Title: Information on Key Projects
1Information on Key Projects
- Edward Farquharson
- 12 December 2006
2Deliverability Framework
- Policy/Rationale
- Economic/policy justification
- Viability
- Technically, contractually, environmentally,
socially viable - Supporting infrastructure available/interfaces
work/dependencies - Bankability
- Contractor interest
- Market Capacity
- Financing terms and conditions can be met
- Credit issues
3Deliverability Framework
- Affordability
- Power affordable for end user taking into account
capex, opex, cost of finance, term of
contract/tenor - Deliverability
- Owner has capacity to manage process
- Legislation/vires in place/acceptable
- Statutory approvals/permits in place
- Timescales
- Stakeholders
4Rehabilitation and Expansion Projects
5Rehabilitation/Expansion Projects Key Issues
- Policy objectives/Rationale
- Solution to existing underperforming/poorly
maintained facilities, but more complex if
financing is required. - Viability
- Operation
- Can be complex due to historical working
practises. - Transfer of existing staff.
- Capex costs
- Environmental investment costs
- Unforeseen capex costs
- Latent defects
- Legacy liabilities
- Warranties
6Rehabilitation/Expansion Projects Key Issues
contd
- Bankability
- Ownership
- Lenders will not permit splitting electricity
sales from old capacity and new - gt ownership of the whole plant must transfer
to the newly financed entity - gt may provide for a capital receipt which can
be used to enhance credit quality - Liability
- Transfer of existing assets requires satisfactory
indemnities in respect of historical liabilities,
maintenance shortfalls etc. - Affordability
- Affordability to end consumer allowing for capex
and OM costs. - Deliverability
- Owner capacity to manage process.
- PPA
7Kariba North Bank Extension
- Location Zambia
- Project Type 360MW Hydropower expansion
- Estimated Capital Cost 300m
- Feasibility Study Completed in 2005 by Sinohydro.
- PPA with ZESCO yet to be developed.
- ZESCO structure of credit support for ZESCO
obligations yet to be developed. - Ownership of extended facility to be determined.
- Good potential structuring possibilities around
ZESCO onward power sales, natural resource
companies and stable environment.
8Hwange
- Location Zimbabwe
- Project Type Thermal project rehabilitation and
expansion from 320MW to 780MW - Estimated Capital Cost 500m
- PPA to be structured with ZESA. Terms to be
agreed. - ZESA credit support for long term obligations to
be agreed. - Fuel supply to come from Hwange Colliery operated
by ZESA Joint Venture. Terms not yet agreed. - Feasibility study required for colliery expansion
in order to supply project est. capital cost
30m. Financing availability not yet determined. - Transmission lines to Namibia for onward sales
require refurbishment, estimated capital cost
20m.
9Hydropower Projects
10Hydropower Projects - Key Issues
- Policy objectives/rationale
- Significant underutilised natural resources by
way of river flows. - Attractive fundamentals in era of high/volatile
oil and gas prices. - Low technical risk (once built).
- Clean energy/Renewable.
- Viability
- Location
- Logistics construction projects requiring mass
mobilisation of equipment and manpower in remote
locations. - Significant accompanying infrastructure
requirements roads, transmission etc. - Interface risk availability, timing, costing.
- Specific Risks
- Geotechnical history of construction time and
cost overruns EPC rare. - Climate rain volume and regularity, water flow,
historic data availability.
11Hydropower Projects - Key Issues contd
- Viability contd
- Social/environmental
- NGOs
- Permitting
- EIA scope certainty.
- Resettlement
- Regulation
- clarity, structure, completeness, long term
stability. - water use rules.
- Timing
- Significant development, mobilisation and
construction lead times.
12Hydropower Projects Key Issues contd
- Bankability
- Long development and construction lead time so
significant interest roll up challenge. - Economics require long tenor debt unavailable in
commercial markets. - Availability of multilateral funding enhancement
mechanisms. - Sensitivity of lenders and investors to
environmental issues. - Foreign exchange and interest rate exposure.
- Bankability of owner group (if applicable).
- Bankability of contractor group.
- PPA terms.
- Long term bankability of PPA and off-taker.
- PRI cover availability.
- Arbitration/dispute resolution mechanisms.
13Hydropower Projects Key Issues contd
- Affordability
- Affordability to end consumer dependent on
potentially uncertain capex and yet to be defined
finance terms and costs, especially debt
maturity. - Deliverability
- Government project team authority, budget,
experience. - Availability and suitability of advisers.
- Bidding and evaluation rules and capacity in
place, transparency. - Scope boundaries.
