Title: Planning and Scheduling Session 4


1
Planning and SchedulingSession 4
2
Review of Session 3
  • The bar chart is an effective way to show the
    schedule
  • The bar chart can show
  • Activity duration
  • Activity Start and Finish dates
  • Relationships between activities
  • A view of the entire project
  • Material submittals, approvals, and deliveries
    need to be scheduled on a procurement schedule or
    by other means.

3
Network Scheduling
  • Schedule produced from the relationships of
    activities
  • Network can be shown in a diagram
  • A Path is a group of activities linked together
    from one point to another
  • Paths can be a few activities or many activities

4
Path Illustration
5
The Critical Path
  • The longest path considering all of the
    dependencies and relationships
  • Any change to the duration of an activity on the
    Critical Path will impact the completion date of
    the project
  • The non-critical paths have float, a number of
    days that can be used in addition to the
    durations of the activities

6
Example Network Diagram
7
Bar Chart from Network Diagram
8
Forward Pass Calculations
9
Network with Forward Pass Calculations
10
Calculating the Backward Pass
11
Network Diagram With Early and Late Dates
12
Network Diagram Solution
13
Critical Path Solution
14
Group Activity Calculations
15
Calculating Lag
16
The Sure Fresh Project Network Diagram
17
The Sure Fresh Project Critical Path Solution
18
Review of Session 4
  • Network scheduling involves scheduling with
    activity relationships
  • Diagrams, showing paths, are often made in
    network scheduling
  • The critical path is calculated considering
    relationships
  • Float is indicated from the backward pass
    calculations

19
(No Transcript)