Title: Managing Dependent Demand


1
Managing Dependent Demand
  • Week 5

2
What is Wrong with EOQ?
  • Nothing
  • Just it assumes that demand is independent
  • It is assumed that the next item demanded is not
    in anyway influenced by the last item demanded.

3
Main Aspect of Dependent Demand
  • Consider the production of a chair or sofa
  • require
  • wood end wood
  • cross piece fabric
  • metal frame foam
  • seat cushion fastener
  • back cushion steel tube

4
Parts Explosion
  • Levels
  • Level 0 finished products
  • Level 1 sub-assemblies
  • Level 2 raw materials
  • For our example what are the various levels

5
(No Transcript)
6
Stock Status 1
7
Stock Status 2
8
Current Orders
  • 200 sofas week 8
  • 350 chairs week 9
  • 100 replacement seat cushions week 7

9
Standard terms
  • Gross requirement (GR)
  • Net requirement (NR)
  • On hand stock (OH)
  • Orders Due (OD)
  • Planned Orders (PO)
  • Safety Stock (SS)
  • NR GR -OH-OD SS

10
Level 1
  • Chairs
  • GR 350 (week 9)
  • NR 350 - 25 20 345 (week 9) so,
  • PO 345 (week 8)
  • Sofa
  • GR 200 (week 8)
  • NR 200 -30 20 190 (week 8) so,
  • PO 190 (week 7)

11
Level 2
  • Back Cushion
  • GR 190x2 380 (week 7)
  • NR 380 - 45 335 (week 7)
  • PO 335 (week 5)
  • GR 345 (week 8)
  • NR 345 (week 8)
  • PO 345 (week 6)
  • Seat Cushions?

12
Materials Requirement Planning(MRP1)
  • Consists of assemblies and sub assemblies
  • Planning done on regular basis
  • Involves decisions on what, how many when
  • Master schedule
  • Explosion
  • Accuracy of reports

13
Key Reports
  • Bill of Materials
  • Where used listing
  • Stock Reports
  • Purchasing records
  • Work in Progress
  • Scrap and Rework reports

14
Manufacturing Resource Planning MRP2
  • Whole capability and limitations of the entire
    plant considered

15
Just in Time (JIT) Manufacture
  • MRP 1 is often just in case
  • JIT assume parts arrive from suppliers as needed
  • Value of JIT
  • lead times reduced
  • space saved
  • Right first time

16
Exam Question
  • Why is dependent demand different from EOQ
  • Give an example of what you understand by
    explosion in MRP1
  • What is the difference between MRP1, MRPII and JIT