Soil Improvement and Ground Modification - PowerPoint PPT Presentation

1 / 49
About This Presentation
Title:

Soil Improvement and Ground Modification

Description:

UNIVERSITI MALAYSIA PAHANG Department of Civil and Environmental Engineering ... shown the improvement of the hydraulic backfill and has confirmed this ... – PowerPoint PPT presentation

Number of Views:7984
Avg rating:3.0/5.0
Slides: 50
Provided by: Owne8
Category:

less

Transcript and Presenter's Notes

Title: Soil Improvement and Ground Modification


1
UNIVERSITI MALAYSIA PAHANG Department of Civil
and Environmental Engineering
  • Chapter 4-1
  • Soil Improvement and Ground Modification

Muzamir bin Hasan, M.Eng. Lecturer
2
Introduction
  • The existing soil at a construction site may not
    always be totally suitable for supporting
    structures.
  • For example, granular soil may be very loose and
    indicate large elastic settlement. So the soil
    needs to be densified to increase its unit weight
    and thus shear strength.

3
Introduction
  • Sometimes the top layer of the soil are
    undesirable and must be removed and replaced with
    better soil.
  • Soft saturated clay layers are often encountered
    at shallow depths below foundation large
    consolidation may occur.

4
Introduction
  • Various tecniques for improving soil are used-
  • Reduce the settlement of structures.
  • Improve the shear strength of soil and thus
    increase the bearing capacity of shallow
    foundations.
  • Increase the factor of safety against possible
    slope failure of embankments and earth dams.
  • Reduce the shrinkage and swelling of soils.

5
Introduction
  • If unsuitable soil conditions are encountered at
    the site, one of the following 4 procedures may
    be adopted to ensure satisfactory performance of
    the structure (Mitchell, 1976)
  • Bypass the unsuitable soil by means of deep
    foundations extending to a suitable bearing
    material.
  • Redesign the structure and its foundations for
    support by the poor soil, a procedure that may
    not be either feasible or economical.
  • Remove the poor material and either treat it to
    improve and replace it, or substitute it by a
    suitable material.
  • Treat the soil in place to improve its properties.

6
Improvement Techniques
  • The factors that must be considered in the
    selection of the best technique in any case
    include the following (Mitchell, 1976)
  • Soil type sand, clay, organic, etc.
  • Area and depth of treatment required depend on
    the geometric characteristics of the soil deposit
    and load distribution.
  • Type of structure and load distribution.
  • Soil properties strength, compressibility,
    permeability, etc.

7
Improvement Techniques
  • Permissible total and differential settlements.
  • Material availability stone, sand, water,
    admixture, stabilizers, etc.
  • Availability of skills and equipment.
  • Environmental considerations waste disposals,
    erosion, water pollution, etc.
  • Local experience and preferences.
  • Economics.

8
Compaction
  • If a small amount of water us added to a soil
    that is then compacted, the soil will have a
    certain unit weight.
  • If the moisture content of the same soil is
    gradually increased and the energy of compaction
    is the same, the dry unit weight of the soil will
    gradually increase.
  • The reason is that water acts as a lubricant
    between the soil particles, and under compaction
    it helps rearrange the solid particles into a
    denser state.

9
Compaction
  • The standard lab test-
  • Standard Proctor test (ASTM designation D-698)
  • Modified Proctor test (ASTM designation D-1557

10
Compaction
11
Compaction
12
Compaction
  • Compaction in the field depends on several
    factors, such as-
  • Type of compactor
  • Soil type
  • Moisture content
  • Lift Thickness
  • Towing speed of the compactor
  • The number of the roller passes

13
Field Compaction
  • Ordinary compaction in the fields is done by
    rollers.
  • Of the several types of roller used, the most
    common are-
  • Smooth wheel roll
  • Pneumatic rubber-tired rollers
  • Sheepsfoot rollers
  • Vibratory rollers

14
Field Compaction
15
Field Compaction
16
Field Compaction
17
Smooth Wheel Roller
  • Can create vertical vibration during compaction.
  • Suitable for proof-rolling subgrades and for
    finishing the construction of fills with sandy or
    clayey soils.
  • Provide 100 coverage under the wheels, and the
    contact pressure can be as high as 300-400kN/m2.
  • However, they do not produce uniform unit weight
    of compaction when used on thick layers.

