Title: TUNISIA
1TUNISIA
- Status of the National Nuclear Infrastructure
Development - in Tunisia
Jomâa SOUISSI, Ing. Société Tunisienne de
l'Électricité et du Gaz
Prof. Adel Trabelsi Centre National des Sciences
et Technologies Nucléaires
IAEA 09 12 February 2010
2Country Overview
- Area 162 155 km²
- Population 10.3 millions
- Population density 63.7 inhabitants/km²
- Urban Population 65.8
- GDP 37 Billions of current US
- GDP per capita 7534 PPP US
3DECISION FACTORS FOR NUCLEAR POWER Energy demand
4DECISION FACTORS FOR NUCLEAR POWER Energy mix
Diversification of sources' supply for a better
energetic independence. In 2007, about 85 of the
produced electric energy came from natural gas.
Electricity production by resource / fuel type
5DECISION FACTORS FOR NUCLEAR POWER fossil fuel
deficit
National production of fossil fuel is limited and
will be in deficit from 2015 (for a pessimistic
scenario without considering eventually the
discoveries of new fields).
6Plans and scenarios
- The optimization study was carried out with WASP
model, shows the following preliminary scenario - 400 MW combined cycle from 2011 to 2022
- First 1000 MW NPP by 2023
- First 600 MW units of coal production from 2024
to 2029 - Second 1000 MW NPP by 2030.
- Gradual downgrading of thermal
- The total installed capacity will be 11.8 GW by
the 2031 for a foreseen total demand of about
48,3 TWh, production of 54,3 TWh and a peak of
approximately 9.7 GW.
7Local industry integration and job creation
- The nuclear option introduction is seen as a
favorable opportunity to develop the countrys
industry, enhance the industrial activities and
boost theier quality aspects. - STEG had established, since 1970s, industrial
subsidiaries (SACEM, SIAME, STE) which had been
afterward privatized. - For large STEG thermal power projects, the use of
local subcontractors have been always highly
encouraged and positively quoted in the bid
evaluation.
8Government Commitment
- On November 03rd 2006, the President of the
Republic commanded the state owned Electricity
Utility (STEG) to conduct the preliminary studies
for an NPP introduction in collaboration with the
Ministry of Higher Education, Scientific Research
and Technology (in charge of the nuclear
applications promotion.)
9NATIONAL STRATEGIC ACTION PLAN
- THE STRATEGIC ACTION PLAN (SAP) WAS ELABORATED
following THE 19 AGENCY MILESTONES (NG-G.3.1) TO
DETERMINE OUR TARGETS AND OBJECTIVES TO ACHIEVE
OUR GOAL - THE SAP DEFINES ALSO THE RESPONSIBILITIES OF
DIFFERENT ACTORS FOR EACH OBJECTIVE TO BE
REALIZED AND THE PERFORMANCE INDICATOR FOR IT.
10NATIONAL STRATEGIC ACTION PLAN
- SEVERAL INTERRELATED ACTIVITIES CONSIDERED IN 3
MAJOR PHASES - CONSIDERATIONS BEFORE A DECISION TO LAUNCH A NPP
PROGRAM ARE TAKEN - PREPARATION WORK FOR THE CONSTRUCTION OF A NPP
AFTER A POLICY DECISION HAS BEEN MADE - ACTVITIES TO IMPLEMENT THE FIRST NPP
11NATIONAL STRATEGIC ACTION PLAN
- AT THE END OF EACH PHASE 3 MILESSTONES
- 1. READY TO MAKE A KNOWLEDGEABLE COMMITMENT TO A
NUCLEAR PROGRAMME - 2. READY TO INVITE BIDS FOR THE FIRST NPP
- 3. READY TO COMMISSION AND OPERATE THE FIRST NPP
12NATIONAL STRATEGIC ACTION PLAN
- THE SAP ALLOWS UNDERSTANDING THE NEED FOR
DEVELOPMENT AND ESTABLISHMENT THE OTHERS ASPECTS - HUMAN RESSOURCES DEVELOPMENT
- COMMUNICATION PLAN WITH STAKEHOLDERS
- FUEL CYCLE STRATEGY (PROCUREMENT POLICY, DISPOSAL
...) - NUCLEAR MATERIAL MANAGEMENT PLAN, etc
- THE SAP HAS BEEN REVIEWED AND VALIDATED BY
IAEA ON APRIL 2009 FOR PHASE 1
13APPROACH and PLANNING
- (PRE-) FEASABILITY STUDY
- SEVERAL ACTIVITIES ACHIEVED BY THE STEG PROJECT
TEAM - ECONOMIC STUDY,
- FINANCIAL ASPECTS,
- ELECTRIC SUPPLY NETWORK, etc
- ENERGY PLANNING IN COLLABORATION WITH THE IAEA
AND INTERNATIONAL EXPERTS. - THE NATIONAL PRELIMINARY ENERGY LANNING
PROGRAMME WILL BE ESTABLISHED AND FINALIZED ON
JUNE 2010 TAKING INTO CONSIDERATION THE
RENEWABLE ENERGIES UTILISATION AS INPUT FOR THE
NATIONAL ENERGY MIX.
