Title: SONA
1SONA
T R A N S P O R T I N F R A S T R U C T U R E
P R O J E C T S
DOTC
SUPER REGIONS
NORTHERN LUZON AGRI- BUSINESS QUADRANGLE
LUZON URBAN BELTWAY
CENTRAL PHILIPPINES SUPER REGION
MINDANAO SUPER REGION
2N L A Q
ITBAYAT Airport project
NORTHERN LUZON AGRI-BUSINESS QUADRANGLE
AIRPORT PROJECTS
BATANES
BASCO Airport project
LAL-LO Airport project
BAGABAG Airport project
PORO POINT Airport project
CASIGURAN Airport project
ALAMINOS Airport project
3BASCO AIRPORT DEVELOPMENT PROJECT
Basco, Batanes
As of 15 August 2008
a. RESUFACING OF EXISTING RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P29.40 M- CY 2007, GOP
TIMETABLE Orig 16 Dec 2007 - 13 May 2008
Rev 16 Dec 2007 - 07 July 2008
4BASCO AIRPORT DEVELOPMENT PROJECT
Basco, Batanes
As of 15 August 2008
b. ASPHALT OVERLAY OF RUNWAY APRON, CONST.
OF DRAINAGE SYSTEM, CONST. OF PERIMETER FENCE
IMPLEMENTING AGENCY DOTC
Timetable D.E. Apr 2008 - May 2008 Rev Jun
2008 - Aug 2008
Project Cost P146.1 M - CY 2008, GOP (DOTC)
- BAC Resolution recommending Award of Contract
already approved. - Notice of Award received by the contractor on 31
July 2008. - For contract review and approval.
5BASCO AIRPORT DEVELOPMENT PROJECT
Basco, Batanes
As of 15 August 2008
c. Improvement of Terminal Building and Fire
Station Building
IMPLEMENTING AGENCY DOTC
Timetable D.E. June 2008 - Aug 2008 C.W.
Procurement 08 Sep 2008 - 17 Nov
2008 Implementation 24 Nov 2008 - 21 Feb 2008
Project Cost P3.0 M - CY 2008, GOP (DOTC)
- Preparation of Detailed Estimates and Program of
Works On-going
d. Air Navigational Facilities (ANF)
IMPLEMENTING AGENCY ATO
Timetable D.E. June 2008 - Aug
2008 Equipment Procurement 08 Sep 2008 - 17 Nov
2008 Implementation 24 Nov 2008 - 21 Feb 2008
Project Cost P8.5 M - CY 2008, GOP (CAAP)
- Preparation of Detailed Estimates and Program of
Works On-going
6ITBAYAT AIRPORT DEVELOPMENT PROJECT
Itbayat, Batanes
As of 15 August 2008
a. CONCRETE PAVING OF RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P10.0 M- CY 2007 GOP
TIMETABLE Orig 05 Aug 2007 - 02 Dec 2007
Rev 29 Nov. 2007 - 17 June 2008
7ITBAYAT AIRPORT DEVELOPMENT PROJECT
Itbayat, Batanes
As of 15 August 2008
b. CONT. CONCRETE PAVING OF RUNWAY AND
CONSTRUCTION OF PERIMETER FENCE
IMPLEMENTING AGENCY DOTC
Project Cost P75.0 M - CY 2008, GOP (DOTC)
TIMETABLE D.E. Apr 2008 - May 2008 C.W.
Procurement June 2008 - 25 Aug
2008 Implementation 01 Sep 2008 - 27 June 2008
- Notice of Award (NOA) received by the contractor
on 01 August 2008. - For contract review and approval.
8BAGABAG AIRPORT DEVELOPMENT PROJECT
Bagabag, Nueva Vizcaya
As of 15 August 2008
a. CONSTRUCTION OF FLIGHT SERVICE STATION
IMPLEMENTING AGENCY ATO-ANF
Project Cost P12.5 M - CY 2007, GOP (CAAP)
TIMETABLE Orig 06 June 2007 - 01 Jan 2008
Rev 01 Feb 2007 - 28 Aug 2008
- Construction of FSS building and rehabilitation
of power house is 81.00 completed as of 28 July
2008.
