Title: Project Management Workshop
1Project Management Workshop
By Jonathan W. Powell, CGFM, PMP
2Agenda
- 'Cost world' perspective
- 'Throughput world' perspective
- Three mechanisms to add 'safety' to projects
- Three mechanisms that waste project 'safety'
- Critical chain analysis to ensure project success
3(No Transcript)
4The Problem
Product Life Cycle
5The Problem (Cont.)
- Development time of 2 years
- New generation of modems every 6 months
- Not are we going to miss but when?
- Huge ramifications
- Miss completely
- Launch inferior product
- Launch good product late
6The Problem (Cont.)
- Genemodem decides to form a think tank
- Three managers (Finance, Engineering, Marketing)
- No budget restrictions
- Mission Find a way to drastically cut
development time
7Solving the Problem
8Answer 1 Cost World Perspective
- Cost World Perspective Driving local
efficiencies - What this fails to account for is the linkage
between dependent steps - Using the analogy of a chain -
It Depends! Which One is the Weakest Link?
9Answer 2 Throughput World Perspective
- Throughput World Perspective Driving production
output - Managing by both the Cost World and Throughput
World causes irreconcilable conflict
10Theory of Constraints Analysis
- Four Step Process
- 1. Identify the Systems Constraint
- Find the weakest link!
- Could be physical or it could be something like
an erroneous policy - 2. Strengthen the Weakest Link
- Adding more capacity
- Hire more people or buy more machines
- Squeeze the maximum from the capacity we already
have
11Theory of Constraints Analysis (cont.)
- Four Step Process (cont.)
- 3. Subordinate Everything to the Systems
Constraint - If the bottleneck can only do 3 units/hour, dont
demand 5 units/hour! - If 3 units/hour is unacceptable then revisit Step
2 - 4. Elevate the Systems Constraint
- Strengthening the weakest link to the point where
it is no longer the weakest link - Repeat the four steps based on the new weakest
link
12Project Management Application
- Step 1 Identify the Constraint
- The constraint for a particular project is its
critical path Delays to the critical path delay
the project as a whole - Step 2 Strengthen the Constraint
- The question We want to strengthen the
constraint the critical path How do we do
this?
13The Concept of Safety
- Safety The difference between the median of the
probability distribution and the actual estimate - Typical for people to provide estimates that give
them over an 80 chance of success - However, probabilities of 80 or more yield
safeties of 200 or better - Three (3) common ways safety is added to a project
14Three Common Ways to Add Safety
- Time estimates are based on pessimistic
experience - Larger number of management levels involved
higher total estimation, because each level adds
its own safety factor - Estimators also protect their estimates from a
global cut
15Three Common Ways to Waste Safety
- Students Syndrome first fight for safety time,
then wait until the last minute anyway - Multitasking
16Three Common Ways to Waste Safety (cont.)
- Reluctance to report an Early Finish
17Project Management Application (Cont.)
- Step 2 Strengthen the Constraint
- Example Project, Four Steps of Varying Length
(all on the critical path)
18Project Management Application (Cont.)
- Step 3 Subordinate Everything to the Constraint
- Develop feeding buffers for tasks that feed into
the critical path - Provide resource buffers eliminate negative
impact of multitasking
19Pulling Together the Pieces
20Project Management Application (Cont.)
- Step 4 Elevate the Systems Constraint
- During the natural progression of a project, the
critical path may change one or more times - A critical path change means that your constraint
has changed - Determine the new constraint and re-perform
four-step analysis - Also, organizations may be performing many
projects - The same resource may be needed to perform
critical path tasks on different projects - The dependencies between the critical path tasks
of the various projects is called the Critical
Chain
21Conclusion
- 'Cost world' perspective
- 'Throughput world' perspective
- Three mechanisms to add 'safety' to projects
- Three mechanisms that waste project 'safety'
- Critical chain analysis to ensure project
success
22Credits and Contact Info
- www.eligoldratt.com
- Jonathan Powell, CGFM, PMP
- jwpowell_at_us.ibm.com
- 240-715-3926