Project Board January Update for Worcs Community - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Project Board January Update for Worcs Community

Description:

Unable to progress Day Care. RBAC Roles defined and Set-Up on the ... Day Care, Mental Health and System Admin still outstanding . Owner. Impact. Rag. Status ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 22
Provided by: csc294
Category:

less

Transcript and Presenter's Notes

Title: Project Board January Update for Worcs Community


1
Project Board January Update for Worcs Community
MH PAS Deployment Project
  • Steve Wormald, Chris Ashman

2
Agenda
  • Welcome
  • Review previous meeting minutes
  • Project Status Presentation
  • Current Status
  • Project Plan, Status
  • SDRC 3 Checklist Status Sign-off
  • Deployment Testing
  • Test Spec Approval
  • Hazzard Assessment
  • Risks and Issues
  • Change Management Update
  • Training Status
  • Communications
  • NHS Finance report
  • AOB
  • Conclusion

3
Current Status Cont/
  • Planned Activities for Period Date 01/02/05 to
    28/02/05
  • Environments
  • Preparation of End User Training Environment
    (Master) with (simulated RBAC)
  • Confirm allocation of Environments from Cluster ?
  • Test Extracts to Trust subset
  • Data Migration
  • Complete loading of the Local Reference Data
  • Migrate updated LRD to Environments Data
    Migration and End User Training using iConfig
    tool
  • Further testing of Full MPI data and activity
    data and Work through data issues.
  • Finalise Extracts for Daycare Group Sessions
  • Full Set Sample of File Extracts to be provided
    for testing
  • Training
  • Re-deliver Day Care training
  • Re-deliver Mental Health
  • Progress localisation of course content and
    complete Modules where possible
  • Complete Preparation of EUT (Master) 1st
    iteration (minus missing modules)
  • Provide clarity on SLAs for EUT Environments

4
Current Status Cont/
  • Planned Activities for Period Date 01/02/05 to
    28/02/05
  • SDRC2 Checklist
  • Agreed and Approved
  • SDRC 3 Checklist
  • Progress outstanding items to be completed by
    16/03/05
  • Business Change
  • Complete and circulate 1STDraft of Procedures and
    Guidlines Document for PCTs and MH for review and
    approval. Further iteration required
  • Complete and circulate 1st Draft of Targets
    Benefits Document for PCTs and MH review and
    approval, Final iteration available circulated
    for Approval 14th March for Project Approval.
  • Communications
  • Cascade messages to Users on the Project Status.
    Team briefs, Newsflash, etc.
  • Further cascading of Communications Briefings to
    Management to SWorcs planned for Jan.

5
Current Status Cont/
  • Planned Activities for Period Date 01/02/05 to
    28/02/05
  • Infrastructure
  • Commence deployment of New PCs and Upgrading
  • N3 installation of Circuits progressing
  • Security Registration Authentication (Smart
    Card)
  • Registration of Sponsors
  • Deliver Registration Schedule and notify Users of
    dates and venues
  • Deployment Testing
  • Work through plans, Roles and Responsibilities,
    localise Scripts
  • Issue Final draft of Test Spec for Approval
  • Set Up Test Room
  • Preparation for Testing Cycle 1 2 Informal
  • Support /Operational Readiness
  • Kick-Off Workstream Activities

6
Current Status Cont/
  • Achievements for this Period Date 01/02/05 to
    28/02/05
  • SDRC2 Checklist
  • Outstanding items completed
  • Business Change
  • Further Workshop conducted on Mental Health.
    Product run through and Assessments.
  • Project Board formally approved the Policies for
    PCTs and MH.
  • Agreement from JNCC on Policies for PCTs and MH.
  • Initial Go Live Users (Confirmed)
  • Completed and circulated 1STDraft of Procedures
    and Guidelines Document for PCTs and MH for
    review and approval (14th Feb).
  • Complete and circulate 1st Draft of Targets
    Benefits Document for PCTs and MH review and
    approval.

7
Current Status Cont/
  • Achievements for this Period Date 01/02/05 to
    28/02/05
  • Communications
  • Further cascading of Communications Briefings to
    Management at RB with further sessions being
    planned for Jan05 to SWorcs.
  • Environments
  • EUT Master Environment configured for Role Based
    Access
  • Unable to perform End to End test for Extracts.
  • Data Migration
  • Data (95.6) with NHS Numbers Less than 1,000
    Duplicates
  • Copied 2nd iteration of Local Reference Data
  • Further samples of MPI (100,00 records) performed
    and sample of Activity Data performed. Unable to
    perform clean run until Gaps in National Value
    tables and Prof Carers, Specialities etc are
    incorporated into Core Configuration (dependant
    upon availability of Core Config 9.1.1)

8
Current Status Cont/
  • Achievements this Period Date 01/02/05 to
    28/02/05
  • Training
  • Delivered Day Care and Mental Health to Trainers
  • Progressed localisation of course content
  • ADTs, Registrations and Referrals, Clinics, Case
    Load Management, Staff Dairies . Unable to
    progress Day Care
  • RBAC Roles defined and Set-Up on the EUT
    (Master).
  • Definitive list for Training finalised
  • Progressed preparation of Master on upgraded
    Environment
  • Infrastructure
  • Desktops for deployment commenced
  • N3 Acceptance of compromise agreement with BT. 3
    x N3 circuits installed with the exception of
    Redditch.

