Chapter 16 Inventory Systems for Dependent Demand - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Chapter 16 Inventory Systems for Dependent Demand

Description:

Inventory Systems for Dependent Demand Master production schedule Material Requirements Planning (MRP) System structure Example MRP II MRP/JIT 2 – PowerPoint PPT presentation

Number of Views:352
Avg rating:3.0/5.0
Slides: 22
Provided by: edut1550
Category:

less

Transcript and Presenter's Notes

Title: Chapter 16 Inventory Systems for Dependent Demand


1
Chapter 16Inventory Systems for Dependent Demand
  • Master production schedule
  • Material Requirements Planning (MRP)
  • System structure
  • Example
  • MRP II
  • MRP/JIT

2
2
Material Requirements Planning
  • How much of an item is needed?
  • When is an item needed to complete
  • a specified number of units...
  • in a specified period of time?
  • Dependent demand drives MRP

3
3
Introductory Example - Dependent Demand
Lead Times A 1 day B 2 days C 1 day D 3
days E 4 days F 1 day
Product Structure Tree for Assembly A
Demand Day 10 50 A Day 8 20 B (Spares) Day
6 15 D (Spares)
Create a schedule to satisfy demand.
4
4
LT 1 day
5
Irwin/McGraw-Hill
  • The McGraw-Hill Companies, Inc., 1998

5
LT 2
Spares
6
Irwin/McGraw-Hill
  • The McGraw-Hill Companies, Inc., 1998

6
7
  • The McGraw-Hill Companies, Inc., 1998

Irwin/McGraw-Hill
7
Master Production Schedule (MPS)
  • Time-phased plan specifying how many and when the
    firm plans to build each end item

MPS (Specific End Items)
8
8
Time Fences
  • Frozen
  • No schedule changes allowed within this window
  • Moderately Firm
  • Specific changes allowed within product groups as
    long as parts are available
  • Flexible
  • Significant variation allowed as long as overall
    capacity requirements remain at the same levels

9
9
Time Fences
10
10
Material Requirements Planning
  • Based on a master production schedule, a material
    requirements planning system
  • Creates schedules identifying the specific parts
    and materials required to produce end items
  • Determines exact numbers needed
  • Determines the dates when orders for those
    materials should be released, based on lead times

11
11
Material planning (MRP)
Irwin/McGraw-Hill
12
  • The McGraw-Hill Companies, Inc., 1998

12
Bill of Materials (BOM) FileA Complete Product
Description
  • Materials
  • Parts
  • Components
  • Production sequence
  • Modular BOM
  • Subassemblies
  • Planning BOM
  • Fractional options

13
13
Inventory Records File
  • Each inventory item carried as a separate file
  • See, for example, Exhibit 16.15
  • Status according to time buckets
  • Pegging
  • Identify each parent item that created demand

14
14
Primary MRP Reports
  • Planned orders
  • to be released at a future time
  • Order release notices
  • to execute the planned orders
  • Changes in due dates of open orders due to
    rescheduling

15
15
Primary MRP Reports
  • Cancellations or suspensions of open orders
  • due to cancellation or suspension of orders on
    the master production schedule.
  • Inventory status data

16
16
Net Change System
  • Activity driven
  • Net change schedules
  • Potential for system nervousness

17
17
Another MRP Example
Requirements include 95 units (80 firm orders and
15 forecast) of X in week 10 plus the following
spares
18
18
Adding some more terminology
  • Gross Requirements
  • On-hand
  • Net requirements
  • Planned order receipt
  • Planned order release

19
19
20
Irwin/McGraw-Hill
20
21
Irwin/McGraw-Hill
21
Manufacturing Resource Planning (MRP II)
  • Goal Plan and monitor all resources of a
    manufacturing firm (closed loop)
  • manufacturing
  • marketing
  • finance
  • engineering
  • Simulate the manufacturing system

23
Write a Comment
User Comments (0)
About PowerShow.com