14APPROACH and PLANNING
- REALISATION OF ACTIVITIES BY NATIONAL
INSTITUTIONS (CNSTN, CNRP, ANME, INM, ) AND
ENGINEERING DEPARTMENTS IN COLLABORATION WITH
FOREIGN COUNTRIES - A- PARTICIPATION OF NATIONAL INDUSTRIAL
SECTOR TO THE NPP PROJECT IMPLEMENTATION,
SECURITY, SAFETY AND PHYSICAL PROTECTION, etc - B- SITES STUDIES
- UNDER THE PHASE 1 OF NPP TWO CANDIDATE
SITES HAVE BEEN SELECTED AND APPROVED BY
AUTHORITIES AMONG ABOUT 19 INITIALY IDENTIFIED.
15APPROACH and PLANNING
- THESE STUDIES ARE BEEING CARRIED OUT BY NATIONAL
SPECILIZED ORGANISATION (CNSTN, CNRP, ANME, INM,
) AND ENGINEERING FIRMS, WITH FOREIGN ASSISTANCE - THE MAJORITY OF THE ACTIVITIES OF THE TWO SITE
EVALUATION STUDY ARE PERFORMED BY THE STEGs
TEAM AND NATIONAL INSTITUTIONS (CNSTN, CNRP,
ANME, INM, ) - IN THIS CONTEXTE THE STEGs TEAM WILL GET
INTERNATIONAL ASSISTANCE FROM FOREIGN FIRMS
(AFNI,) UNDER A BILATERAL AGREEMENT .
16APPROACH and PLANNING
- REALISATION OF ACTIVITIES BY INTERNATIONAL
SPECILIZED ENGINEERING COMPANIES - - FUEL CYCLE AND RADIOACTIVE WASTE MANAGEMENT,
- REACTOR TECHNOLOGY SELECTION,
-
- NPP CONSTRUCTION SCHEDULE,
- INVITATION OF TENDER.
17APPROACH and PLANNING
- SITE - RISKS OF FLOODS,
- INDUCED HUMAN ACTIVITIES ASSESMENT,
- INFRASTRUCTURE,
- CONSTRUCTION MATERIAL
- ASSESMENT OF ENVIRONMENTAL IMPACTS,
- THE FOREINS FIRMS WILL UNDERTAKE THE
OVERALL OF THE SITE STUDIES RESPONSIBILITY USING
THE DATA COLLECTED BY ALL INVOLVED BODIES IN VIEW
TO FINALIZE THE SITE SELECTION PROCESS.