9
Current Status Cont/
  • Achievements this Period Date 01/02/05 to
    28/02/05
  • Security Registration Authentication (Smart
    Card)
  • Sponsors being Sponsored has commenced.
  • Initial Go Live Users being registered
  • Trusts progressing defining RBAC roles despite
    difficulties. Roles defined for Mental Health and
    Community ?

10
Current Status Cont/
  • Planned Activities for next Period Date 01/03/05
    to 31/03/05
  • SDRC 3 Checklist
  • Progress outstanding items to be completed by
    16/03/05 progressing
  • SDRC 4 Checklist
  • Progress items on Checklist
  • Business Change
  • Complete and circulate 1STDraft of Procedures and
    Guidlines Document for PCTs and MH for review and
    approval (14th Feb). Revised draft 28/02/05
  • Complete and circulate 1st Draft of Targets
    Benefits Document for PCTs and MH review and
    approval (14th Feb). Revised draft 05/03/05 and
    issue for Project Board Approval 14/03/2005
  • Communications
  • Cascade messages to Users on the Project Status.
    Team briefs, Newsflash, etc. Done
  • Further cascading of Communications Briefings to
    Management to SWorcs planned for Jan. Done

11
Current Status Cont/
  • Planned Activities for next Period Date 01/03/05
    to 31/03/05
  • Environments
  • Preparation of End User Training Environment
    (Master) with (simulated RBAC) 1st Iteration of
    Master released, further iterations to follow
    Staff Diaries and Day Care,
  • Confirm allocation of Environments from Cluster
    8 Environments available, notification to reduce
    to 5 from Cluster, refer to issue log
  • Test Extracts to Trust subset
  • Data Migration
  • Complete loading of the Local Reference Data
  • Migrate updated LRD to Environments Data
    Migration and End User Training
  • Further testing of activity data and Work through
    data issues.
  • Finalise Extracts for Daycare Group Sessions
    (Prepare for Full Go Live)
  • Full Set Extracts to be provided for testing
  • Training
  • Further assistance to be provided on Mental Act,
    by Product Specialist.
  • Complete Preparation of EUT (Master) 1st
    Iteration of Master released, further iterations
    to follow Staff Diaries and Day Care as
    localisation is completed.
  • Provide clarity on SLAs for EUT Environments.
    Meeting on the 2ND March (CCN to be approved by
    Cluster) Interim arrangement to be agreed.

12
Current Status Cont/
  • Planned Activities for next Period Date 01/03/05
    to 31/03/05
  • Infrastructure
  • Commence deployment of New PCs and Upgrading
    kick-off
  • N3 installation of Circuits progressing refer to
    issue
  • Security Registration Authentication (Smart
    Card)
  • Registration of Sponsors W/O 28/02/05
  • Deliver Registration Schedule and notify Users of
    dates and venues
  • Deployment Testing
  • Work through plans, Roles and Responsibilities,
    localise Scripts Completed
  • Issue Final draft of Test Spec for Approval
  • Set Up Test Room 02/03/05
  • Preparation for Testing Cycle 1 2 Informal
    Cycle 3 4 Informal
  • Complete testing
  • Support /Operational Readiness
  • Kick-Off Workstream Activities Kicked-off
  • Complete deployment verification document
  • Complete Volumetrics and issue draft for Approval

13
Project Plan
  • Project Status

14
SDRC Status
  • SDRC1
  • Formally Signed-off by Peter Jones Project
    Executive on behalf of the Project Board.
  • SDRC2
  • Formally Signed-off by Peter Jones Project
    Executive on behalf of the Project Board.
  • SDRC3
  • Presented to the Project Board for formal
    approval, on the following provisos
  • SDRC 3.01 Test Plan Agreed Final Draft presented
    for Project Board Approval is Signed-off
  • SDRC 3.07 Target Benefits Final Draft presented
    for Project Board Approval is Signed-off within 1
    Week.
  • SDRC 3.08 Benefits realisation tasks resourced
    and monitored. To be completed during SDRC 4.
  • SDRC4 Progressing

15
Top Issues
16
Top Issues Cont/
17
Top Issues Cont/
18
Top Risks Cont/
19
Top Risks Cont/
20
Top Risks Cont/
21
Top Risks Cont/
22
Conclusion
  • Agreement to continue to proceed
  • Agree Actions from Board meeting
  • Next Board Meeting Teusday the 12th of April 3pm
    to 5pm POWCH Conference Room Bromsgrove