Title: Electron Cooling Commissioning Plans
1Electron Cooling Commissioning Plans
- Sergei Nagaitsev
- September 16, 2004
- Contributions from C. Gattuso,
- A. Shemyakin and D. Broemmelsiek
2Recycler stack evolution with rapid transfers
Cold antiprotons 50 eV-s, 10 ? mm-mrad Ready for
a transfer to the Tevatron
0
8
15
At present, the max. number of stored pbars is
15e11
3Prepare 9 (6 eV-s each) bunches for extraction
4Recycler transfers with gated cooling
- Every 30 min, a new batch of 22E10 pbars (15-p
mm-mrad, 15 eV-s) arrive from the Accumulator and
is kept separately for 25 minutes. - During 25 min, the batch is pre-cooled by gated ?
SC. The ? emittances are cooled from 15 to below
10 p mm-mrad. The longitudinal emittance is kept
unchanged. - After that, the stack of 50 eV-s, 7-p mm mrad is
merged with a 15-eVs, 10-p mm mrad batch. Now the
electron cooling is applied. After 30 min, the
phase space is cooled from 65 to 50 eVs, making
it ready for the next merge.
5Recycler transfers with gated cooling
Gated cooling ON OFF
Cold Stack
New batch
6Gated Cooling
Two segments of beam (25e10 pbars each) one
cooled/gated and one not. The uncooled bunch
shows natural emittance growth due to IBS and
coulomb scattering.
7Electron Cooling Long. Rate Design Goal
- Cooling needed 30 eV-s per hour
- To minimize the IBS rate, a 65-eV-s stack will be
kept in a 4-µs long bunch 95 of particles will
have its energy offset 8 MeV. - For particles with ?E 8 MeV the drag rate needs
to be about 4 MeV/hr to cool 15 eV-s in 30
minutes.
8Calculated long. drag rates
Design goal
9Equilibrium long. emittance
- For a nearly constant drag rate F0 4 MeV/hr the
equilibrium energy distribution is not gaussian
but exponential f(E) exp(-E/s), where s
D/(2F0) and D is the diffusion rate. - The diffusion rate is mostly determined by the
intra-beam scattering - All our experience with the stochastic cooling
system in Recycler to date is consistent with the
IBS being the second (after new batch injection)
largest longitudinal heating mechanism.
10Calculated IBS diffusion rates for various
emittances 6,7,8 and 10 µm
11Performance goal for the long. equilibrium
emittance 54 eV-s
12The commissioning project plan summary
- Will begin on Dec. 1, 2004 an approximate date
for the end of the shutdown. - The Recycler will be brought to its pre-shutdown
state. Same team, which commissioned the Recycler
in 2004. - The Electron cooling group will continue the
installation until Feb 1, 2005. - On Feb 1, 2005 the Recycler starts to contribute
to HEP luminosity (mixed-source operations). - The Recycler operations group and systems group
becomes responsible for operations. - This continues uninterrupted until about Apr 1,
2005. - On Feb 1, 2005 the effort switches over to the
electron beam commissioning. - Pelletron and U-bend start-up
- All of the electron cooling group the Recycler
team.
13The project plan summary
- On Mar 15, 2005 start commissioning of the
complete electron beamline. - Run electron beam in a pulsed mode
- Pbar operations are uninterrupted
- On Apr 4, 2005 start establishing a DC beam.
- The Recycler beam may be interrupted
- 2-weeks cycle 5-days ecool work (two shifts per
day), 9-days pbar operations - Investigate and correct MI ramp effects on the
electron beam - Minimize the effects of the electron beam on the
Recycler beam, start running pbar and electron
beams concurrently - Establish a 500-mA dc electron beam by July 08,
2005 - On July 11, 2005 start adjusting the electron
beam parameters - 500 mA dc beam is stable
- Establish and adjust the beam trajectory in the
cooling section - Measure the electron beam properties
- The pbar beam is interrupted when electron
envelope is measured. - By Sep 08, 2005 demonstrate the electron cooling
14The project plan summary
- In Sep-Dec 2005 the Recycler continues to operate
and contribute to the HEP luminosity. - The cooling rates are measured electron cooling
is optimized - Dec 31, 2005 project ends.
