Title: IPROMS
1IPROMS Kick-Off Meeting Andrea GENTILI EC
Project Officer (Andrea.gentili_at_cec.eu.int) 15
October 2004, Cardiff, United Kingdom
This presentation is a DRAFT version, any
information given is INDICATIVE and NON-BINDING
2Project Organisation
- Co-ordinator
- Project Management Board
- Project Technical Committee
- Task Leaders
- Exploitation Group - User Group
- Commissions Programme Officer
3Critical Success Factors
- Clear project programme with partners roles well
defined - Partners commitment to objectives - in-line with
business strategies - Effective Management and understanding between
partners - Sound exploitation plans and continuous follow-up
of exploitation and dissemination
4Contract Structure
- Core contractstandard with specifics of project
- Annex IDescription of Work - the project
- Annex IIGeneral Conditions
- Annex III Specific provisions (e.g. competitive
calls for new contractors)
5Contract Structure
- Annex IV - Form A
- Consent of contractors identified in the
core-contract (article 1.2) to accede to the
contract. - Annex V - Form B
- Accession of new legal entities to the
contract. - Annex VI - Form C
- Financial statement per activity. Specific to
each instrument and/or type of action. To be
filled periodically by each contractor.
6Range of Contractual Agreements
Subcontractor
Coordinator
Contract
Contractor x
ConsortiumAgreement
Commission Contract
Commission
Contractor y
Contract
Contractor z
Subcontractor
7Contractors
- General Rule Participant contractor
- Every legal entity contributing to a project
must have a contractual link with the Community - A contractor may carry out exclusively management
tasks - Exceptional cases subject to very restrictive
rules - Third parties identified in Annex I
- Subcontractors
-
8Subcontracting
- Subcontracting is considered as an exception
- where it is necessary to subcontract certain
elements of the work, this should be clearly
identified in Annex I. - any subcontract, the costs of which will be
claimed under the project, must be offered to the
best bid (value for money) in compliance with the
national legislation of the contractor concerned. - For public legal entities internal rules for
selection of service providers (public call for
tender) - For private legal entities submission of several
quotes (usually a minimum of three), unless it
has an established framework contract for the
provision of those services.
9Signature and entry into force
- Contractual link of all contractors with the
Commission - New Contract enters into force upon signature
of coordinator and Commission - All the contractors are identified in the core
contract Art. 1.2 - Coordinator must ensure other contractors sign
within delays - Distribution of advance - Several options
available minimum number of participants/all
participants - Evolution of consortium possible
- where one or more does not sign the Form A
article 2 - in case of enlargement (new contractors)
article 3 - Project begins in the date established in the
contract (this can be before the contract enters
into force but usually later)
10 Amendments
- Art.10 of Core Contract Art.8 of Annex II
- Request in writing
- New at the request of the coordinator, deemed to
act on behalf of the consortium - New Tacit amendments with implicit agreement of
the Commission within 6 weeks only for
modification and evolution of the consortium and
for technical reports - New in IP/NoE, enlargement of the consortium to
new contractors and new activities may be
foreseen. This enlargement follows, in principle,
a competitive call launched by the consortium
with evaluation of proposals by external experts
11Further novelties
- Payments to be confirmed by an audit certificate
- Consortium Management costs reimbursed up to
100 within the limit of 7 of Community
contribution - cost categories are replaced by conformity to
contractors own accounting rules and legal
environment
12pre-financing and start of project
- Distribution of pre-financing to co-ordinator
within 45 days of the date of entry into force of
contract/date of signature of minimum number of
participants/date of signature of last contractor - Distribution of pre-financing to contractors
not before minimum number of contractors have
acceded to the contract - Project begins in the date established in the
contract (this can be before the contract enters
into force but usually later)
13financial aspects
- No cost categories but list of ineligible costs
Art. II.19(2) - For financial reporting use Form C - Model of
Financial Statement per Activity (specific per
instrument) - To be eligible, costs must be
- actual, economic and necessary for the project
- incurred during the duration of the project
- (exception costs of final reports)
- recorded in the accounts of the contractor (or
third parties) and must exclude indirect taxes,
duties, interests, costs reimbursed in respect of
another Community project - follow contractors own accounting rules
- Not give rise to profit
14financial aspects
- Indication on cost categories in annual report
- Audit certificates by external auditor (for
public bodies - competent public auditor) per
partner every year (IP/NoE) after 1 year and at
the end (STREP/CA) only at the end (SSA)
15Costs
- Breakdown between type of activity Demo, RTD,
Training, Management and Other activities - Each cost must be recorded under the correct type
of activity in order to allow easy verification
of the costs (audit certificate) - Management cost are limited to 7 of the total EC
funding
16Cost reporting models
- FC actual direct and indirect costs
- FCF (variant of FC) actual direct costs flat
rate for indirect costs (20 of total actual
direct costs minus subcontracting) - AC actual additional direct costs flat rate
for indirect costs (20 of total actual
additional direct costs minus subcontracting) -
only for those non-commercial or non-profit
organisations that do not have an accounting
system allowing to share direct and indirect
costs relating to the project
17Cost reporting models
General Rule a legal entity applies the same
cost model in ALL contracts established under FP6
except may move from AC to FCF/FC or from FCF to
FC (one way ticket)
18Progress Reporting Schedule
Reporting schedule for a 36-month project
Interim Activity report (normally 6 months
intervals)
Periodic activity report
Periodic Financial Management Report (cost
statements)
Audit certificate
Final Activity Report
Final Financial Management Report
36
30
24
18
6
12
Project Months
