Update on FCPS Construction/Renovation Projects - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Update on FCPS Construction/Renovation Projects

Description:

... information pertaining to lead abatement ALL abatement work will be conducted when students are NOT present in the building ... Adaptive Reuse Architect: Lucas ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 26
Provided by: LisaC85
Category:

less

Transcript and Presenter's Notes

Title: Update on FCPS Construction/Renovation Projects


1
Update on FCPS Construction/Renovation Projects
  • March 2009

2
Cassidy Elementary Renovation
  • Architect Tate.Hill.Jacobs Architects
  • General Contractor D.W. Wilburn, Inc.
  • Substantial Completion Date August, 2010
  • Contract Sum 11,069,360
  • Change Orders to Date 0
  • Current Phase 1

3
Cassidy Elementary Renovation
  • Rendering of Final Façade

4
Cassidy Elementary Renovation
  • March 4 Pre-construction meeting held at school
    with Owner, A/E Team and construction
    personnel
  • March 9 Begin on-site staging with setting of
    office trailer and fencing by GC
  • March 16 Site demolition in area of new
    addition, including removal of existing
    portable classroom and location of utilities
    Movement of 4 classrooms to portables
  • March 23 Earth excavation for foundation systems
    of new addition Prepare gym stage area for
    demolition
  • March 30 Demolition of gym stage area over
    spring break

5
Cassidy Elementary Renovation
  • Abatement Issues
  • Asbestos abatement will begin spring break and
    continue throughout course of project, as needed
  • Lead no abatement activities at this time but
    will be addressed throughout course of project,
    as needed
  • Information will be sent this week providing
    parents of younger children with information
    pertaining to lead abatement
  • ALL abatement work will be conducted when
    students are NOT present in the building

6
Cassidy Elementary Renovation
  • Staging Area
  • View to Portables

View from Portables
Demo Work
7
Russell Cave Elementary Renovation
  • Architect Pearson Peters Architects
  • General Contractor Congleton-Hacker
    Construction
  • Substantial Completion Date August, 2010
  • Contract Sum 5,001,150
  • Change Orders to Date 0
  • Current Phase 1

8
Russell Cave Elementary Renovation
  • Rendering of Final Façade

9
Arlington Elementary Renovation
  • Architect RossTarrant Architects
  • General Contractor Set to bid on April 21
  • Substantial Completion Date August, 2010
  • Contract Sum TBD
  • Change Orders Pending 36,900 (1)
  • Current Phase Demolition

10
Arlington Elementary Renovation
  • Rendering of Final Façade

11
Arlington Elementary Renovation
  • February 2 Phase A demolition begins at
    Arlington Elementary School site
  • March 4 Phase A progress meeting high water
    table is documented, demolition scope is 75
    complete Excavation of debris continues
  • March 10 Demolition of gymnasium is submitted as
    a change order and pricing approved
  • March 13 Gymnasium is taken down and on-site
    refuse continues to be excavated
  • March 30 Phase B plans to advertise for bid.
    Phase B includes the remainder of the scope
    of the addition/renovation project
  • April 3 Substantial completion of Phase A is
    set for review
  • April 15 Final completion of Phase A. Site
    turned over to FCPS until award of Phase B
    contract

12
Arlington Elementary Renovation
  • Demo Main Bldg.
  • Demo Main Bldg.

Demo Gym
Demo Gym
13
Bryan Station Middle Renovation
  • Architect Clotfelter-Samokar Architects
  • General Contractor Preston Construction Group
  • Substantial Completion Date August, 2010
  • Contract Sum 10,769,400
  • Change Orders to Date 0
  • Current Phase Phase 1 to begin June 1

14
Bryan Station Middle Renovation
  • Rendering of Final Façade

15
Leestown Middle Renovation
  • Architect Lucas/Schwering Architects
  • General Contractor Set to bid on April 9
  • Substantial Completion Date August, 2010
  • Contract Sum TBD
  • Change Orders to Date 0
  • Current Phase N/A

16
Leestown Middle Renovation
  • Rendering of Final Façade

17
Lafayette High Stadium Replacement
  • Architect Strand Associates
  • General Contractor Set to bid mid-July
  • Substantial Completion Date July, 2010
  • Contract Sum TBD
  • Change Orders to Date 0
  • Current Phase Construction Documents

18
Lafayette High Stadium Replacement
  • Rendering of Stadium

19
Central Bus Garage Adaptive Reuse
  • Architect Lucas/Schwering Architects
  • General Contractor Set to bid on April 23
  • Substantial Completion Date August, 2009
  • Contract Sum TBD
  • Change Orders to Date 0
  • Current Phase Construction Documents

20
Central Bus Garage Adaptive Reuse
  • Façade

21
Central Bus Garage Adaptive Reuse
  • Proposed Floor Plan

22
2009 District Facilities Plan
  • Approved by
  • Kentucky Board of Education
  • February 2009

23
2009 District Facilities Plan
  • 2009-10 Projects
  • New Elementary _at_ Keithshire
  • Equine/Agriscience Center
  • Clays Mill Elementary Renovation
  • Tates Creek Middle Renovation
  • Yates Elementary Renovation

24
2009 District Facilities Plan
  • 2010-11 Projects
  • Breckinridge Elementary Renovation
  • Cardinal Valley Elementary Renovation
  • Mary Todd Elementary Renovation
  • Millcreek Elementary Renovation

25
Tonights Agenda Items
Project Agenda Item
? Clays Mill Elementary Approval of Design Consultant Clotfelter-Samokar Architects
? Yates Elementary Approval of Design Consultant ShermanCarterBarnhart Architects
? Tates Creek Middle Approval of Design Consultant RossTarrant Architects
? Elementary _at_ Keithshire Approval of Design Consultant GBBN Architects
? Equine/Agriscience Center Approval of Design Consultant Tate.Hill.Jacobs Architects
? Arlington Elementary Approval of Change Order 1Demolition of Gym 36,900
? Central Bus Garage Approval of Construction Documents Advertisement for Bids 6,039,531
? Bryan Station Middle Approval of Bid, Revised BG-1 GC Contract Preston Construction Group 10,769,400 Total Project Cost 13,345,600
Write a Comment
User Comments (0)
About PowerShow.com