing them (We crash the
least-cost activity times to seek a reduced total
time for the entire project and we do it
step-wise as inexpensively as possible.)
58End of Chapter 3