Title: Activity-Based Costing and Cost Management Systems
15
Chapter Five
- Activity-Based Costing and Cost Management
Systems
2Traditional, Volume-Based Product-Costing System
- Aerotech produces three complex printed circuit
boards referred to as Mode I, Mode II, and Mode
III. - The following information is obtained from
company records
3Traditional, Volume-Based Product-Costing System
- Additional information includes
Manufacturing overhead is determined as follows
4Traditional, Volume-Based Product-Costing System
5Traditional, Volume-Based Product-Costing System
- With these product costs, Aerotech established
target selling prices (Cost 125).
209.00 x 1.25
6Traditional, Volume-Based Product-Costing System
- Aerotech wishes to see what target selling prices
would be suggested when using activity-based
costing.
Lets see how ABC works.
7Activity Based Costing System (ABC)
- ABC systems follow a two-stage procedure to
assign overhead costs to products.
Assigning overhead to products is a difficult
process.
I agree!
8Activity Based Costing System (ABC)
- ABC systems follow a two-stage procedure to
assign overhead costs to products.
Lets begin by identifying our major activities.
Stage OneIdentify significant activities and
assign overhead costs to each activity
in proportion to resources used.
9Activity Based Costing System (ABC)
- ABC systems follow a two-stage procedure to
assign overhead costs to products.
Overhead assigned to activities are called
activity cost pools.
Stage TwoIdentify cost drivers appropriate to
each activity and allocate overhead to the
products.
10Overhead Costs Total budgeted cost 3,894,000
Identification of Activity Cost Pools
Activity Cost Pools
Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
11Overhead Costs Total budgeted cost 3,894,000
Identification of Activity Cost Pools
Activity Cost Pools
Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
More Cost Pools
12Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
Receiving/Inspection cost pool 200,000
Material-Handling cost pool 600,000
Quality-Assurance cost pool 421,000
Packaging/Shipping cost pool 250,000
13STAGE ONE
Various overhead costs related to machinery
Maintenance
Lubrication
Depreciation
Electricity
Computer Support
Calibration
Activity cost pool
Machinery Cost Pool Total budgeted cost
1,212,600
14STAGE TWO
Calculate the pool rate
Budgeted Machinery Costs 1,212,600
Budgeted Machine Hours 43,000
28.20/hour
Cost Assignment
15STAGE ONE
Calculation of total setup cost
Activity cost pool
Setup Cost Pool Total budgeted cost 3,000
16STAGE TWO
Calculate the pool rate
Budgeted Setup Costs 3,000 Planned
Production Runs 15 runs
200 per run
Cost Assignment
17STAGE ONE
Various overhead costs related to engineering
Engineering salaries
Engineering software
Engineering supplies
Depreciation
Activity cost pool
Engineering Cost Pool Total budgeted cost
700,000
18STAGE TWO
Engineering Cost Pool Total budgeted cost
700,000
Allocate based on engineering transactions
Cost Assignment
19STAGE ONE
Various overhead costs related to
general operations
Plant depr.
Property taxes
Plant mgmt.
Insurance
Plant maint.
Security
Activity cost pool
Facility Cost Pool Total budgeted cost 507,400
20STAGE TWO
Calculate the pool rate
Budgeted Facilities Cost
507,400 Budgeted Direct-Labor Hours
118,000
4.30/hour
Cost Assignment
21Product Cost from ABC
- Here are the new product costs so far . . .
22Other Overhead Costs
23Other Overhead Costs
14.82
24Product Cost from ABC
- These are the new product costs when Aerotech
uses ABC.
25Product Diversity
- Both original and ABC target selling prices are
based on (Cost 125).
The selling price of Mode I and II are
reduced and the selling price for Mode III is
increased.
209.00 1.25
183.44 1.25
26Product Diversity
- Can you identify any problems Aerotech is likely
to face as a result of this distortion?
Traditional costing understates the cost of
complex, low volume products.
27ABC Some Key Issues
- The Past
- Small number of products which did not differ
much in required manufacturing support. - Labor was the dominant element in the cost
structure.
- The Present
- Numerous products with more and complicated
production requirements. - Labor is becoming an ever smaller part component
of total production costs.
28Cost Drivers
- A characteristic of an event or activity that
results in the incurrence of costs. In selecting
a cost driver, we must consider . . .
Degree of Correlation
Behavioral Effects
Cost of Measurement
29Homogeneous Activity Cost Pools
- A homogeneous cost pool is a grouping of overhead
costs in which each cost component is consumed in
roughly the same proportion by each product line.
A homogeneous cost pool uses a single cost driver.
30Transaction Costing
Transaction processing provides
a readily measurable gauge of departmental activit
y.
31Storyboarding
- A procedure used to develop a detailed process
flow chart, which visually represents activities
and the relationships among activities.
Step 1
These are the steps we follow to build a memory
board.
Step 2
Step 3
Step 4
32Direct versus Indirect Costs
- Volume-Based Costing
- All production costs except direct materials and
direct labor are lumped together in one overhead
cost pool.
- Activity-Based Costing
- An effort is made to account for as many costs
as possible as direct costs of production. -
Indirect Costs
33Indicators of Need for ABC
Product-line profit margins are hard to explain
Direct labor is a small percentage of total costs
Line managers do not believe the product costs
reports
Sales are increasing, but profits are declining.
Some products that have reported high profit
margins are not sold by competitors
Marketing does not use costs reports for pricing
decisions
34Optimal Product-Costing System
Cost
Total Cost
High
Cost of inferior decisions resulting from inaccura
te information.
Design, implementation and maintenance costs
Information System Accuracy
Low
High
Low
Optimal system
35Cost Management Systems
Objectives
- Measure the cost of resources consumed.
- Identify and eliminate non-value-added costs.
- Determine the efficiency and effectiveness of all
major activities. - Identify and evaluate new activities that can
improve future performance.
36Non-Value-Added Costs
Suppose our production process looks like this
VA Valued-added activity NVA
Non-value-added activity
37Non-Value-Added Costs
Our goal is to reduce or eliminate the
non-value-added activities.
VA Valued-added activity NVA
Non-value-added activity
38ABC in the Service Industry
Activities tend to be nonrepetitive human tasks.
Implementation Problems
High proportion of facility-level costs
39End of Chapter 5
This is real value-added time!