Title: WGA Annual Meeting SSGWI Studies
1SSG-WI Transmission Study Transmission Issues
Group Meeting September 4, 2003
2Overview
- SSG-WI
- SSG-WI Studies
- Methodology
- Assumptions
- Results
- Sub-Regional Studies
- Northwest Power Pool
- Rocky Mt.
- Why isnt sufficient expansion being done?
3Why SSG-WI?
- SSG-WI Formed by the Three RTOs to facilitate
development of a seamless Western Market - SSG-WI Goal is to facilitate the development of
electric infrastructure necessary to support
competitive wholesale electricity markets. - Focuses on economic transmission needs, economic
considerations influencing future generation/load
patterns, flows congestion - WECC Studies Focuses on Reliability, Adequacy
4- Goals Objectives
- Facilitate development of a flexible, cost
effective, robust west-wide transmission network
to facilitate competitive wholesale electricity
markets. - Identifies future congestion and bottlenecks that
impact cost effective and efficient service - Provides developers, load serving entities, and
Transmission Owners information on economic
transmission needs, locational impacts of
generation and load additions, cost/benefits of
new transmission additions. - Provides a forum for parties and consortiums to
identify common transmission additions to
implement
5SSG-WI Studies
6- Studies
- Time frame for expansion options of 5-10 years in
the future beyond already committed projects - Studies use transmission ratings and cost
estimates from reliability based analysis - Studies use production cost techniques (market
simulation tool) as surrogate for estimating
future dispatch, load and generation patterns,
and operational effects as influenced by
economics, and given reliability - Understood to be conservative floor on estimates
- Given unit commitment, assumes transparency and
ample scheduler time to make best dispatch - Studies use Regional Economic Planning Database
- Partnership with WECC CREPC, Coordinated
- Development validation efforts equitably shared
- Portable Usable on various models
- Visible Typical data, not confidential,
encumbered, or proprietary, publicly available - Transparent No Black Boxes, expansion info
available to all - User Improved
7Methodology
8Assessing New Transmission Benefits
- VOM Reduction Reduction of Variable OM costs
from reducing bottlenecks and allowing lower cost
generation through system - Net Benefit Method
9Net Transmission Benefits with added Transmission
Consumers
Consumer surplus (benefit) increases in A, prices
fall
Price Falls
Area A
(Cheaper Imports)
Transmission Addition
Producer surplus (benefit) decreases in B, prices
rise
Area B
Price Rises
Net Benefits method adds price effects of
increasing consumer surplus and decreasing
producer surplus
Producers
10Evaluating Transmission Projects
- Conduct simulations with and without a
transmission upgrade - Track change in fuel costs, VOM
- Track estimated market energy prices at load and
generation - Compare consumer surplus and producer surplus to
calculate economic benefit of an upgrade - How to value producer surplus is a policy issue
- Compare cost of transmission upgrade to economic
benefits - Develop cost-effective projects
- Compare common expansion elements
- To various Generation Scenarios
- To various consortium, cluster, or party
interests - To policies and societal goals
- Develop consensus on plan
11Economic Benefits From Transmission
- Reduce overall operational costs
- Improve Access and Flexibility to lower cost
power and portfolio diversity - Improve market access and market operation
- Hedge against price spikes and market power
- Capture fuel diversity
- Reduce losses
- Accomplish energy policies
- Increase Reliability
12What is not Modeled Yet
- Bidding behavior
- Contracts
- Wheeling costs
- Generation fixed costs
13Modeling and Database Status
- Not done yet
- Bidding behavior
- Contracts
- Wheeling costs
- Generation fixed costs
- Yet to Come
- Granularity
- Hydro shaping and hourly model
- Zone Changes
- Ownership and Schedules
- Load Diversity
- Pricing Pancakes
- Operational Characteristics
- Storage Issues
- Hydro
- Emission Allowances
- Fuel Delivery
- Wind Variability
- Bidding Behavior
- Forced Outages
- Losses
14Assumptions
- Two years (2008 2013) were chosen to identify
short-term and longer-term potential transmission
needs - In 2013 -three scenarios with different
generation types intended as bookend measures
were chosen to bracket the potential
transmission needs - Gas scenario - new generation (2008 - 2013) adds
18,000 MW, of gas fired combined cycle, located
near load centers - Coal scenario - displaces 16,000 MW of the Gas
scenario generation and requires transmission to
serve load - Renewable scenario - adds 25,000 MW of renewable,
displacing 9,000 MW of of the Gas scenario
generation, predominately located in remote areas
and requiring transmission to serve load
15Path Expansion 2013 (Value Rank) - 2008
16(No Transcript)
172008 Results
- SSG-WI Study focused on 2013 generation scenarios
but provided other information. - With Expected Transmission and Generation, there
are Transmission Constraints not being addressed - Study includes six of BPAs Infrastructure
Projects and still have Significant Congestion - NWPP Sub-Regional Planning Effort will follow up
the SSG-WI work with incremental and more
detailed studies, focused on the Northwest
18Results Summary 2008
- Existing WECC Transmission Costs
- WECC 2008 Case shows some bottle-necked
inexpensive resources - 110 million VOM
savings, and 600 million net benefit - Resource Development
- New resources are mostly gas-fired CCCTs
- Capacity by fuel type is shifting toward gas, the
change in energy is greater than the rate of
capacity increase - Total VOM Cost Estimates
- More sensitive to gas scenario than hydro
scenario - In 2008, for every 1/MMbtu change in gas price,
fuel costs in the Western Interconnection change
2 billion
19(No Transcript)
202008 Shadow Prices - (2003 )
21Developing a broad regional consensus
- Different entities have different concerns
- Generation Companies
- Transmission Owners
- Permitting Agencies
- Landowners
- Environmental groups
- No common forum to Develop a common vision for
all of these entities - The answer is to form sub-regional groups where
all interested parties can participate in
developing the plan
22Sub-Regional Planning
- Local Stakeholder Involvement and Review
- Representative rep at Regional Level
- Localized and Micro Visibility of Costs and
Benefits for facilitation of Financing and
Implementation - Closer to Jurisdictional, LSE, and Consortium
Organization - Clustering and Overcoming 888 Queing Problems
- Coordination of Sub Regional Projects Identified,
with Regional Projects, Schedules, and Markets - Granularity and detail
23(No Transcript)
24Current Efforts
- SSG-WI results show further evidence that there
is congestion not only with new generation
scenarios, but also in 2008. - NWPP Transmission Assessment Committee (NTAC) is
scoping out its mission - NTAC will provide further analysis of expansion
value but will not have the authority to allocate
costs or compel construction. - Will this information spur transmission
construction?
19
25Impediments to Transmission Construction
- High-risk, long-term investments
- Could economics of project change in next 40
years? - Limited access to capital
- better investments available
- Free Rider and distributed benefits Issues
- why take the risk if someone else might do it.
- Benefits are wide spread to other systems than
those making the investment - Uncertainty about rules for Cost Recovery and
Rights - - Allocation of cost/rights between States,
Jurisdictions, Parties - - Tariff rules 888, SMD, LGIA, ???
- Not everyone wants to remove congestion
- some congestion can improve market position.
20
26Improvement Areas
- Stabilize rules
- Assure revenue recovery
- Assure property rights for investments
- Remove incentive or ability to block projects
- Streamline regulatory review for multi-state
projects
21
27Potential Solution
- Independent Entity Responsible for Planning and
Expansion - Provide justification of projects for regulatory
approval - Identify beneficiaries and allocate costs
- Provide dispute resolution
22