proposed for May 1-2 June 6-7? Status report to DOE/NSF. in Washington May 30. DOE/NSF review ... software QA/QC: regression testing, bug tracking, version control ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 16
Provided by: cms5
Learn more at: https://uscms.org
Category:

less

Transcript and Presenter's Notes

Title: PMG 20010321 Lothar A T Bauerdick, Fermilab1


1
U.S. CMS S/C PMG March 21, 2001
  • Agenda
  • Overall Project Status Lothar A T Bauerdick
  • CAS Status Ian Fisk
  • UF Status Vivian ODell
  • U.S. CMS Software and Computing Calendar
  • US LHC Common Projects
  • report to DOE and NSF March 30
  • meeting at Fermilab May 8-9
  • Blucher SCOP Review
  • proposed for May 1-2 gt June 6-7?
  • Status report to DOE/NSF
  • in Washington May 30
  • DOE/NSF review
  • CMS and ATLAS at Fermilab Oct 9-12

2
U.S. LHC Common S/C Projects
  • Very productive first meeting end of January at
    CERN
  • Starting Working Groups with WG chairscharged to
    write up activities and technical goals
  • Facilities and Computer RD (ODell, Baker)
  • Network Infrastructure (Newman, Gardner)
  • Distributed Data Management and Processing
    (Avery, Shank)
  • Database Evaluation (Bunn, Wenaus)
  • Software Environments and Tools, Analysis
    Infrastructure (Fisk, Tull)
  • Common Project Oversight (Bauerdick, Huth)
  • Facilities People will start quarterly Workshops
    (BNL, Fermi, ev. Tier2)
  • sharing UF experience in hardware/vendors/OS and
    system administration
  • Computing hardware RD
  • Computer hardware cost tracking, vendor relations
  • System administration, Networking
  • System monitoring and performance tools
  • First Facilities Workshop March 2830, hosted at
    BNL
  • Next Common Projects Meeting May 8-9 at Fermilab

3
Status Report FY2001Q1
  • 1st quarterly report sent out Feb 20 to
  • US LHC Project Office, PMG and US CMS
  • Report on Technical Status/Progress
  • UF detailed effort reports along WBS (see
    V.ODell)
  • CAS will use CAS engineers regular reporting
    (see I.Fisk)
  • Report on Performance and Financial Status
  • Cannot measure schedule performance in earned
    value
  • Experience on labor costs cannot readily be
    extrapolated
  • CCS Tasks and Deliverables Document coming up gt
    see I.Fisks talk
  • Will allow us to better define milestones and
    deliverables for US CAS WBS

4
Status Report FY2001Q1
  • Effort on User Facilities
  • determined bottom up gt see Vivian ODells
    presentation

2.5 FTE Tier2Personnel (NSF)!
5
Funding Status Feb (and March) 2001
  • Funding StatusFunding Sources Expected
    and Received

6
Re-Organization of CMS Computing
  • CMS Core Computing and Software now part of CPT
    project
  • Addresses cross-project nature of key
    deliverables
  • Recognizes cross-project groups and task forces

7
CCS Management Structure
  • Core Computing and Software Management Structure
  • Responsible for MOU deliverables Tier 0/1/2
    centers, core software
  • PMs, RM, TC six Level2 tasks w/ managers
    assigned for 1 year
  • Presented to SCB/CIB, MB, CB gt approved CIB
    will need constitution e.g.
    representation of RCs

Task Breakdownto Level3
8
Hoffmann Review Report Released
  • Report of the Steering Group of the LHC
    Computing Review
  • Multi-Tiered computing model adopted
  • Total costs T0-T2 h/w 240 MCHF, CERN T0T1 is 1/3
  • network at T1 is 1.5-3Gbps/exp
  • Data Challenges and h/w prototypes
  • to be launched in 2001, reach 50 complexity in
    2004
  • Deployment of initial system 2005-7 in equal cost
    proportions
  • MO rolling replacement w/ constant budget of
    yearly 1/3 of initial investment
  • Personnel of experiments and CERN IT
  • Core Software teams seriously understaffed,
  • staff reduction at CERN IT incompatible with
    mission
  • SC2 committee
  • highest level s/c management from experiments,
    CERN/IT and RC
  • Technical Assessment Groups
  • MOUs
  • funding/responsibilities for h/w, s/w, human
    resources, policies for access
  • Interim MOUs or software agreements by end of
    2001 to ensure s/w development