ON-GOING CONSTRUCTION OF TOWER
9BAGABAG AIRPORT DEVELOPMENT PROJECT
Bagabag, Nueva Vizcaya
As of 15 August 2008
b. COMPLETION OF CONCRETE PAVING OF RUNWAY,
APRON, TAXIWAY, VPA ACCESS ROAD AND
CONSTRUCTION OF PERIMETER FENCE
TIMETABLE D.E. Feb 2008 - Mar 2008
Project Cost P78.50 M - CY 2007, GOP (DOTC)
- Notice of Award (NOA) received by the contractor
on 15 August 2008. - For contract review and approval.
c. REHABILITATION OF TERMINAL BUILDING
Timetable D.E. June 2008 - Sep 2008 C.W.
Procurement 08 Sep 2008 - 17 Nov
2008 Implementation 24 Nov 2008 - 21 Feb 2008
Project Cost P5.0 M - CY 2008, GOP (DOTC)
- Preparation of Detailed Estimates and Program of
Work on-going. - Advertised 08 August 2008.
10ALAMINOS AIRPORT DEVELOPMENT PROJECT
Alaminos, Pangasinan
As of 15 August 2008
a. PRE-FEASIBILITY STUDY/MASTER PLAN
IMPLEMENTING AGENCY DOTC
Timetable F.S. Procurement July 2008 - 29 Sep
2008 Implementation 06 Oct 2008 - 03 Apr 2008
Project Cost P7.50 M - CY 2006
- Technical Evaluation Report on the proposals of
the three (3) shortlisted consulting firms for
signature of the TWG members and submission to
BAC.
11CASIGURAN AIRPORT DEVELOPMENT PROJECT
Casiguran, Aurora
As of 15 August 2008
a. REHABILITATION OF AIRSTRIP ( Phase 1 Fencing,
Clearing, Embankment and Sub-base )
IMPLEMENTING AGENCY ATO-AMS
Project Cost P15.0 M - CY 2006, GOP
TIMETABLE Orig March 2007 - July 2007 Rev
July 2007 - Sept. 2007
- COMPLETED - 30 October 2007.
COMPLETED AIRSTRIP
COMPLETED BARBED WIRE FENCE
12CASIGURAN AIRPORT DEVELOPMENT PROJECT
Casiguran, Aurora
As of 15 August 2008
b. CIVIL WORKS-Concreting of Runway, Apron,
Taxiway, Perimeter Fence and Runway Markers
Timetable D.E. Feb 2008 - Mar 2008 C.W.
Procurement 21 Feb 2008 - 25 Mar 2008 Rev 21
Jul 2008 - 08 Sep 2008 Implementation 15 Sep 2008
- 14 Sep 2009
IMPLEMENTING AGENCY ATO-AMS
Project Cost P152.50 M - CY 2008, GOP (CAAP)
- Funds sub-allotted to CAAP on 10 June 2008.
Advertised on 29 July 2008. - Opening of Eligibility held on 14 August 2008.
c. Construction of Terminal Shed and Elevated
Water Tank
IMPLEMENTING AGENCY ATO-AMS
Timetable D.E. 18 July 2008 - 31 July
2008 C.W. Procurement 04 Aug 2008 15 Sep
2008 Implementation 23 Sep 2008 - 23 Mar 2009
Project Cost P4.5 M - CY 2008, GOP
- Bid plans and specifications for revision and
approval. - Funds for transfer to CAAP.
13NORTHERN CAGAYAN AIRPORT PROJECT
Cagayan Valley
As of 15 August 2008
a. FEASIBILITY STUDY / MASTER PLAN
IMPLEMENTING AGENCY DOTC
Timetable Procurement Dec 2007 - Apr
2008 Implementation
Project Cost P7.50 M - CY 2006, GOP (DOTC)
- Notice of Award received by the Contractor on 30
July 2008.
