Title: Public Private Partnerships Case Studies
1Public Private PartnershipsCase Studies
Jim HatterInnovative Finance Technical Service
Team
Federal Highway Administration-National Resource
Center
2Presentation Outline
- Why PPP
- Leasing of Public Assets
- Case Studies
- Summary
3Why Public Private Partnerships?
- Challenges facing the nations highways
- Age and deterioration
- Congestion
- Safety
- Needed capital improvements
- Current investment 68 billion/year National
Highway System - Maintain and improve 130-160 billion
4Impact of Inflation
Provided by AAShTO
5Public Private Partnerships
JOSHUA LUTZ / REDUX FOR TIME
6Public Private Partnership (PPP, P3)
- Contractual agreement between public and private
partners which allows more private sector
participation than is traditional. - Alphabet soup construction
- D-B (design-build)
- D-B-B (design-bid-build)
- D-B-F (design-build-finance)
- D-B-O-M-F (design-build-operate-maintain-finance)
- Concession
- Long term lease of public facilities to a private
party the concessionaire
7Partnering More Than Financial Risk
- Share and shift risk
- Private sector expect return for risk
- Public sector Profit is a bad concept
- Public sector adjustment
- Sharing of assets
8Examples of Compensation Provisions
9Public Private Financing
10 Creative Financing Case Study
T495 Capital Beltway HOT Lanes
- 14 mile segment of beltway
- Two HOT lanes each direction
- Variable tolls HOV-3 free
- Replacement of ageing infrastructure (50 bridges)
11 Sources Uses of Funds
Includes 19.2 M Contingency Used
Includes 45.8 M Contingency Used
Funded 5 yrs. Post Construction
Includes 65M Contingency Used from TIFIA and
Equity
11
12TIFIA Debt Service Equity Distributions
T495 Capital Beltway HOT Lanes
Distribution Reserve Release
Assurety Replacement
13Missouri Safe Sound Bridge Program
- Public Private Partnership 400-600 million
- Replacement or rehabilitation of 802 bridges
- 30 year D-B-O-M-F
- 25 year availability payments
- MoDOT Federal-aid bridge funds
- Missouri Bridge Partners
- Zachry American Infrastructure
- Parsons Transportation Group
- Fred Weber Inc.
- Clarkson Construction
- HNTB
- Infrastructure Corporation of America
14Missouri Safe Sound Bridge Program
Responsibilities
Missouri Bridge Partners
MoDOT
- Construction, maintenance, finance
- Pays ROW purchase price
- Pays utilities relocation costs
- Obtains temporary easements
- Draft third-party agreements
- Performs public information
- Provides design design computations
- Participates in bridge ratings
- Makes availability Payments
- Negotiate ROW price
- Review/approve third-party agreements
- Obtain environmental permits
- Verifies completion of milestones
- Performs program wide Public relations
- Conducts bridge inspections ratings
15Port Access ProjectThe Port of Miami Tunnel
16Port AccessImportance of Port
- POM is top international cruise terminal, 10th
international cargo port based on containerized
shipments, and top seaport in Florida based on
dollar volume
- 20.7 billion in imports/exports
- 81,800 jobs
- 5 billion in wages
- 12 billion in economic output
17Port Access Existing truck routes through
Downtown Miami
- Must go through 6 to 7 signals inbound and
outbound
18Port AccessTruck traffic will increase
- Nearly 5,500 trucks buses travel to/from POM
through downtown streets - By 2030, estimated truck traffic
will nearly double
19Port AccessYears of Planning
- Since 1979, improved access to Port of Miami seen
as necessity - Nearly every option explored
- In 1989, FDOT analyzed eight alternatives in
Project Development Environmental (PD E) study
20Port AccessOption Selected
- Tunnel under main channel of Government Cut
- Roadway work on Dodge and Watson Islands
- MacArthur Causeway Bridge widening
21Port AccessBuilding the Tunnel
- Involves specially-constructed Tunnel Boring
Machine approx. 42 ft. high - TBM consists of cutter head and trailing support
gear - Excavation will take just over one year6 months
in each direction
22Port Access FDOT Procurement Schedule
- December 5, 2005 Industry Forum (D-B-O-M-F)
- February 17, 2006 Releases Request for
Qualifications - April 12, 2006 Receives Statement of
qualifications from potential bidders - April 28, 2006 Announces short-list of bidders
- November 1, 2006 Publishes Request for Proposals
- March 5, 2007 Receives proposals from
- 3 short-listed bidders
- May 2, 2007 Best Value Proposal named MAT
under intent to award subject to local
funding - Next Step MAT (Miami Access Tunnel)
- Contract execution
23Port AccessTunnel PPP Agreement
- 35-year agreement between FDOT concessionaire
- FDOT begins availability payments once tunnel
opens, adjusted for inflation - Estimated to be 2012
- Payment subject to reduction if tunnel not
operational during required hours - Tunnel will be returned to FDOT in first-class
condition at end of contract
24Port Access Project Capital Cost
- Top Ranked Proposal capital and related cost -
665 million - 150 million for risk reserve for geology risk
and related items - 50 million for project inspection
- Total capital cost - 865 million (FDOT cost
estimate at 1.2 billion)
25Port Access Construction Schedule
- Upon execution of Concession Agreement, FDOT will
issue a Notice to Proceed design - MAT will have nine-month period to begin
construction - In RFP response, MAT stipulated a 47-month
construction schedule - MAT must meet defined construction period
26Port Access Construction Schedule
27Port AccessFunding the POMT
- FDOT contributing 50 of capital cost (432.5
million) from Strategic Intermodal System (SIS)
funds - Local partners must match capital costs
- FDOT funding tunnel Operations Maintenance from
statewide maintenance funds (about 200 million
over 30 years)
28Port AccessFunding the POMT
- Cash Flow
- 100 million during construction
- 350 million upon POMT completion
- Remaining in annual availability payment
- Covers both remaining capital and annual
operations and maintenance costs - Proposal at 33 million in 2007 dollars (FDOT
estimate at 68 million) - Amount will adjust based on annual inflation
29In Summary
- USDOT SAFTEALU support PPP
- PPP is not for every Project
- Educate the Public
- www.fhwa.dot.gov/ppp
- Manuel for using PPPs
- PPP Toolkit
30Questions