Group member : - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

Group member :

Description:

Gas dehydration column design Glycol injection method. Triethelyne glycol (TEG). The TEG enters from the top of the dehydrator. The wet gas enters from the bottom. – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 38
Provided by: Mans153
Category:

less

Transcript and Presenter's Notes

Title: Group member :


1
United Arab Emirates UniversityCollege of
EngineeringChemical petroleum Engineering
Design of Oil Production Surface Facilities
  • Group member
  • Mansoor Sulaiman AlBalooshi
    200308910
  • Saleh Salem AlAmeri
    200235706
  • Ahmed Mohamed Obaid
    200209570
  • Advisor Dr Mohamed Al Nakoua

2
Acknowledgments
  • We would like to thank
  • Dr. Mohammed Al Nakoua - our advisor.
  • Dr. Ahmed Gaouda - our coordinator.

3
Contents
  • Objective.
  • Introduction.
  • Plant Design.
  • Material Balance.
  • Separators Design.
  • Gas Sweetening Column Design.
  • Gas Dehydration Column Design.
  • Conclusions.

4
Objective
  • Design a plant for separation and treatment of
    petroleum fluids.

5
Introduction
  • Data
  • Dubai Petroleum Company.
  • MARGAM field which is an onshore field.
  • It is a gas field.

6
Plant Design
7
(No Transcript)
8
Material Balance
  • Material balance was carried out using HYSYS
    program on
  • First separator.
  • Second separator.
  • Mixing point.

9
Material Balance for first separator
  • Flow rate of natural gas
  • 125 MMSCFD
  • 6241.753 Kgmole/hr

10
Component Stream3 (kgmole/hr) Stream2 Kgmole/hr Stream4 Kgmole/hr
H2O 0.53 1.515 2328.531
N2 6.5191 18.435 H.C. 2.747
CO2 16.1001 19.446 -
C1 1001.1575 2385.505 -
C2 109.5017 66.923 -
C3 86.5833 22.476 -
iC4 26.743 3.788 -
C4 40.3151 4.546 -
iC5 20.5423 1.263 -
C5 16.0631 0.758 -
C6 17.8126 0.253 -
C7 43.7242 0.505 -
Total 1385.592 2525.413 2331.28
11
Component Stream5 (kgmole/hr) Stream6 Kgmole/hr Stream7 Kgmole/hr
H2O - 0.5299 0.0001
N2 - - 6.5191
CO2 16.1 - -
C1 1001.1575 - -
C2 6.101 - 103.4007
C3 - - 86.5833
iC4 - - 26.743
C4 - - 40.3151
iC5 - - 20.5423
C5 - - 16.0631
C6 - - 17.8126
C7 - - 43.7242
Total 1023.359 0.5299 361.7035
12
Component Stream2 (kgmole/hr) stream5 (kgmole/hr) Stream8 (kgmole/hr)
H2o 1.515 - 1.515
N2 18.434 - 18.434
CO2 19.446 16.1 35.546
C1 2385.505 1001.1575 3386.6625
C2 66.923 6.101 73.024
C3 22.476 - 22.476
iC4 3.788 - 3.788
C4 4.546 - 4.546
iC5 1.263 - 1.263
C5 0.758 - 0.758
C6 0.253 - 0.253
C7 0.505 - 0.505
Total 2525.413 1023.359 3548.772
Stream2
Stream8
Stream5
13
Separators Design
  • Horizontal separator
  • Two separators were designed

14
Procedure for sizing separator
  • Calculate CD
  • Vt 0.0119 (?L ?g/?g) dm/CD
  • Re 0.0049 ?g dmVt/ µg
  • CD 24/Re 3/(Re)0.5 0.34
  • First assumption for CD is 0.34

15
Procedure for sizing separator (continue)
  • Calculating Z
  • Tpc 170.5307.3 S.G
  • Ppc709.6-58.7 S.G
  • PPr P/ Ppc
  • Tpr T/ Tpc

16
Procedure for sizing separator (continue)
17
Procedure for sizing separator (continue)
  • Gas Capacity Constraint
  • dLeff 420 TZ(Qg/P) (?L ?g/?g)
    (CD/dm)0.5