14PORO POINT AIRPORT DEVELOPMENT PROJECT
San Fernando, La Union
As of 15 August 2008
Upgrading of San Fernando Airport (Phase 1)
Construction of Field Office and Facilities,
Control Tower bldg., Power Water Receiving
Station and Renovation of Fire Station Bldg.
IMPLEMENTING AGENCY BCDA
Project Cost P 471.63 M Rev P
471.406 M - GOCC/BCDA
TIMETABLE June 2007 - July 2008
- On-going with 68.15 actual accomplishment as
against target accomplishment of 66.67, ahead by
1.48, as of 31 July 2008. - On-going activities include construction of new
taxiway, extension of runway, new control tower,
rehabilitation of Passenger Terminal and Fire
Station Buildings, construction of Water
Receiving Station Power House Building and
completion of Perimeter Fence. - Also on-going are the provision of utilities
(power, water/fire supply system) and Air
Navigation and Support Facilities.
15PORO POINT AIRPORT DEVELOPMENT PROJECT
San Fernando, La Union
As of 15 August 2008
On-going Construction Control Tower
On-going removal of Hill
On-going renovation of Fire Station Bldg.
On-going Construction of Fence
On-going concreting of existing apron (thickness
of 260mm)
On-going excavation of trapezoidal ditches
channels
On-going Construction of water receiving
On-going Construction of power house
16L U B
South Aurora
LUZON URBAN BELTWAY
South Nueva Ecija
AIRPORT PROJECTS
South Tarlac
South Zambales
DMIA
Pampanga
Bulacan
Polillo Is.
Bataan
Rizal
NCR
NAIA 3
Laguna
Cavite
Batangas
Quezon
Marinduque
Or. Mindoro
Occ. Mindoro
17NINOY AQUINO INTERNATIONAL AIRPORT TERMINAL 3
18NAIA INTERNATIONAL PASSENGER TERMINAL 3
As of 30 June 2008
COMPLETION, REACTIVIATION, TESTING AND
COMMISSIONING ON A TURNKEY BASIS OF NAIA Terminal
3
IMPLEMENTING AGENCY MIAA
TIMETABLE 9 Months from contractors receipt of
NTP
Project Cost P 792.0 M
NAIA PT is now operational.
- On 20 June 2008, actual simulations of arrival
procedures was carried out. The simulation
includes testing of aerobridges and baggage
conveyor for which PAL has agreed to deploy one
Airbus A340 aircraft from its international fleet
for the simulation of a 350 passenger arrival and
departure. - MIAA begin servicing domestic flights of Cebu
Pacific, PAL and Air Philippines starting 23 July
2008. Handling international flights will be
started next year. - With a capacity of 13 million passengers a year,
the new terminal will relieve crowding at the
domestic airport, which handles more than five
(5) million passengers.
19DIOSDADO MACAPAGAL INTERNATIONAL AIRPORT
Clarkfield, Pampanga
As of 30 June 2008
a. PASSENGER TERMINAL 1 REHABILITATION EXPANSION
IMPLEMENTING AGENCY CIAC
Project Cost P 68.0 M - DMIA
Civil Works P
83.5.0 M - DMIA
Equipment
TIMETABLE May 2007 - December 2007 Rev July
2007 - Mar 2008
- COMPLETED on 31 March 2008.and was inaugurated by
PGMA last 4 April 2008. - The DMIA currently operates 39 international
flights per week with an average of 21,000
passengers per day departing and arriving at the
passenger terminal building.
Considering the projected increase in DMIAs
traffic in the coming years, the concern for a
seamless connection between SCTEP-NLEX and SLEX
via C5 as well as the need business districts
(CBDs) was highlighted.