15Electron cooling system setup at MI-30/31
16Electron cooling system setup at MI-30/31
17Electron cooling system setup at MI-30/31
18Electron beam design parameters
- Electron kinetic energy 4.34 MeV
- Absolute precision of energy ? 0.3
- Energy ripple ? 10-4
- Beam current 0.5 A DC
- Duty factor (averaged over 8 h) 95
- Electron angles in the cooling section
- (averaged over time, beam cross section, and
cooling section length), rms ? 0.2 mrad
19The Wide Band run - History
- 20-Mar-01- Fist time HV on both tubes
- 28-Dec-01 - 0.6 A in the short beam line
- 18-Nov-02 - beginning of a shutdown to switch to
the full-scale line - 17-Jul- 03 - DC beam recirculated through the
full-scale line - 30-Dec-03- 0.5 A DC beam
- 29-May-04- 0.1 A beam with no scalloping in the
cooling section
20The WideBand run History summary
- Short beam line
- 20 months of operation, including 8 months of
shutdowns - Operation learning unknowns (ions, crash
dynamics, reliable acceleration rate)
diagnostics - Shutdowns 70 to repair, 30 to install new
equipment - Corresponding stage at MI-31 is supposed to take
1.5 months - 8-months shutdown to install the full-scale line
- Corresponding stage at MI-31 is supposed to take
3 months - Full-scale beam line (recirculation)
- 6 months of operation, including 2.5 months of
shutdowns - Operation diagnostics learning optics
unknowns (wall charges, high losses) - Shutdowns primarily for repairs
- Corresponding stage at MI-31 is supposed to take
4 months - Full-scale beam line (cold beam)
- 5 months of operation, including 1.5 months of
shutdowns - Operation diagnostics optics
- Shutdowns 10 to repair, 90 to install new
equipment
21The WideBand run Recirculation results
22The WideBand Tests Electron Angles in the
cooling section
23The Plan- stage 1
- Pelletron and U-bend commissioning 1.5 month
- Tubes conditioning
- Each section is conditioned to 1.1 MV. The total
voltage of 5 MV is stable with all lenses on. - Optics measurements in U-bend
- A pulsed beam is transported through the U-bend
with low losses (lt 2). - The OTR monitor under the acceleration tube and
the pepper pot are commissioned. Data to restore
the beam parameters at the acceleration tube exit
are taken. - DC beam in U-bend
- BPMs in the U-bend are commissioned.
- Crash diagnostics and the protection system are
tested. - 0.2 A beam stays at 4.34 MeV in a shift-long run
with 95 duty factor.
24The Plan- stage 2
- Full beam line commissioning 3 weeks
- A pulsed beam is transported through the entire
beam line with low losses (lt 2 ). - All BPMs (in the pulse mode) and the YAG/OTR at
the end of the cooling section are commissioned. - Trajectory responses are measured in the entire
line, are analyzed, and major discrepancies are
resolved.
25The Plan stage 3
- DC beam commissioning 3 months
- Establish 5 mA DC beam.
- Beam line optics
- A program for measuring transfer matrixes is
commissioned. - All elements are measured with a DC beam. A
simulated differential trajectory in the cooling
section fits measurements within 0.05 mm. - The absolute value of the electron energy is
measured with precision of 0.3 by using the
results of the longitudinal field measurements
and the wave length of the electron trajectory in
the cooling section. - Energy stability
- Energy fluctuation in the bandwidth up to 100 Hz
is estimated by analysis of a BPM signal from a
high- dispersion region. - Day-to- day energy variations are analyzed from
measurements of the electron wave length in the
cooling section. The relative value of both
effects should not exceed 0.01 .