18
Procedure for sizing separator (continue)
  • liquid Capacity Constraint and seam to seam
    length
  • d2Leff tr QL /0.7
  • Lss Leff d/12 (for gas capacity)
  • Lss 4/3 Leff (for liquid capacity)

19
Procedure for sizing separator (continue)
20
Data
T,oR P,psia Qg,MMscfd QL , bbl/d µg, Cp tr,min dm,micron
560 1002 125 3000 0.013 2 100
?L 62.43 lbm/ft3
?g2.7((S.Gg)P/TZ) 4.34 lbm/ft3
21
Sizing first separator
  • By iteration CD is found to be 1.004
  • Z 0.78

d,in Gas Leff,ft Liquid Leff,ft Lss (gas),ft Lss(liquid),ft 12 Lss/d
24 26.616 14.881 28.616 35.489 17.744
30 21.293 9.524 23.793 28.391 11.356
36 17.744 6.614 20.744 23.659 7.886
42 15.209 4.859 18.709 20.279 5.794
48 13.308 3.72 17.308 17.744 4.436
A 48-in diameter 18-ft length separator provides
about two minutes retention time
22
Sizing second separator
  • Data

P,psia T,oR µg,Cp (S.G)g QL,bbl/d Qg,MMscfd dm,in tr,min
480 510 0.01 0.9 1.5 0.7 100 3
Z 0.81 ?L 62.43 lbm/ft3 ?g 2.824 lbm/ft3
CD 1.003
23
Sizing second separator (continue)
d,in Gas Leff,ft Liquid Leff,ft Lss (gas),ft Lss(liquid),ft 12 Lss/d
36 0.23 0.011 6 0.306 3
A 24-in (3-ft) diameter 6-ft length separator
provides about three minutes retention time
24
Reason for sweetening Natural gas
  • To meet sales specifications.
  • To prevent corrosion.
  • To allow less costly metallurgy.
  • To remove toxicity hazards. (H2S).

25
Gas sweetening column design
  • Monoethanolamine (MEA) as a reactive solvent.
  • Amine enters the top of the sweetening tower.
  • The acid gas enters from the bottom of the tower.
  • A number of trays which in our project equal to
    twenty trays.

26
(No Transcript)
27
Gas sweetening column design
  • The amine and the acid contacted and the amine
    absorb CO2 by chemical reaction.
  • The loaded Amine (rich amine) with CO2 exit from
    the bottom of the tower.
  • 25 of Amine can be regenerated after sweetening

28
Gas sweetening column design
  • Circulation rate, gpm
  • (K)(MMscfd)(Mole of acid gas)
  • (2.05)(3)(1.0) 6.15 gpm

29
Gas sweetening column design
  • For the diameter we have flow 3MMscfd and the
    pressure is 465psig.
  • I. D. 12 in.

30
(No Transcript)
31
Main reasons for gas dehydration
  • Hydrate formation can plug valves, fittings or
    even pipelines.
  • Corrosion, especially when CO2 and/or H2S are
    also present.
  • Water will condense in the pipelines causing slug
    flow and possible erosions.

32
Gas dehydration column design
  • Glycol injection method.
  • Triethelyne glycol (TEG).
  • The TEG enters from the top of the dehydrator.
  • The wet gas enters from the bottom.
  • The dehydrators internals consists of a number
    of trays which are twenty trays.

33
(No Transcript)
34
Gas dehydration column design
  • The glycol absorbs the water vapor form the wet
    gas.
  • The dry gas goes out from the top of the
    dehydrator.
  • The wet glycol leaves the dehydrator from the
    bottom.
  • 99 of wet glycol can be regenerated after
    dehydration.

35
Gas dehydration column design
  • For the diameter we have flow 3MMscfd and the
    pressure is 480psia.
  • I. D. 2 ft

36
(No Transcript)
37
Conclusions
  • Data was collected from Dubai Petroleum Company
  • Two separators were designed for the system
  • Gas dehydration and sweetening columns were also
    designed.
  • The final plant products were sweet methane gas,
    NGL, Water, Carbon dioxide
  • HYSYS was found a powerful software
Write a Comment
User Comments (0)
About PowerShow.com