Title: Group member :
1United Arab Emirates UniversityCollege of
EngineeringChemical petroleum Engineering
Design of Oil Production Surface Facilities
- Group member
- Mansoor Sulaiman AlBalooshi
200308910 - Saleh Salem AlAmeri
200235706 - Ahmed Mohamed Obaid
200209570 - Advisor Dr Mohamed Al Nakoua
2Acknowledgments
- We would like to thank
- Dr. Mohammed Al Nakoua - our advisor.
- Dr. Ahmed Gaouda - our coordinator.
3Contents
- Objective.
- Introduction.
- Plant Design.
- Material Balance.
- Separators Design.
- Gas Sweetening Column Design.
- Gas Dehydration Column Design.
- Conclusions.
4Objective
- Design a plant for separation and treatment of
petroleum fluids.
5Introduction
- Data
- Dubai Petroleum Company.
- MARGAM field which is an onshore field.
- It is a gas field.
6Plant Design
7(No Transcript)
8Material Balance
- Material balance was carried out using HYSYS
program on - First separator.
- Second separator.
- Mixing point.
9Material Balance for first separator
- Flow rate of natural gas
- 125 MMSCFD
- 6241.753 Kgmole/hr
10Component Stream3 (kgmole/hr) Stream2 Kgmole/hr Stream4 Kgmole/hr
H2O 0.53 1.515 2328.531
N2 6.5191 18.435 H.C. 2.747
CO2 16.1001 19.446 -
C1 1001.1575 2385.505 -
C2 109.5017 66.923 -
C3 86.5833 22.476 -
iC4 26.743 3.788 -
C4 40.3151 4.546 -
iC5 20.5423 1.263 -
C5 16.0631 0.758 -
C6 17.8126 0.253 -
C7 43.7242 0.505 -
Total 1385.592 2525.413 2331.28
11Component Stream5 (kgmole/hr) Stream6 Kgmole/hr Stream7 Kgmole/hr
H2O - 0.5299 0.0001
N2 - - 6.5191
CO2 16.1 - -
C1 1001.1575 - -
C2 6.101 - 103.4007
C3 - - 86.5833
iC4 - - 26.743
C4 - - 40.3151
iC5 - - 20.5423
C5 - - 16.0631
C6 - - 17.8126
C7 - - 43.7242
Total 1023.359 0.5299 361.7035
12Component Stream2 (kgmole/hr) stream5 (kgmole/hr) Stream8 (kgmole/hr)
H2o 1.515 - 1.515
N2 18.434 - 18.434
CO2 19.446 16.1 35.546
C1 2385.505 1001.1575 3386.6625
C2 66.923 6.101 73.024
C3 22.476 - 22.476
iC4 3.788 - 3.788
C4 4.546 - 4.546
iC5 1.263 - 1.263
C5 0.758 - 0.758
C6 0.253 - 0.253
C7 0.505 - 0.505
Total 2525.413 1023.359 3548.772
Stream2
Stream8
Stream5
13Separators Design
- Horizontal separator
- Two separators were designed
14Procedure for sizing separator
- Calculate CD
- Vt 0.0119 (?L ?g/?g) dm/CD
- Re 0.0049 ?g dmVt/ µg
- CD 24/Re 3/(Re)0.5 0.34
- First assumption for CD is 0.34
15Procedure for sizing separator (continue)
- Calculating Z
- Tpc 170.5307.3 S.G
- Ppc709.6-58.7 S.G
- PPr P/ Ppc
- Tpr T/ Tpc
16Procedure for sizing separator (continue)
17Procedure for sizing separator (continue)
- Gas Capacity Constraint
- dLeff 420 TZ(Qg/P) (?L ?g/?g)
(CD/dm)0.5 -
18Procedure for sizing separator (continue)
- liquid Capacity Constraint and seam to seam
length - d2Leff tr QL /0.7
- Lss Leff d/12 (for gas capacity)
- Lss 4/3 Leff (for liquid capacity)
19Procedure for sizing separator (continue)
20Data
T,oR P,psia Qg,MMscfd QL , bbl/d µg, Cp tr,min dm,micron
560 1002 125 3000 0.013 2 100
?L 62.43 lbm/ft3
?g2.7((S.Gg)P/TZ) 4.34 lbm/ft3
21Sizing first separator
- By iteration CD is found to be 1.004
- Z 0.78
d,in Gas Leff,ft Liquid Leff,ft Lss (gas),ft Lss(liquid),ft 12 Lss/d
24 26.616 14.881 28.616 35.489 17.744
30 21.293 9.524 23.793 28.391 11.356
36 17.744 6.614 20.744 23.659 7.886
42 15.209 4.859 18.709 20.279 5.794
48 13.308 3.72 17.308 17.744 4.436
A 48-in diameter 18-ft length separator provides
about two minutes retention time
22Sizing second separator
P,psia T,oR µg,Cp (S.G)g QL,bbl/d Qg,MMscfd dm,in tr,min
480 510 0.01 0.9 1.5 0.7 100 3
Z 0.81 ?L 62.43 lbm/ft3 ?g 2.824 lbm/ft3
CD 1.003
23Sizing second separator (continue)
d,in Gas Leff,ft Liquid Leff,ft Lss (gas),ft Lss(liquid),ft 12 Lss/d
36 0.23 0.011 6 0.306 3
A 24-in (3-ft) diameter 6-ft length separator
provides about three minutes retention time
24Reason for sweetening Natural gas
- To meet sales specifications.
- To prevent corrosion.
- To allow less costly metallurgy.
- To remove toxicity hazards. (H2S).
25Gas sweetening column design
- Monoethanolamine (MEA) as a reactive solvent.
- Amine enters the top of the sweetening tower.
- The acid gas enters from the bottom of the tower.
- A number of trays which in our project equal to
twenty trays.
26(No Transcript)
27Gas sweetening column design
- The amine and the acid contacted and the amine
absorb CO2 by chemical reaction. - The loaded Amine (rich amine) with CO2 exit from
the bottom of the tower. - 25 of Amine can be regenerated after sweetening
28Gas sweetening column design
- Circulation rate, gpm
- (K)(MMscfd)(Mole of acid gas)
- (2.05)(3)(1.0) 6.15 gpm
29Gas sweetening column design
- For the diameter we have flow 3MMscfd and the
pressure is 465psig. - I. D. 12 in.
30(No Transcript)
31Main reasons for gas dehydration
- Hydrate formation can plug valves, fittings or
even pipelines. - Corrosion, especially when CO2 and/or H2S are
also present. - Water will condense in the pipelines causing slug
flow and possible erosions.
32Gas dehydration column design
- Glycol injection method.
- Triethelyne glycol (TEG).
- The TEG enters from the top of the dehydrator.
- The wet gas enters from the bottom.
- The dehydrators internals consists of a number
of trays which are twenty trays.
33(No Transcript)
34Gas dehydration column design
- The glycol absorbs the water vapor form the wet
gas. - The dry gas goes out from the top of the
dehydrator. - The wet glycol leaves the dehydrator from the
bottom. - 99 of wet glycol can be regenerated after
dehydration.
35Gas dehydration column design
- For the diameter we have flow 3MMscfd and the
pressure is 480psia. - I. D. 2 ft
36(No Transcript)
37Conclusions
- Data was collected from Dubai Petroleum Company
- Two separators were designed for the system
- Gas dehydration and sweetening columns were also
designed. - The final plant products were sweet methane gas,
NGL, Water, Carbon dioxide - HYSYS was found a powerful software