9
Interim MOU for CMS CCS
  • CMS is preparing for interim MOUs on Computing
    and Core Software
  • Full MOU would be premature
  • CMS and (most) funding agencies not ready
  • Milestone Software and Physics TDRs
  • Interim MOU
  • Get Hoffmann Panel recommendations approved by
    the RRB
  • Address manpower problems for CAS
  • Expose computing plans and get agencies to
    formally take note
  • agreement in principle
  • Fund the prototyping phase
  • Caveat Numbers will change
  • Effort to get ready for April RRB
  • Task breakdown for CMS CCS gt tasks,
    deliverables, FTEs
  • Computing numbers from Hoffmann Panel
  • Sizing for T0, T1, T2, for prototypes and for
    production system
  • Costs and budget for prototyping phase (CERN 12M
    CHF)

10
MOUs and SOWs w/ U.S. Institutions
  • The Project is committed to follow management
    and budget procedures as established in U.S.
    CMS for the construction project
  • Project file with all effort put in, identified
    by WBS number
  • MOUs and SOWs with participating institutes
  • Institutes account and invoice all expenditure by
    WBS number to PO
  • Project Manager signs off invoices, then the
    money flows
  • Work needed to bring the WBS to a state to
    support the procedures
  • Working with Caltech and UC San Diego (prototype
    Tier2 sites)on SOWs and MOUs to the effort and
    procedures

11
Progress on Prototype Tier2
  • Started Process of defining MOUs and SOWs with
    Caltech and UCSD
  • Meeting at Caltech Feb 23 to work on SOW, agreed
    on procedure
  • Working now on fleshing out the WBS
  • Define effort, tasks, milestones and deliverables
    for the SOW
  • Agree on MOU and SOW, listing
  • personnel (on and off-project),
  • responsibilities, deliverables (referring to
    WBS), reporting, procurement authorization
  • contributed effort, services and equipment,
  • costs and funding,
  • schedule and milestones
  • SOW gives budget authorization, institute will
    invoice Project, funds will then be sent to
    institute
  • Level3 Manager (Julian Bunn) reports to Level2 UF
    Manager
  • (Ceterum Censeo We did NOT YET receive the
    funding for the pTier2 effort!)

12
Hire Project Support Person
  • Project Support Computing Professional with
    software project experience
  • Develop, deploy, support project management tools
  • tools for WBS and scheduling MSProject, XProject
  • Tools for documentation Doxygen, document
    archival, analysisdesign, reverse-engineering
  • Tools for communication hyper-news, mailing
    lists, VC, group agenda, web
  • Help to establish and support
  • software process design reports, release cycles,
    code reviews
  • software QA/QC regression testing, bug tracking,
    version control
  • Documentation software and hardware systems
  • Work with project managers on
  • developing and maintaining the WBS, schedule,
    milestones,
  • with budget officers on budget and book keeping
    of funds
  • Support reporting to project oversight and peer
    reviews on effort, budget, schedule and work
    performance
  • Personnel Request has been sent out

13
NSF Funding
  • Submitted Funding Allocation Request to the U.S.
    LHC Program Office
  • Discussed it with funding agencies on Jan 25,
    2001 at Minnesota MeetingNo response
    yet.
  • Phone Conference w/ DOE and NSF this Friday,
    March 23, 2001
  • Funding Status and Tier 2 Issues

14
PPDG and CMS
  • PPDG proposal to SciDAC (DOE)
  • Collaboration b/w HENP and CS
  • Develop, acquire, deliver Grid-enabled tools to
    data-intensive requirements
  • vertical integration of new mechanisms w/ Grid
    middleware (e.g. Globus) and experiment specific
    applications
  • requested funding FY2001/2/3 is 3.5M/4.0M/4.5M
  • CMS participation and requested funding for FY01
  • Caltech (160k), Fermilab (160k), UC San Diego
    (80k), U Florida
  • At Fermilab CMS and DØ Project Management (Ruth
    Pordes)
  • Shahzad Muzaffar, Jim Amundson DØ people
  • Work model HEP experiment teams will work with
    CS teams on deliverables
  • Distributed Production File Services
  • Distributed Interactive Analysis Services
  • Object-Collection Access Services
  • e.g. Distributed Production File Services
  • GDMP product-izing, improving stability and
    scalability
  • Setup project, invite participation

15
US CMS SC Project Costs
  • Nov2000 Project Plan Total Costs 65.65 M FY01
    to FY06 (escalated)

16
Steps Towards a Base Line
  • Delayed deployment at T1(h/w depl. starts
    2005)will need some thinking
  • 3.5 FTE from UF til 2003
  • 1 FTE from CAS til 2003
  • 1 FTE in PO
  • Put in reality for 2001
  • Need to work on FY2002
  • De-scoping in UF

VERY PRELIMINARY DRAFT