Title: Peng Xu, Philip Haves, James Braun, MaryAnn Piette
1A Case Study of Precooling with Zone Temperature
Reset in a Commercial Office Building
- Peng Xu, Philip Haves, James Braun, MaryAnn
Piette - January 23, 2004
- Sponsored by the California Energy Commission and
the California Institute for Energy Efficiency
2Outline
- Aim
- Test site description
- Precooling and demand shedding strategies
- Test results
- Utility analysis
- Conclusions and future work
3Aim
- Demonstrate the potential for reducing
peak-period electrical demand in a
moderate-weight commercial building using
building structural mass.
4Executive Summary
- Precooling and zone temperature reset can shift
up to 100 of cooling power from on- to off-peak
in a moderate-weight commercial buildings - Electricity peak demand reduced by as much as 2.3
W/ft2 - Potential for cost savings when combined with
Critical Peak Pricing
5Case Study - Introduction
- Started in August 2003
- Purpose - preliminary study to assess potential
and need for further work - Potential demand reduction/load shifting in
moderate-weight buildings - Effectiveness of precooling and zone temperature
reset - Thermal comfort
6Test Site Description
- Medium-sized government building
- Santa Rosa, CA
- 80,000 ft2 (40,000 ft2 office 40,000 ft2
courthouse) - 3 stories
- Relatively low mass building structure
- 6 in. concrete floor, 4 in. concrete wall, medium
furniture density, standard commercial carpet - High window-to-wall ratio
- Floor to ceiling glazing on south and north
façade - Typical internal loads
- Number of occupants
- 100 (office side)
7South Facade
8North Facade
9Windows
- Single glazing
- Tinted glass
- Internal blinds
10Cooling Plant
- West wing three 75-ton, 30-year old McQuay
air-cooled chillers - East wing two 60-ton, 10-year old Carrier
air-cooled chillers - Constant-speed water pumps, one for each chiller
- Two stage compressors
11HVAC Secondary Systems
- Five VAV air handling units (three single duct
two dual duct systems) - Variable-speed supply and return fans
- 50-60 VAV zones
- DDC control (Alerton)
- No global rest of zone temperature
12Building Operation
- 5 am - 8 am - start up
- 8 am - 5 pm - occupancy
- 2-3 hot/cold calls per month
- No major faults, some modest problems
- One undersized cooling coil
- Some air balance problems
- Lack of reheat coils in single-duct systems
causes temp control problems
13Precooling Zonal Reset Strategies
14Monitoring
- Existing
- Whole building power meters
- Chiller power meters
- Weather station
- HVAC performance data from EMCS
- 500 data points
- 15 minute intervals
- Added
- AHU fans power meters
- Operative temperature sensors
15Operative Temperature Comfort
Room
Regular temperature sensor
Radiant heat exchange
screen
Convective heat exchange
Operative temperature sensor
globe
16Peak OA Temperature vs. Peak Demand
17Classification of Weather Conditions
Hot days
Warm days
Cool days
18Comparison of Baseline Test Conditions
19Tests Performed
20Cool Days Limited Precooling
21Warm Day Limited Precooling
22Extended Limited Precooling
23Hot days Extended Precooling
24Chiller Power Limited Precooling
0.7 W/sf shed
25Results Fan Power
26Results Zone Temp
27Critical Peak Pricing (1 of 3)
- Operating time
- CPP high price 300pm 6pm
- CPP moderate price 1200pm 300pm
- CPP days (12 days 5/1 10/31)
- Average of maximum outside air temperatures in
San Francisco, San Jose, Sacramento and Fresno gt
98 oF
28Critical Peak Pricing (2 of 3)
- Current tariff A-10S
- Non CPP Day Rate
- On-peak credit, 0.0559/kWh, (12 pm- 6 pm)
- Part-peak credit, 0.0050/kWh, (830 am-12 pm)
- CPP Day Rate
- Moderate price, 0.24/kWh (12 pm 3 pm)
- High price, 0.82/kWh, (3 pm-6 pm)
29Critical Peak Pricing (3 of 3)
30Market Potential Cooling in Office Buildings
- State-wide peak demand 50GW
- Commercial cooling - largest contributor 15,
7.5 GW
31Conclusions
- Precooling zone temp reset can shed up to 80
100 of the cooling peak load, without comfort
complaints, even in relatively high outside
temperature conditions (90 oF) - Benefits of nocturnal precooling are unclear
- Economic savings can be made if combined with CPP
or similar DR programs