19Payments and reporting schedule (example of a 3
year contract)
Final reporting period
Final report
Audit
Reported costs
Second reporting period
Periodic activity report
Audit
Reported costs
Third advance payment
Detailed work plan
Periodic activity report
First reporting period
Audit
Reported costs
Second advance payment
Detailed work plan
Start of the project
Initial advance payment
Detailed work plan
0
6
12
18
24
30
36
20Cash Flow
Total Spent
Negative cash flow
Pre-financing(85 for first 18 months)
PeriodicPayment
Periodic Payment
Final Payment
21Implementation of the project
- Periodic Report containing (45 days after the
end of each reporting period) - Activity Report
- A management level overview of the activities
- A description of progress toward scientific and
technological objectives - A description of progress toward the milestones
and deliverables foreseen - The identification of problems encountered and
corrective action taken
22Implementation of the project
- Management Report
- A management-level justification of the
resources, linking them to activities implemented
and justifying their necessity - A financial part
- A financial statement showing the total eligible
costs incurred broken down by type of activity
(by each participant) - A summary financial report consolidating the
costs and requested Community contribution,
broken down by type of activity (by the
co-ordinator) - A report on the allocation of the Community
financial contribution to each participant
23Implementation of the project
- Final Report containing
- Final Report
- A Final Activity Report covering all the work,
objectives, and the final plan for using and
disseminating the knowledge, including summary of
all aspects - A Final Management Report covering the full
duration of the project including a summary
financial report consolidating the claimed costs
of all contractors - Any Supplementary Final Reports required by any
Annex to the contract. - A Report on the distribution between participants
of the final payment of the Community financial
contribution. (60 days after receipt of final
payment by the coordinator)
24Implementation of the project
- Audit certificate
- In addition, and at the times foreseen by the
contract, the consortium will submit an audit
certificate for each participant. - The audit certificate will be provided by an
independent external auditor or by a competent
public official and will certify the overall
total of eligible costs incurred by each
participant.
25Report preparation procedure
Partners
Commission
Respect deadlines
Periodic Report
Issues/Requests/Reminders
Consolidate technical, exploitation financial
data
Co-ordinator/Project Office
Early reminders about reports due
Individual partners
26Web-site to be considered
- Public pages
- project abstract, contact details
- publications
- Internal pages (FTP server)
- full contact details of personnel
- project programme, contract
- meeting schedules, venues
- minutes of meeting, reports, etc.
27Joint liability (1)
- New Collective responsibility of the contractors
- Mechanism by which a contractor may be held
liable, technically and/or financially, fully or
partially, for the action of another contractor - Why?
- Reinforce the protection of the financial
interests of the Community, both quantitative
(only pay what is due to be paid) and qualitative
(ensure that the project continues) - Consequence of FP6 principle of autonomy of the
consortium if the money is granted to the
consortium, which decides on its allocation, then
the consortium as a whole is to be held liable
28Audits and Controls
- The Commission may at any time during the
contract and up to five year after the end carry
out scientific, technological or financial
controls or audits - These controls and audits can be carried out by
the Commission or by outside reviewers or
auditors - In exceptional cases outside reviewers may be
refused on the grounds of commercial
confidentiality -
29Controls (2) Art. II.29
How? New continuous monitoring by Commission
with external experts (mandatory for IP and
NoE), based on simplified procedures (no public
procurement) New periodical reviews of results
achieved and expenditure made - go/no-go
procedure (12 months basis for IP NoE - ad hoc
for other instruments)
30Sanctions
Autonomy implies accountability New in case of
irregularity in a contract... 1 - exclusion from
the contract 2 - New exclusion from OTHER FP6
contracts, and from other Community policies 3 -
New ineligible to participate in FP6 activities,
and from other Community policies New
liquidated damages in case of financial
overstatement Without prejudice to civil and
criminal sanctions
31Consortium agreement
- Regulates internal organisation and management of
consortium (Mandatory for IP and NoE) - Between contractors - NOT signed nor approved by
the Commission - Non binding guidelines provided by the Commission
- Suggestion should include clear agreements in
case of joint liability (e.g. a common emergency
fund)
32Consortium Agreement
Complementary to Commission Contract
- Management
- distribution of funds (automatic or
non-automatic) - internal organisation of work, internal
reporting - evolution of the consortium
- IPR (to be decided before signature of contract)
- Risk management / collective responsibility
- Decision-making process
33Intellectual Property Rights (IPR)
- Developed on the basis of
- Feedback from FP5
- Features of the new instruments
- contractors may leave/join during the project
- larger projects
34IPR - Principles
- Consistency with FP5 (similar concepts)
- Simplification
- ? New Same IPR rules for ? all instruments
(fewer exceptions) - ? New Same IPR rules for all contractors
- Increased certainty, in particular regarding
access rights (restricted to what is necessary) - Increased emphasis on the management of knowledge
and IP (especially new instruments)
35Rules relating to Intellectual Property
Access Rights (art. II.35)
36For more information
- Legal framework within FP6 / Model contract
- europa.eu.int/comm/research/fp6/working-groups/mod
el-contract/index_en.html - www.cordis.lu/fp6/find-doc.htm
- Approved core contract and annex II
- Approved annex III
- Consortium checklist, financial guidelines, Form
A- accession to the contract - Helpdesk
- www.ipr-helpdesk.org
- RTD-A03-Question-juridiques_at_cec.eu.int
- General information on FP6-NMP
- www.cordis.lu/fp6/nmp.htm
- Guidelines
- For Project Co-ordinators
- For Reporting (draft available at
http//www.cordis.lu/nmp/find-doc.htm)