26The Plan stage 3 (cont.)
- Beam position
- Drifts and oscillations of the electron beam
position in the cooling section and in the entire
line are measured and contributions of major
sources of the motion, including MI ramp effects,
are determined. - A feedback loop stabilizing the beam position in
the cooling section is commissioned. - Effects of e-beam aborts on pbars
- Effects of e-beam aborts on pbars are measured,
including recording pressure in MI-30 region and
pbar positions. - Establish 0.5 A DC beam
27The Plan- stage 4
- Pbar cooling 2 months
- Low electron beam temperature in the cooling
section
28The Plan- stage 4 (cont.)
- Observe electron cooling
- The energies are aligned within 0.3 using
absolute calibrations for both beams. - Effect of electron cooling is observed by
longitudinal Schottky monitor.
29 Pbar Beam Preparation for Cooling Demo
- 1010 antiprotons
- Coasting beam, No MI Ramps
- Ion trapping
- possible emittance growth
- Transverse Stochastic Cooling, wait until
emittances are controlled - Initial momentum cooling
30Beam Preparation, II
- Use an RF level to smear momentum spectrum and
fill the momentum aperture to 0.3 - 100Hz resolution bandwidth
- 3sec sweep, 20 averages
- After 4 minutes, spectrum has relaxed
- Tr. emittance remains small (3-pi). Loss of
reliable emittance data
31Cooling Model
- Electron beam
- Beam current 0.5 A
- rms angle spread 0.1 mrad (Teff 0.46 eV)
- rms energy spread (lab frame) - 200 eV
- Cooling section length 1.8 m (10 of total
cooling section) - Pbar beam
- Emittance (n, 95) 3-pi mm mrad
- full energy spread 28 MeV
- Relevant properties
- Coulomb log 7.2
- ve?gt vp?gtgt ve?? -- rest frame e-beam distribution
is flat - Cooling force for small vp?? is constant it
is a drag rate, R0
32Take Actual Spectra and Apply Model
3315 Minutes 5dB signal
34The Plan- stage 5
- Cooling optimization 2.5 months
- Adjustment of e-beam parameters
- Settings files for several beam currents and
solenoid fields are composed. - 0.5 A beam stays at 4.34 MeV in a shift-long run
with 95 duty factor. - Measurements of drag rate
- Gated stochastic cooling
- Recycler transfer commissioning
- Accumulation of 3?1012 pbars
35Assumptions
- The commissioning team is identical to WBs as of
May 04 (including B. Chase ( Co.), T.
Bolshakov, B. Kramper, G. Saewert ( Co.), C.
Schmidt) and/or expanded by the Recycler dpt. - Two 6-hour shifts are run 5 days a week.
- By the beginning of commissioning (Feb. 1, 05),
all equipment is installed and is ready to go. - Interference with the Recyclers HEP operations
is negligible. - We are very lucky, and no major repairs are
necessary during commissioning. - No interruptions caused by a lab-wide shutdown
are included.
36Interference with the Recyclers work for
luminosity
- Effects of ECool bends and cooling section field
on the pbar dynamics in RR- should be corrected
anyway - Effects of the ebeam space charge on pbar
dynamics in RR- supposed to be negligible - Changes in the pbar lifetime caused by a pressure
rise in the cooling section- is negligible
according to measurements in WB - Drag force- e- beam measurements can be done
either at low electron currents or at the
electron energy shifted by 1 - Measurements of DC beam dimensions in CS and
measurements with the YAG/OTR downstream of the
cooling section- no pbars in RR
37The summary
- The Recycler is brought up to its present level
through a known and well-documented process - The Recycler never stops contributing to the HEP
luminosity, it just becomes more efficient over
about 12 months period. - The electron cooling beam is commissioned through
a series of well-defined incremental steps. - We have no schedule contingency in our plan
everything has to work just right.