20DIOSDADO MACAPAGAL INTERNATIONAL AIRPORT
Clarkfield, Pampanga
As of 30 June 2008
b. MASTERPLAN PHASE 1
IMPLEMENTING AGENCY CIAC
PHASE 1A - Express freight, Fuel Farm, Heavy
Maintenance (MRO) General Freight Runway Taxiways
PHASE 1A - Passenger Terminal Concourse
Passenger Aircraft Parking Positions Airport
Plaza and GTC Fuel Farm Taxiways Fire Stations
Control Tower
TIMETABLE 2ND qrt of 2007 - Dec 2011 Rev 3rd
qrt of 2008 - Dec 2011
Project Cost P 56.6 B
- KOICA gave 2M technical grant to CIAC for the
Feasibility Studies on the Master/Development
Plan of DMIA. - KOICA submitted the Feasibility Study of the
Terminal 2 to CIAC, CDC with NEDA and DOTC
representatives last 03 June 2008. The complete
Feasibility Study for the whole Phase 1 Project
will be submitted within ten (10) months which
will be in October 2008. - The Invitation to Apply for Eligibility and to
Submit a Proposal to Design, Finance, Construct
and Operate the DMIA Passenger Terminal 2 Project
through a Joint Venture with the CIAC was
published on 11 July 2008. - Submission and Opening of Eligibility Documents ,
Technical and Financial Proposals is scheduled on
29 August 2008.
21DIOSDADO MACAPAGAL INTERNATIONAL AIRPORT
Clarkfield, Pampanga
As of 30 June 2008
b. RADAR APPROACH CONTROL
IMPLEMENTING AGENCY CIAC
TIMETABLE June 2006 - Dec 2006 Rev Sep 2005 -
May 2007
Project Cost P 529.23 M GOCC/ODA
- The Radar System is now fully operational.
22Camarines Norte
CENTRAL PHILIPPINES
SOUTHERN LUZON Airport project
Catanduanes
Camarines Sur
SUPER REGION
Albay
AIRPORT PROJECTS
BULAN Airport project
Sorsogon
Northern Samar
SAN JOSE (carabao Is.) Airport project
Masbate
Samar
Eastern Samar
BUSUANGA Airport project
KALIBO Airport project
Biliran
Aklan
Capiz
GUIUAN Airport project
Leyte
Antique
Iloilo
SAN VICENTE Airport project
TACLOBAN Airport project
Guimaras
Cebu
BACOLOD Airport project
Southern Leyte
Negros Occ.
Bohol
Palawan
PANGLAO Airport project
KABANKALAN Airport project
Siargao
Negros Or.
SIARGAO Airport project
Siquijor
Camiguin
PUERTO PRINCESA Airport project
DUMAGUETE Airport project
Dapitan
BALABAC Airport project
23ILOILO AIRPORT DEVELOPMENT PROJECT
Cabatuan Sta. Barbara, Iloilo
As of 30 June 2008
IMPLEMENTING AGENCY DOTC
TIMETABLE April 2004 March 2007
Project Cost P 8,758.72 B (revised project
cost)
- Project was inaugurated by her Excellency PGMA
last 13 June 2007. - Start of commercial
operation on 14 June 2007.
LANDSIDE
AIRSIDE
APRON
MAIN VEHICULAR PARKING AREA
24ILOILO AIRPORT DEVELOPMENT PROJECT
Cabatuan Sta. Barbara, Iloilo
As of 30 June 2008
b. CONSTRUCTION OF SECURITY FENCE ALONG NIADP
ACCESS ROAD
IMPLEMENTING AGENCY DOTC
Project Cost P34.0 M , CY 2008
- For issuance of eligibility / ineligibility
statement to the responsive bidder.
c. CONSTRUCTION OF SECONDARY ACCESS ROAD
IMPLEMENTING AGENCY DOTC
Project Cost P124.0 M , CY 2008
d. IMPROVEMENT OF ATC INTER-FACILITY DATA
COMMUNICATIONS
IMPLEMENTING AGENCY ATO
Project Cost P5.0 M , CY 2008
25BACOLOD (Silay) AIRPORT DEVELOPMENT PROJECT
Silay City, Negros Occidental
As of 30 June 2008
IMPLEMENTING AGENCY DOTC
TIMETABLE August 2004 - Jan 2008
Project Cost P 4.065 B (revised cost amount
based from approved VO Nos. 1 3)
PTB airside
PTB landside
- Project was inaugurated and opened for operation
on 18 January 2008 - Access Road is completed. Currently utilized for
public use. Schedule for turn-over to LGU-Silay
City.
