DO Readout Timeline Split Silicon V2.0

Description:

Fabricate/test CFT digital boards. Install/test calorimeter shapers. Fabricate/test Muon Fanout Cards. Muon SFE & SRC complete. Final installation of Level 3/DAQ ... – PowerPoint PPT presentation

Number of Views:123
Avg rating:3.0/5.0
Slides: 2
Provided by: Jonathan5
Category:

less

Transcript and Presenter's Notes

Title: DO Readout Timeline Split Silicon V2.0


1
DO Readout TimelineSplit Silicon V2.0
Fiber TrackerSiliconForward MuonCalorimeterOve
rall InstallationTrigger
2000
2001



M A M J J A
S O N D J F M



Install N S trusses in Collision Hall
Roll detector into Collision Hall
Remove shield wall
Platform moves, returns east
North
South
CFT install align
CFT hookup
Detector Hooked Up
Install VLPC cassettes
1st CFT crate operational
Fabricate/test 12-chip CFT analog FE boards
Fabricate/test 8-chip CFT analog FE boards
Run II begins
CFT mixer boards available
Fabricate/test CFT digital boards
Install/test calorimeter shapers
1st CAL quadrant available
Install/commission silicon front-end (sequencers,
VRB)
Install/hookup/checkout SMT
Low mass cables procured
Commission Level 1 Trigger (CAL, Muon, CTT/PS)
Produce/test SMT interface cards
Final installation of Level 3/DAQ
Muon SFE SRC complete
Commission Level 2 (CAL, Muon, CTT/PS)
Fabricate/test Muon Fanout Cards
Install C- and B-layer MDTs pixels
Detector Hookup/Commissioning
Phase III
Cosmic Ray Commissioning Tracker Muon Systems,
Cosmic Triggering
Phase I Central Muon, DAQ, RECO, Trigger
Phase II
Tracker Hookup (CFT, SMT, PS), VLPCs, Trigger,
Forward Muon