Title: Chapter 16 Inventory Systems for Dependent Demand
1Chapter 16Inventory Systems for Dependent Demand
- Master production schedule
- Material Requirements Planning (MRP)
- System structure
- Example
- MRP II
- MRP/JIT
2
2Material Requirements Planning
- How much of an item is needed?
- When is an item needed to complete
- a specified number of units...
- in a specified period of time?
- Dependent demand drives MRP
3
3Introductory Example - Dependent Demand
Lead Times A 1 day B 2 days C 1 day D 3
days E 4 days F 1 day
Product Structure Tree for Assembly A
Demand Day 10 50 A Day 8 20 B (Spares) Day
6 15 D (Spares)
Create a schedule to satisfy demand.
4
4LT 1 day
5
Irwin/McGraw-Hill
- The McGraw-Hill Companies, Inc., 1998
5LT 2
Spares
6
Irwin/McGraw-Hill
- The McGraw-Hill Companies, Inc., 1998
67
- The McGraw-Hill Companies, Inc., 1998
Irwin/McGraw-Hill
7Master Production Schedule (MPS)
- Time-phased plan specifying how many and when the
firm plans to build each end item
MPS (Specific End Items)
8
8Time Fences
- Frozen
- No schedule changes allowed within this window
- Moderately Firm
- Specific changes allowed within product groups as
long as parts are available - Flexible
- Significant variation allowed as long as overall
capacity requirements remain at the same levels
9
9Time Fences
10
10Material Requirements Planning
- Based on a master production schedule, a material
requirements planning system - Creates schedules identifying the specific parts
and materials required to produce end items - Determines exact numbers needed
- Determines the dates when orders for those
materials should be released, based on lead times
11
11Material planning (MRP)
Irwin/McGraw-Hill
12
- The McGraw-Hill Companies, Inc., 1998
12Bill of Materials (BOM) FileA Complete Product
Description
- Materials
- Parts
- Components
- Production sequence
- Modular BOM
- Subassemblies
- Planning BOM
- Fractional options
13
13Inventory Records File
- Each inventory item carried as a separate file
- See, for example, Exhibit 16.15
- Status according to time buckets
- Pegging
- Identify each parent item that created demand
14
14Primary MRP Reports
- Planned orders
- to be released at a future time
- Order release notices
- to execute the planned orders
- Changes in due dates of open orders due to
rescheduling
15
15Primary MRP Reports
- Cancellations or suspensions of open orders
- due to cancellation or suspension of orders on
the master production schedule. - Inventory status data
16
16Net Change System
- Activity driven
- Net change schedules
- Potential for system nervousness
17
17Another MRP Example
Requirements include 95 units (80 firm orders and
15 forecast) of X in week 10 plus the following
spares
18
18Adding some more terminology
- Gross Requirements
- On-hand
- Net requirements
- Planned order receipt
- Planned order release
19
1920
Irwin/McGraw-Hill
2021
Irwin/McGraw-Hill
21Manufacturing Resource Planning (MRP II)
- Goal Plan and monitor all resources of a
manufacturing firm (closed loop) - manufacturing
- marketing
- finance
- engineering
- Simulate the manufacturing system
23