18HUMAN RESSOURCES DEVELOPMENT PROGRAM
- THE TUNISIAN APPROACH FOR HRD HAD DEFINED THE
FOLLOWING OBJECTIVES WHICH SHOULD BE ACHIEVED FOR
RELIABLE SUPPLY OF COMPETENT WORKFORCE - Ensure needed competence,
- Organize work activities,
- Anticipate human resources needs,
- Monitor and continually improve performance
19HUMAN RESSOURCES DEVELOPMENT PROGRAM
- INTEGRATING THE ASSESMENT OF SKILLS AND
COMPETENCES NEEDED THROUGHOUT THE PROJECT LIFE OF
THE PLANNED NPP. - HR DEVELOPMENT STRATEGIC PLAN TAKING INTO
ACCOUNT ALL ORGANIZATIONS INVOLVED AND THE ENTIRE
NPP PROJECT - THIS PLAN SHOWS THE STRATEGY TO TIMELY FILL THE
NEED OF SKILLS FOR EACH PHASE OF THE PROJECT,
INCLUDING THE TRAINING AND THE FOREIGN ASSISTANCE
PROGRAM.
20HUMAN RESSOURCES DEVELOPMENT PROGRAM
- PREPARATION OF THE DECISION 2008-2012 Training
programme for 10 engineers per year in
collaboration with foreign Institutions, - INVITATION TO TENDER AND CONSTRUCTION
2013-2022Training of 50 engineers per year at
national institutions - TWO NATIONAL EDUCATION PROGRAMME FOR MASTER
DEGREE IN NUCLEAR ENERGY AND ENERGY PLANIFICATION
ARE PLANNED FOR THE NEXT ACADEMIC YEAR
(2010-2012)
21 STATUS OF OF THE NATIONAL NUCLEAR POWER
INFRASTRUCTURE
- TO BUILD THE NATIONAL NUCLEAR POWER
INFRASTRUCTURE WE NEED THREE MAIN ACTORS - DECISION MAKERS (Government /Utility)
- TECHNOLOGY HOLDERS (Research Centers,Institutions
, Industry) - INTERNATIONAL COOPERATION
22STATUS OF OF THE NATIONAL NUCLEAR POWER
INFRASTRUCTURE
- IN PARALLEL WITH TECHNICO-ECONOMIC STUDY OF
PHASE1, THE LEGILATIF AND INSTITUTIONAL FRAMEWORK
WAS PERFORMED BY A NATIONAL LEGISLATIF GROUP
WORKING UNDER THE AUSPICES OF The National Atomic
Energy Commission. - THE LEGISLATIF GROUP HAD ACHIEVED THE
FOLLOWING TEXTES - THE NATIONAL NUCLEAR LOW in 2009, including
creation of a National Agency for Radioactive
Waste and Spent fuel Management - THE LOW FOR CREATING THE National Nuclear Energy
Agency (NNEA) - THE LOW FOR CREATING THE National Nuclear Safety
Agency (NNSA- Regulatory Body) - THE NNEA AND NNSA SHOULD BE EFFECTIVE THIS YEAR
2010
23KEY DATES
- ACHIEVEMENT OF FEASIBILITY STUDY2012
- SUPPLYER SELECTION AND CONTRACT AWARD2015
- ENTRY IN FORCE OF CONTRACT Beginning 2016
- POURING THE FIRST STRUCTURE CONCRETE Beginning
2017 - NPP COMMISSIONNG 2023
24CONCLUSION.
- EMBARKING ON A NUCLEAR POWER PROGRAME REQUIRES
LONG TERM COMMITMENTS AND ADEQUATE NUCLEAR
INSTRASTRUCTURE WITH AN EFFECTIVE AND INDEPENDENT
Regulatory Body TO SUPPORT IT, WHICH TUNISIA IS
UNDERTAKING - ALTHOUGH GENERAL GUIDANCE AND CONSIDERATIONS ARE
DERIVED FROM INTERNATIONAL TOOLS (IAEA Guides,
EUR, URD,), TUNISIA IS ESTABLISHING ITS OWN
REQUIREMENTS WITH RESPECT TO ITS NATIONAL
STRATEGY AND CHARACTERISTICS WITH REALISTIC
VISION ABOUT NUCLEAR TECHNOLOGY AVAILABLE FOR
LONG TERM PROJECT.
25- THANK YOU FOR YOUR ATTENTION