14Inga 1 and 2
- Location Democratic Republic of Congo
- Project Type Hydropower rehabilitation 1775MW
- Estimated Capital Cost 600m
- PPA with SNEL to be developed. Terms yet to be
agreed. - Existing scope of MOU between SNEL and Magenergy
unclear. - Tender process for remaining units to be
clarified. - Ownership post rehabilitation currently believed
to remain with SNEL. - SNEL onward sales to neighbouring utilities to
be developed. - Transmission line capital costs estimate unclear.
15OMVG
- Location Guinea
- Project Type Hydropower new builds 368MW
- Estimated Capital Cost Kaleta 190m
Sambangolou 300m - PPA with Senegal, Gambia and Guinea-Bissau
DistCos to be developed. Terms yet to be agreed. - Tender process due to be launched in Jan 2007.
- Priority project of West African Energy Exchange
(EEEOA) and CEDEA. - Related transmission line of 1,677 km through
four countries (West African Loop) at estimated
cost of 385m to be developed.
16Kafue Gorge (Lower)
- Location Zambia
- Project Type 750MW Hydropower new build
- Estimated Capital Cost 600m
- PPA with ZESCO to be developed. Terms to be
agreed. Onward sales to Nampower being finalised. - ZESCO credit support in respect of long term
obligations yet to be agreed. - Appetite of natural resource companies for power
to be explored. - Feasibility study required for conjunctive
operation of plants on Zambezi to be completed. - Tender status unclear. Status of a Chinese or
Indian MOU unclear.
17Thermal Power Projects
18Key Issues Thermal Power Projects
- Policy objectives/Rationale
- Proven technologies, good investor appetite,
flexibility of placement near demand, speed of
implementation. - Viability
- Standardized/modular design and build approaches
reduced capex and time. - Power Purchase Agreement.
- Well understood, but term of contract and credit
worthiness of offtaker critical. - Security of fuel supply.
- Current oil and gas prices challenge
competitiveness of new build in developing world. - De-risking any currency mismatch between fuel
payments, power sales and debt repayments
critical. - Proximity to mines, if coal fired
(availability/quality).
19Key Issues Thermal Power Projects contd
- Bankability
- Well established financing structures.
- Relatively short construction times.
- EPC contracts.
- Deep and liquid market for debt placement
(country risk dependent). - Proven investor appetite and established
benchmarks for risk. - Affordability
- Exposure to volatility in delivered fuel supply
costs. - Shorter construction periods and lower capex
component reduce impact of finance terms. - Deliverability
- Planning, emissions, noise levels, environmental
permits. - Emissions.
20Kudu
- Location Namibia
- Project Type 800MW Gas fired new build
- Estimated Capital Cost 530m
- Plant size developed due to economics of fuel
supply, Namibia demand some 80MW. - PPA with Nampower to be developed dependent on
ESKOM sales. - Fuel supply from Kudu gas field, timing and price
to be agreed. Field operator still to finalise
commercial terms. - Transmission line status to ESKOM to be
clarified. - Prioritisation by Nampower to be confirmed.
21Transmission Line Projects
22Key Issues Transmission Projects
- Policy objectives/Rationale
- Need to move power across regions due to
hydropower focus, or need to oversize capacity to
underpin fuel field development e.g. Kudu. - Requirement for strong government support to
ensure viability. - Viability
- Physical security of assets over large distances
is problematic affordable insurance package will
be key. - Bankability
- Is there a role for private sector capital? Is it
an interesting asset class? - What sort of return is appropriate for a low risk
business in a higher risk environment? - Cross border sovereign issues?
- PPAs require structuring similar to tolling
agreements. - Financial viability of customer.
23Transmission Projects Key Issues contd
- Affordability
- Interdependency with supply and distribution.
- Line capacity.
- Deliverability
- Capacity of transnational groups.
- Way leaves/land acquisition existing routes?
- Differing legislation, permits.
- Tariff policy.
24Malawi-Mozambique Transmission Line
- Location Malawi-Mozambique
- Project Type Regional transmission
- Estimated Capital Cost 84m
- Complex PPA structure to be finalised, sale from
HCB to Malawi ESCOM wheeled through EDM. - Feasibility study status to be confirmed.
- Prioritisation of host governments to be
confirmed. - World Bank commitment in principle for 62m,
terms to be clarified.
25Zambia-Tanzania-Kenya Transmission
- Location Zambia-Tanzania-Kenya
- Project Type Regional Transmission
- Estimated Capital Cost 342m
- Nairobi (Kenya) - Arusha (Tanzania) to be public
sector funded. - Arusha (Tanzania)-Dar es Salaam public sector.
- Dar es Salaam - Zambia link funding not yet
identified. - Feasibility study underway by Norplan A.S., due
to complete in 2007. - PPA structure for sales to TANESCO/KPLC to be
finalised.