Title: Titles Line Up with the Starmark
1TXU Load Schedule Performance- August 2001
May 1, 2002
2Summary and Key Points
- August 2001
- First month new market settlement systems were
used - Initial estimates of load imbalance were
significantly overstated - TXUs load forecast performance was appropriate,
given conditions known at the time - The magnitude of load energy imbalance does not
correlate with the magnitude of the Balancing
Energy Neutrality Adjustment (BENA) - TXU Electric was regulated, and therefore costs
and credits incurred in ERCOT settlements were
reflected in TXU Electrics fuel balance - The method of allocating congestion costs that
led to BENA charges in August has now been
changed
2
3Reliability is Job 1
- Some things dont change In the new competitive
market, as in the former regulated environment,
reliability is the No. 1 concern - Utilities in Texas have a long history and
tradition of providing reliable service TXU
Electric was a regulated utility in August 2001 - In the summer of 2001, the ability to keep the
lights on was the first priority - Because of tight supplies in 1999-2000, the PUC
sought repeated assurances - California blackouts raised the issue in the
public mind - Pilot project, move to single control area
highlighted concerns - TXU scheduled its power needs appropriately to
ensure adequate supplies to meet summer peak
loads, based on the best information available at
the time
3
4August 2001 First Month of New Era
- Step change in market operation rather than
incremental change - Load forecasting became more difficult
- Change in control area operators. TXU Electric
no longer managed supply and demand in real time - Customer load scheduled for 96 intervals and by
congestion zones for first time - Communication of deemed actual customer meter
data is delayed by 45 days - New data systems were developed and implemented
at pilot opening to estimate total customer load - Historically, day-ahead peak load forecasting
variance has been about 3. The variance in
August for all hours averaged 5
4
5Initial estimates of load scheduling
imbalance were significantly overstated and were
ultimately corrected in the true-up settlement
TXUs load schedules averaged only about 5 over
actual load
5
6TXU Electric August Daily Load Schedule Energy
Variance
6
7TXU Electric August 11 - High Load Schedule
Energy Variance
7
8TXU Electric August 17 - High Load Schedule
Energy Variance
8
9TXU Electric August 27 - High Load Schedule
Energy Variance
9
10TXU Electric August Daily Settlements for BENA,
Resource and Load Imbalance
10
11August 14 - TXU Electric BENA Charges
11
12August 15 - TXU Electric BENA Charges
12
13August 22 - TXU Electric BENA Charges
13
14TXU Electric was a regulated utility in August
and therefore 90 of the profits from off-system
sales impacted regulated fuel expenses Customer
fuel expense for August 2001 was reduced by 14.2
due to the net impact of BENA payments and
credits from load imbalances and resource
imbalances
- BENA charges from ERCOT (expense). 34.0
million - Load Imbalance (credit). - 22.0
million - Resource Imbalance (credit).... - 26.2
million - NET REDUCTION IN RECONCILABLE FUEL 14.2
million
PUC rules allow utilities to share in profits
from off-system sales (resource imbalances
payments) with customers receiving 90 of the
proceeds. TXU received 2.9 million in August.
However, at ERCOT true-up settlement completed in
March 2002, changes in BENA, load imbalance and
resource imbalance resulted in an additional
charge of 3.0 million.
14
15Congestion Cost Allocation Protocol Has Changed
- In August 2001, congestion costs were allocated
on a pro rata share of customer load - This allocation method was adopted as an interim
solution - Allowed all participants to purchase supplies in
ERCOT without regard to congestion - Costs of clearing congestion were primarily paid
through BENA charges - Allocation methodology changed in February 2002
- Market participants began work on new rules in
September 2001. - Participants are now directly assigned the
congestion costs they create - BENA, although still used as a charge type, no
longer covers congestion costs and is quite small
15
16Summary and Key Points
- August 2001 was the first month of the new
competitive market and the first month that new
market settlement systems were used. - Although load forecasting was more difficult in
the new market, TXUs performance was appropriate
to ensure reliability and the lowest reasonable
cost. - During August, TXU Electric did not believe that
the initial ERCOT settlement data provided a
basis for changing load forecasts - TXU Electric was regulated, and therefore did not
earn excess profits in August 2001. - The method of allocating congestion costs in
August has now been changed to ensure that only
participants who create congestion pay the costs.
- The market was not harmed by the actions of TXU
Electric TXU Electrics generators would likely
have received market clearing prices as a
resource imbalance, in lieu of load imbalance
payments, if actual load had equaled forecasted
load.
16