26BALABAC AIRPORT DEVELOPMENT PROJECT
Balabac, Palawan
As of 30 June 2008
IMPLEMENTING AGENCY DOTC
TIMETABLE July 2007 - October 2007 Rev Mar
2008 - Sept 2008
Project Cost P7.5 M, pump-priming
- On-going with 48.29 accomplishment.
- The study will be completed in Six (6) months.
b. PROJECT IMPLEMENTATION / CIVIL WORKS
- The airport project is for private sector
participation. Recommended for BOT scheme
(solicited proposal). - The Department is still awaiting for official
communications from private sector who may be
interested to develop the project.
Problems / Issues
- The Department has not received yet any
communications from private sector who may be
interested to implement the project.
Recommendation/s
- Discuss with DOTC and DOT regarding the concern.
27BUSUANGA AIRPORT DEVELOPMENT PROJECT
Coron, Busuanga Island, Palawan
As of 30 June 2008
PHASE I Rehabilitation and Improvement of
Existing Facilities including Concreting of Apron
and Runway and Construction of Terminal Building
(Runway Extension 340m x 30m) Apron Concreting
Drainage Canal
a. LOCALLY-FUNDED PROJECT
TIMETABLE January 2007 - August 2007
IMPLEMENTING AGENCY DOTC
Project Cost P40 M, pump-priming CY 2006
- Completed - 30 November 2007.
COMPLETED CONCRETE PAVEMENT
28BUSUANGA AIRPORT DEVELOPMENT PROJECT
Busuanga, Coron Island, Palawan
As of 30 June 2008
b. FS / MP
IMPLEMENTING AGENCY DOTC
TIMETABLE Oct 2007 - March 2008
Project Cost P12.0 M, pump-priming , CY 2006
- On-going with 95 accomplishment. Awaiting for
submission of Final Report by the Consultant.
c. KOICA FUNDS (3 M)
(Runway concreting, (unpaved part), apron(pccp),
fencing, strip grade correction, terminal
building, fire truck, tractor mower, maintenance
vehicle)
IMPLEMENTING AGENCY DOTC
Project Cost P160.0 M -KOICA Grant
TIMETABLE April 2007 - December 2008
- On-going with 92.71 actual accomplishment as
against 85.20, with 7.51 ahead of schedule, as
of 31 July 2008.
29BUSUANGA AIRPORT DEVELOPMENT PROJECT
Busuanga, Coron Island, Palawan
As of 30 June 2008
d. PURCHASE/INSTALLATION OF 1-30 KVA DEGS
IMPLEMENTING AGENCY ATO
Project Cost P0.80 M, CY 2008
30PUERTO PRINCESA AIRPORT DEVELOPMENT PROJECT
Puerto Princesa, Palawan
As of 30 June 2008
PHASE I
a. REHABILITATION AND EXPANSION OF EXISTING
PASSENGER TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Aug 2007 - Mar 2008 Rev
Aug. 2007 - Apr 2008
Project Cost P30.0 M, pump-priming, CY 2006
- Suspended as of 19 December 2007 with 49
accomplishment.
