Forward Multiplicity Detector (FMD)
2 Forward Multiplicity Detector (FMD)
ITS
Outer ring
Inner ring
FMD 3
FMD 1
FMD 2
3Detector elements
Muon absorber cabling
Final Inner Digitizer
Final FMD3 cone with beam pipe support
Complete module (outer type)
Cone assembly test
4System tests already done
Mechanical assembly with models at CERN
Beam tests with gt5000 active channels and 2
digitizer cards 1 RCUDATE
Full read-out tests with DigitizerRCUDATE
5Pre-commissioning
- Pre-commissioning plans prior to installation
- _at_NBI - assemble complete detectors (FMD3
FMD2, then FMD1) - - complete test with RCU, DDL, DATE,
TTC/LTU, cooling - (but not final CAEN LV and HV)
- - basic DCS panels, tested on simulated
CAEN and real RCU/DCS card - _at_CERN (Jan-Feb 2007)
- - retest as above, but with final CAEN
power supplies - Status of pre-commissioning (_at_NBI)
- - FMD3 mechanics ready, FMD2 starting
production - - all detector modules in house
- - TTC/LTU being set up
- - cooling plates in production
- - DCS work starting
- - complete read-out working
6Electronics Racks
- Locations of racks in the cavern drawings of
rack content including rack patch-panels and
possible communication lines between racks and
entry point of cables (top, bottom ?) - - Rack O13 contains one EASY 3000 crate
with 48 V power supply etc - one patch panel to distribute the LV cables
from 10 digitizers and 3 RCUs to 4 low
voltage modules - - Rack X06 contains one SY1527 crate
- one patch panel to distribute the HV cables
from 70 modules - and 6 high voltage modules
- Schedule for arrival of electronics and
individual rack components at CERN. - - Power supply crates hopefully early 2007
- - Power supply modules before August 2007
delivery schedule unknown - - Patch panels to be mounted together with
cable connectors - Electronics commissioning
- - Power supplies to be installed and
commissioned together with FMD3
7Detector Arrival _at_ CERN
- Installation dates FMD3 16-20 February 2007
- FMD2 07 March 2007
- FMD1 03-05 July 2007
- When will the detector arrive at CERN ?
- - before mid January 2007 (FMD3 and FMD2, FMD1
later) - What are the dimensions of the transport cradle
that must be brought to the place of
installation ? How will it be brought there? - - 2 times 1x1x1 m3 by car
- How many people will participate in the
installation ? - - 6-8 people (physicists and technicians)
- How many days before installation will the team
arrive ? - - early-mid January for lab. test 3-4 people
- - for installation above 3-4 people
8Cables Patch panels
- Status of cable, fibre and connector ordering.
- - C side cables on absorber done, remaining
defined - but cables not pulled. Fibres not pulled.
- - A side defined, but missing final cable
lengths and final patch panel designs. - Plans for cabling, connector and cable testing
activity by subgroup. - - NBI - cables on absorber and service
chariot - - all cable connectors
- - full cable testing
- - CERN - pull long cables and all fibres
- Needed patch panels and status of patch panels.
- - Still to be done panels on A side (PP2, PP1,
PP0) - panels in racks (LV and HV distributions)
9Installation (1)
- Minimum status of services at start of
installation. - - all cables and fibres ready and tested
- - LTU/TTC running
- - DAQ running
- - CAEN HV and EASY LV crates and some modules
delivered - - preferably cooling water from TPC heat screen
system - Installation tooling provided by the subdetector
group. - - support for cones during assembly
- Other Infrastructure needed.
- - full ITS installation infrastructure
- Installation scenario day by day.
- - Before installation date install and cable
RCU modules - - FMD3 3 days mechanical installation, then
complete test - - FMD2 1 day mechanical installation
- 1 day (12/03/2007) set aside for complete
test after the cable hook-up
10Installation (2)
- Tests and verifications during installation for
cables, fibers and cooling lines. - - cables etc should be tested before
installation - - FMD3 should be verified through to the racks
and counting rooms (with DCS and DAQ) - - FMD2 cannot be cabled until TPC is in place
- ideally detector should be tested with the
commissioning electronics - Not clear what is possible with temporary
cabling, power etc. - Alignment requirements
- - assured at required precision by ITS
installation scenario
11Commissioning summary (1)
At NBI
- Test all detector modules at NBI.
- Results stored in systematic fashion. Make list
of repairs, send modules to CERN. - Pre-assembly at NBI
- Cables
- Shielding (HF and light)
- Cooling
- Mechanical fit. Detectors, Honeycomb, Digitizer,
beam tube support. - Noise tests
- RO system w. 2 branches
- Calibration pulse test
- DCS control software
- Monitor software, test and calibration scripts.
- Check safety procedures (leakage current, auto
shut off at beam injections, etc) - Final e-beam test at Aarhus data taken 4-5
November - Test inner and outer digitizers with. inner and
outer detectors. - S/N systematics
- Rate dependence
- System stability
- Limitations at NBI
12Commissioning summary (2)
At CERN
- Detector operation at CERN in Lab. conditions
similar to NBI lab. - (Re-) Assemble detector system after transport
- Connect detectors to LV, HV, and self-generated
trigger - Run with stand-alone DAQ
- Operate system in lab. Measure noise, stability
and rate - Detector operation at CERN in Lab. conditions
similar to ALICE. - Connect detectors to real LV, HV, and trigger
- Establish DCS control of hardware
- Run with real external trigger (LTU/TTC) and
real ALICE DAQ - Operate system in lab. Measure noise, stability
and rate - Calibration and Control procedures
- Exercise scripts to calibrate (pedestals, gain)
and operate detector (start/stop/reset/load) - Exercise first monitor programs
- Check stability and rate performance
- Check safety procedures (leakage current, auto
shut off at beam injections, etc) - Preparation in ALICE (in pit) prior to
installation - Verify all cables/connectors (long cables and
local (PP-to detector) cables) - Availability of trigger signal
- Availability of real HV, LV - LV situation
problematic due to CAEN delivery schedule
13Commissioning summary (3)
At CERN post installation
- Detector operation in ALICE.
- Connect detectors to real LV, HV, and trigger
- Establish DCS control of final hardware
- Run with real external trigger (TTC) and real
ALICE DAQ - Operate system in ALICE. Measure noise and
stability. - Calibration and Control procedures
- Exercise scripts to calibrate (pedestals, gain)
and operate detector (start/stop/reset/load) - Exercise first monitor programs
- Check stability and rate performance