Title: Titles Line Up with the Starmark


1
Texas Choice Pilot Project November 2001
2
Texas Choice Pilot Project
TXU Contract Status as of 11-01-01
Contracted as of 11-01-01
Customer Class
5 Pilot Load
Residential Non-residential, non- demand
metered Industrial demand metered Commercial
and other demand metered Other
113,295 9,901 customers 183,054 kW 503,712
kW 151,196,500 kWh
50,753 customers 1,748 customers 107,682
kW 509,329 kW 81,651,078 kWh
3
Texas Choice Pilot Project
TXU Switch Status as of 11-01-01
Premises
Completed 26,998 Scheduled 7,251 Total
Switches 34,249 Contracted 57,371
60 of contracted have been scheduled or switched
4
Texas Choice Pilot Project
General Observations
  • Multiple Pilot delays in startup caused issues
    with system date issues and difficulty with
    changes
  • Market Participants ERCOT Databases will always
    have some level of discrepancies
  • 80-20 rule will apply resulting in special
    handling of exceptions
  • Transaction process timing is key to achieve
    desired transaction results

5
Texas Choice Pilot Project
Pilot Challenges
  • Transaction Starts and Stops
  • Requests to separate transaction types and send
    to special file sites
  • Volume Issues caused slow downs and data to be
    out of sync
  • Continual need to reconcile with ERCOT Market
    Participants
  • Notice period to request cancels and switchbacks
    caused delays and resulted in switches that
    should not have completed

6
Texas Choice Pilot Project
  • Weekly data reconciliation with ERCOT to ESI
    level
  • Lifecycle transaction tracking
  • Ongoing timing challenges with ERCOT processing
    of metering data
  • Contracted customers moved out while switches
    were pending and new customer moved in
  • Maintaining filenames is key to research and
    service requests, as well as, 997 confirmations

7
RETAIL QUALIFICATION TESTING (RQT)
8
RQT - Basis for Testing
Business Processes Tested
  • RQT is based on scenario maps defined by TX SET
  • Each scenario map represents many possible
    business process threads
  • RQT focuses on specific threads of the Scenarios
  • Each RQT script tests one or more scenarios

9
RQT - What is being testing?
Flight 1001
  • Basic switch - with objection invalid ESI ID
  • Move-Out - date change cancel
  • Move-In de-energized - rejected date change
  • CSA - move-in rejected drop date change
  • Drop to POLR
  • Ad Hoc Historical Usage
  • Service Orders - meter exchange, dis/reconnect
  • Usage/invoice/payment

10
RQT- Things to Remember
  • RQT does not assure a problem-free market
  • It is never too early to start planning for
    market testing
  • Use the Retail Testing Website as a resource
  • Successful RQT is required in order to execute
    TXUs delivery service agreement