Activity-Based Costing and Cost Management Systems - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

Activity-Based Costing and Cost Management Systems

Description:

Activity-Based Costing and Cost Management Systems 5 Traditional, Volume-Based Product-Costing System Aerotech produces three complex printed circuit boards referred ... – PowerPoint PPT presentation

Number of Views:116
Avg rating:3.0/5.0
Slides: 40
Provided by: JonA53
Category:

less

Transcript and Presenter's Notes

Title: Activity-Based Costing and Cost Management Systems


1
5
Chapter Five
  • Activity-Based Costing and Cost Management
    Systems

2
Traditional, Volume-Based Product-Costing System
  • Aerotech produces three complex printed circuit
    boards referred to as Mode I, Mode II, and Mode
    III.
  • The following information is obtained from
    company records

3
Traditional, Volume-Based Product-Costing System
  • Additional information includes

Manufacturing overhead is determined as follows
4
Traditional, Volume-Based Product-Costing System
5
Traditional, Volume-Based Product-Costing System
  • With these product costs, Aerotech established
    target selling prices (Cost 125).

209.00 x 1.25
6
Traditional, Volume-Based Product-Costing System
  • Aerotech wishes to see what target selling prices
    would be suggested when using activity-based
    costing.

Lets see how ABC works.
7
Activity Based Costing System (ABC)
  • ABC systems follow a two-stage procedure to
    assign overhead costs to products.

Assigning overhead to products is a difficult
process.
I agree!
8
Activity Based Costing System (ABC)
  • ABC systems follow a two-stage procedure to
    assign overhead costs to products.

Lets begin by identifying our major activities.
Stage OneIdentify significant activities and
assign overhead costs to each activity
in proportion to resources used.
9
Activity Based Costing System (ABC)
  • ABC systems follow a two-stage procedure to
    assign overhead costs to products.

Overhead assigned to activities are called
activity cost pools.
Stage TwoIdentify cost drivers appropriate to
each activity and allocate overhead to the
products.
10
Overhead Costs Total budgeted cost 3,894,000
Identification of Activity Cost Pools
Activity Cost Pools
Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
11
Overhead Costs Total budgeted cost 3,894,000
Identification of Activity Cost Pools
Activity Cost Pools
Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
More Cost Pools
12
Product- Sustaining Level
Unit Level
Batch Level
Facility Level
Machinery cost pool 1,212,600
Setup cost pool 3,000
Engineering cost pool 700,000
Facility cost pool 507,400
Receiving/Inspection cost pool 200,000
Material-Handling cost pool 600,000
Quality-Assurance cost pool 421,000
Packaging/Shipping cost pool 250,000
13
STAGE ONE
Various overhead costs related to machinery
Maintenance
Lubrication
Depreciation
Electricity
Computer Support
Calibration
Activity cost pool
Machinery Cost Pool Total budgeted cost
1,212,600
14
STAGE TWO
Calculate the pool rate
Budgeted Machinery Costs 1,212,600
Budgeted Machine Hours 43,000

28.20/hour


Cost Assignment
15
STAGE ONE
Calculation of total setup cost
Activity cost pool
Setup Cost Pool Total budgeted cost 3,000
16
STAGE TWO
Calculate the pool rate
Budgeted Setup Costs 3,000 Planned
Production Runs 15 runs
200 per run


Cost Assignment
17
STAGE ONE
Various overhead costs related to engineering
Engineering salaries
Engineering software
Engineering supplies
Depreciation
Activity cost pool
Engineering Cost Pool Total budgeted cost
700,000
18
STAGE TWO
Engineering Cost Pool Total budgeted cost
700,000
Allocate based on engineering transactions
Cost Assignment
19
STAGE ONE
Various overhead costs related to
general operations
Plant depr.
Property taxes
Plant mgmt.
Insurance
Plant maint.
Security
Activity cost pool
Facility Cost Pool Total budgeted cost 507,400
20
STAGE TWO
Calculate the pool rate
Budgeted Facilities Cost
507,400 Budgeted Direct-Labor Hours
118,000
4.30/hour


Cost Assignment
21
Product Cost from ABC
  • Here are the new product costs so far . . .

22
Other Overhead Costs
23
Other Overhead Costs
14.82
24
Product Cost from ABC
  • These are the new product costs when Aerotech
    uses ABC.

25
Product Diversity
  • Both original and ABC target selling prices are
    based on (Cost 125).

The selling price of Mode I and II are
reduced and the selling price for Mode III is
increased.
209.00 1.25
183.44 1.25
26
Product Diversity
  • Can you identify any problems Aerotech is likely
    to face as a result of this distortion?

Traditional costing understates the cost of
complex, low volume products.
27
ABC Some Key Issues
  • The Past
  • Small number of products which did not differ
    much in required manufacturing support.
  • Labor was the dominant element in the cost
    structure.
  • The Present
  • Numerous products with more and complicated
    production requirements.
  • Labor is becoming an ever smaller part component
    of total production costs.

28
Cost Drivers
  • A characteristic of an event or activity that
    results in the incurrence of costs. In selecting
    a cost driver, we must consider . . .

Degree of Correlation
Behavioral Effects
Cost of Measurement
29
Homogeneous Activity Cost Pools
  • A homogeneous cost pool is a grouping of overhead
    costs in which each cost component is consumed in
    roughly the same proportion by each product line.

A homogeneous cost pool uses a single cost driver.
30
Transaction Costing
Transaction processing provides
a readily measurable gauge of departmental activit
y.
31
Storyboarding
  • A procedure used to develop a detailed process
    flow chart, which visually represents activities
    and the relationships among activities.

Step 1
These are the steps we follow to build a memory
board.
Step 2
Step 3
Step 4
32
Direct versus Indirect Costs
  • Volume-Based Costing
  • All production costs except direct materials and
    direct labor are lumped together in one overhead
    cost pool.
  • Activity-Based Costing
  • An effort is made to account for as many costs
    as possible as direct costs of production.

Indirect Costs
33
Indicators of Need for ABC
Product-line profit margins are hard to explain
Direct labor is a small percentage of total costs
Line managers do not believe the product costs
reports
Sales are increasing, but profits are declining.
Some products that have reported high profit
margins are not sold by competitors
Marketing does not use costs reports for pricing
decisions
34
Optimal Product-Costing System
Cost
Total Cost
High
Cost of inferior decisions resulting from inaccura
te information.
Design, implementation and maintenance costs
Information System Accuracy
Low
High
Low
Optimal system
35
Cost Management Systems
Objectives
  • Measure the cost of resources consumed.
  • Identify and eliminate non-value-added costs.
  • Determine the efficiency and effectiveness of all
    major activities.
  • Identify and evaluate new activities that can
    improve future performance.

36
Non-Value-Added Costs
Suppose our production process looks like this
VA Valued-added activity NVA
Non-value-added activity
37
Non-Value-Added Costs
Our goal is to reduce or eliminate the
non-value-added activities.
VA Valued-added activity NVA
Non-value-added activity
38
ABC in the Service Industry
Activities tend to be nonrepetitive human tasks.
Implementation Problems
High proportion of facility-level costs
39
End of Chapter 5
This is real value-added time!
Write a Comment
User Comments (0)
About PowerShow.com