18
Smooth Wheel Roller
19
Smooth Wheel Roller
20
Smooth Wheel Roller
21
Smooth Wheel Roller
22
Smooth Wheel Roller
23
Pneumatic Rubber-Tired Rollers
  • Better in many respects than smooth wheel
    rollers.
  • May weight as much as 2000 kN, consist of a
    heavily loaded wagon with several rows of tires.
  • These tires are closely spaced four to six in a
    row.
  • The contact pressure under the tires may range up
    to 600-700kN/m2, and they produce about 70-80
    coverage.
  • Can be used for sandy and clayey soil compaction,
    produce a combination of pressure and kneading
    action.

24
Hamm Model GRW 18 Rubber Tired (Pneumatic)
Roller
25
Pneumatic Rubber-Tired Rollers
26
Sheepsfoot Rollers
  • Consist basically of drums with large numbers of
    projections.
  • The area of each of the projections may be 25-90
    cm2.
  • Most effective in compacting cohesive soils.
  • The contact pressure under the projections may
    range from 1500-7500 kN/m2.
  • During compaction in the field, the initial
    passes compact the lower portion of a lift.
  • Later, the middle and top of the lift are
    compacted.

27
Sheepsfoot Rollers
28
Vibratory Rollers
  • Efficient in compacting granular soils.
  • Vibrators can be attached to smooth wheel,
    pneumatic rubber-tired, or sheepsfoot rollers to
    send vibrations into the soil being compacted.

29
Dynamic Compaction
  • Is a technique that is beginning to gain
    popularity in United States for densification of
    granular soil deposits.
  • This process primarily involves dropping a heavy
    weight repeatedly on the ground at regular
    intervals.
  • The weight of the hammer used varies from 8-35
    metric tons and the height of the hammer drop
    varies between 7.5 and 30.5 m. The stress waves
    generated by the hammer drops help in the
    densification.

30
Dynamic Compaction
  • The degree of compaction achieved depends on
    the-
  • a) weight of the hammer
  • b) height of the hammer
  • c) spacing of the locations at which the hammer
    is dropped

31
Dynamic Compaction
  • Densification by dynamic compaction is performed
    by dropping a heavy weight of steel or concrete
    in a grid pattern from heights of 30 to 100 ft.
    It provides an economical way of improving soil
    for mitigation of liquefaction hazards.
  • Local liquefaction can be initiated beneath the
    drop point making it easier for the sand grains
    to densify. When the excess pore water pressure
    from the dynamic loading dissipates, additional
    densification occurs.
  • As illustrated in the photograph, however, the
    process is somewhat invasive the surface of the
    soil may require shallow compaction with possible
    addition of granular fill following dynamic
    compaction.

32
Dynamic Compaction
33
Dynamic Compaction
34
  • Techniques Dynamic compaction
  • The dynamic compaction technique is used to
    densify the ground to great depths thanks to the
    creation of very high energy waves. The technique
    was invented and developped by Mr. Louis MENARD
    and MENARD .

Source www.menard-soltraitement.com/
35
  • It requires the use of pounders weighing 15 to 40
    tons released in free fall from a height of 10 to
    40 meters. The arrangement of the impact points
    and the other parameters of the treatment
    (energies, phasing, rest periods) depend on the
    characteristics of the soil to be treated and on
    the results of the trial zone. This ground
    treatment process is used for the foundations of
    buildings, or to stabilise large areas of
    embankment work or loose soil.

Source www.menard-soltraitement.com/
36
  • Saint-Etienne Industrial and Business Park
  • The site is an old mining discovery zone filled
    in over around sixty meters deep. A total
    surface of six hectares are foreseen as building
    area. The settlements monitored over a six month
    period thanks to 21 measuring points ranged from
    5 to 43 cm.

