Title: Update on FCPS Construction/Renovation Projects
1Update on FCPS Construction/Renovation Projects
2Cassidy Elementary Renovation
- Architect Tate.Hill.Jacobs Architects
- General Contractor D.W. Wilburn, Inc.
- Substantial Completion Date August, 2010
- Contract Sum 11,069,360
- Change Orders to Date 0
- Current Phase 1
3Cassidy Elementary Renovation
- Rendering of Final Façade
4Cassidy Elementary Renovation
- March 4 Pre-construction meeting held at school
with Owner, A/E Team and construction
personnel - March 9 Begin on-site staging with setting of
office trailer and fencing by GC - March 16 Site demolition in area of new
addition, including removal of existing
portable classroom and location of utilities
Movement of 4 classrooms to portables - March 23 Earth excavation for foundation systems
of new addition Prepare gym stage area for
demolition - March 30 Demolition of gym stage area over
spring break
5Cassidy Elementary Renovation
- Abatement Issues
- Asbestos abatement will begin spring break and
continue throughout course of project, as needed - Lead no abatement activities at this time but
will be addressed throughout course of project,
as needed - Information will be sent this week providing
parents of younger children with information
pertaining to lead abatement - ALL abatement work will be conducted when
students are NOT present in the building
6Cassidy Elementary Renovation
View from Portables
Demo Work
7Russell Cave Elementary Renovation
- Architect Pearson Peters Architects
- General Contractor Congleton-Hacker
Construction - Substantial Completion Date August, 2010
- Contract Sum 5,001,150
- Change Orders to Date 0
- Current Phase 1
8Russell Cave Elementary Renovation
- Rendering of Final Façade
9Arlington Elementary Renovation
- Architect RossTarrant Architects
- General Contractor Set to bid on April 21
- Substantial Completion Date August, 2010
- Contract Sum TBD
- Change Orders Pending 36,900 (1)
- Current Phase Demolition
10Arlington Elementary Renovation
- Rendering of Final Façade
11Arlington Elementary Renovation
- February 2 Phase A demolition begins at
Arlington Elementary School site - March 4 Phase A progress meeting high water
table is documented, demolition scope is 75
complete Excavation of debris continues - March 10 Demolition of gymnasium is submitted as
a change order and pricing approved - March 13 Gymnasium is taken down and on-site
refuse continues to be excavated - March 30 Phase B plans to advertise for bid.
Phase B includes the remainder of the scope
of the addition/renovation project - April 3 Substantial completion of Phase A is
set for review - April 15 Final completion of Phase A. Site
turned over to FCPS until award of Phase B
contract
12Arlington Elementary Renovation
Demo Gym
Demo Gym
13Bryan Station Middle Renovation
- Architect Clotfelter-Samokar Architects
- General Contractor Preston Construction Group
- Substantial Completion Date August, 2010
- Contract Sum 10,769,400
- Change Orders to Date 0
- Current Phase Phase 1 to begin June 1
14Bryan Station Middle Renovation
- Rendering of Final Façade
15Leestown Middle Renovation
- Architect Lucas/Schwering Architects
- General Contractor Set to bid on April 9
- Substantial Completion Date August, 2010
- Contract Sum TBD
- Change Orders to Date 0
- Current Phase N/A
16Leestown Middle Renovation
- Rendering of Final Façade
17Lafayette High Stadium Replacement
- Architect Strand Associates
- General Contractor Set to bid mid-July
- Substantial Completion Date July, 2010
- Contract Sum TBD
- Change Orders to Date 0
- Current Phase Construction Documents
18Lafayette High Stadium Replacement
19Central Bus Garage Adaptive Reuse
- Architect Lucas/Schwering Architects
- General Contractor Set to bid on April 23
- Substantial Completion Date August, 2009
- Contract Sum TBD
- Change Orders to Date 0
- Current Phase Construction Documents
20Central Bus Garage Adaptive Reuse
21Central Bus Garage Adaptive Reuse
222009 District Facilities Plan
- Approved by
- Kentucky Board of Education
- February 2009
232009 District Facilities Plan
- 2009-10 Projects
- New Elementary _at_ Keithshire
- Equine/Agriscience Center
- Clays Mill Elementary Renovation
- Tates Creek Middle Renovation
- Yates Elementary Renovation
242009 District Facilities Plan
- 2010-11 Projects
- Breckinridge Elementary Renovation
- Cardinal Valley Elementary Renovation
- Mary Todd Elementary Renovation
- Millcreek Elementary Renovation
25Tonights Agenda Items
Project Agenda Item
? Clays Mill Elementary Approval of Design Consultant Clotfelter-Samokar Architects
? Yates Elementary Approval of Design Consultant ShermanCarterBarnhart Architects
? Tates Creek Middle Approval of Design Consultant RossTarrant Architects
? Elementary _at_ Keithshire Approval of Design Consultant GBBN Architects
? Equine/Agriscience Center Approval of Design Consultant Tate.Hill.Jacobs Architects
? Arlington Elementary Approval of Change Order 1Demolition of Gym 36,900
? Central Bus Garage Approval of Construction Documents Advertisement for Bids 6,039,531
? Bryan Station Middle Approval of Bid, Revised BG-1 GC Contract Preston Construction Group 10,769,400 Total Project Cost 13,345,600