Source www.menard-soltraitement.com/
37
  • The ground improvement solution chosen was deep
    dynamic compaction with an energy of 700 t.m,
    combined with standard 300 t.m compaction The
    soil characteristics of the worst zone were as
    follows up to 12 meters deep 0.37 MPa lt Pl-Po
    lt 0.86 MPa 3.0 MPa lt Ep lt 8.8 MPa

Source www.menard-soltraitement.com/
38
Vibroflotation
  • Is a technique developed in Germany in 1930s for
    in-situ densification of thick layers of loose
    granular soil deposits.
  • The process involves the use of a vibroflot
    (called vibrating unit), which is about 2 m in
    length.
  • The vibrating unit has an eccentric weight inside
    it and can develop a centrifugal force.

39
Vibroflotation
  • The weight enables the vibrating unit to vibrate
    horizontally.
  • There are openings at the bottom and top of the
    vibrating unit for water jets.
  • The vibrating unit is attached to a follow up
    pipe.

40
Vibroflotation
  • Vibroflotation involves the use of a vibrating
    probe that can penetrate granular soil to depths
    of over 100 feet. The vibrations of the probe
    cause the grain structure to collapse thereby
    densifying the soil surrounding the probe. To
    treat an area of potentially liquefiable soil,
    the vibroflot is raised and lowered in a grid
    pattern. Vibro Replacement is a combination of
    vibroflotation with a gravel backfill resulting
    in stone columns, which not only increases the
    amount of densificton, but provides a degree of
    reinforcement and a potentially effective means
    of drainage.

41
Vibroflotation
42
Vibroflotation
43
Vibroflotation
  • The entire compaction process can be divided into
    4 stages-
  • The jet at the bottom of the vibroflot is turned
    on, and the vibroflot is lowered into the ground.
  • The water jet creates a quick condition in the
    soil, which allows the vibrating unit to sink.
  • Granular material is poured into the top of the
    hole. The water from the lower jet is transferred
    to the jet at the top of the vibrating unit. This
    water carries the granular material down the
    hole.
  • The vibrating unit is gradually raised in about
    0.3 m lifts and held vibrating for about 30
    seconds at a time. This process compacts the soil
    to the desired unit weight.

44
Vibroflotation
  • The capacity of successful densification of in
    situ soil depends on several factors, the most
    important of which is the grain-size distribution
    of the soil and also the nature of the backfill
    used to fill the holes during the withdrawal
    period of the vibroflot.

45
Vibroflotation
46
  • Techniques Vibroflotation
  • The compaction of a loose soil or a loose
    backfill can be achieved at high depth by
    penetration of a vibrator. In granular soils,
    this penetration results in a liquefaction of the
    surrounding soil and a quasi immediate
    settlement. Further to the results of a trial
    zone, Menard defines - the vibrator frequency
    - the power of the vibrator - the requested
    period of vibration for each different soil layer

Source www.menard-soltraitement.com/
47
  • PASIR PAJANG CONTAINER TERMINAL (Singapore)
  • In 1996, Menard was awarded the soil improvement
    works of a reclamation area made of hydraulic
    fill on a depth of about 10 m. The aim of this
    soil improvement was to densify the hydraulic
    backfill, increase the bearing capacity and
    reduce the liquefaction potential.

Source www.menard-soltraitement.com/
48
  • The technical solution adopted by Menard was a
    combined treatment made of dynamic compaction for
    the first 5 m and vibroflotation for the layer 5
    to 10 m. The acceptance criteria defined by the
    client was a value of qc higher than 15 MPa over
    the 10 m to be densified. A geotechnical campaign
    made of 46 CPTs before the works and 60 CPTs
    after the works has shown the improvement of the
    hydraulic backfill and has confirmed this
    acceptance criteria. .

Source www.menard-soltraitement.com/
49
Source www.menard-soltraitement.com/
Write a Comment
User Comments (0)
About PowerShow.com