31PUERTO PRINCESA AIRPORT DEVELOPMENT PROJECT
Puerto Princesa, Palawan
As of 30 June 2008
PHASE I
b. CONSTRUCTION OF PERIMETER FENCE AND EXPANSION
OF APRON
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig 05 Oct 2007 - 29 Jan
2008 Rev 05 Oct 2007 - 29 Feb 2008
Project Cost P15.0 M, CY 2007
32PUERTO PRINCESA AIRPORT DEVELOPMENT PROJECT
Puerto Princesa, Palawan
As of 30 June 2008
PHASE 2
a. COMPLETION OF PTB REHABILITATION/EXPANSION
INCLUDING TERMINAL EQUIPMENT/FACILITIES
IMPLEMENTING AGENCY DOTC
TIMETABLE August 2008 - May 2009
Project Cost P15.0 M, DOE-Malampaya Shares
- The Contractor commenced work on 06 August 2008.
b. AIRPORT REDEVELOPMENT
IMPLEMENTING AGENCY DOTC
TIMETABLE 4th quarter 2008 - 1st quarter 2009
Project Cost P 3.202 B DOE-Malampaya Shares
- ROWA is 95 completed.
- NEDA-ICC-CC approved the project on 08 February
2008.
33PUERTO PRINCESA AIRPORT DEVELOPMENT PROJECT
Puerto Princesa, Palawan
As of 30 June 2008
PHASE 2
c. PURCHASE/INSTALLATION OF 16 CHANNELS OF VLS
IMPLEMENTING AGENCY ATO
Project Cost P2.5 M, CY 2008
d. UPGRADING OF MET INSTRUMENT
IMPLEMENTING AGENCY ATO
Project Cost P1.7 M, CY 2008
e. EXPANSION/REHABILITATION OF POWERHOUSE
IMPLEMENTING AGENCY ATO
Project Cost P1.5 M, CY 2008
f. PAF REPLICA WORKS
Project Cost P20.0 M, CY 2008
34SAN VICENTE AIRPORT DEVELOPMENT PROJECT
San Vicente, Palawan
As of 30 June 2008
PHASE I
TIMETABLE Jan 2007 - Dec 2007
a. SITE ACQUISITION
IMPLEMENTING AGENCY DOTC
Project Cost P15 M, Pump-priming, CY 2006
- LGU has already acquired 56 lots, 21 lots on
process for transfer of title and 21 lots under
expropriation.
b. CONSTRUCTION OF AIRSTRIP
(1,200m x 36m runway)
IMPLEMENTING AGENCY DOTC
Project Cost P85.0 M, Malampaya funds
TIMETABLE Orig Mar 2007 - Nov 2007 Rev Mar
2007 - June 2008
35SAN VICENTE AIRPORT DEVELOPMENT PROJECT
San Vicente, Palawan
As of 30 June 2008
PHASE 2
a. CONTINUATION OF CONSTRUCTION OF AIRSTRIP
(1,800m x 45m runway)
IMPLEMENTING AGENCY DOTC
TIMETABLE 28 Jan 2008 - 02 Dec 2008
COST P100.0M, CY 2006, Malampaya funds
- On-going with 76.41 actual accomplishment.
36SAN VICENTE AIRPORT DEVELOPMENT PROJECT
San Vicente, Palawan
As of 30 June 2008
PHASE 3
a. CONSTRUCTION OF APRON AND TAXIWAY
(Apron 150m x 95m) (Taxiway 18m x 95m)
IMPLEMENTING AGENCY DOTC
Project Cost P50.0M, CY 2007
TIMETABLE 31 Oct 2007 - 27 May 2008 Rev 31
Oct 2007 - 23 July 2008
- On-going with 96.82 actual accomplishment.
PHASE 4
a. PRELIMINARY ENGINEERING STUDY / FS
IMPLEMENTING AGENCY DOTC
TIMETABLE 07 Sep 2007 - Feb 2008 Rev 07 Sept
2007 - 31 July 2008
Project Cost P6.0M, CY 2006, pump-priming
- On-going with 95 accomplishment.
- Awaiting for the submission of Final Report.
b. CONCRETING OF RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P50.0M, CY 2008
37SAN JOSE AIRPORT DEVELOPMENT PROJECT
Carabao Island, Romblon
As of 30 June 2008
Project Cost P303.0 M, GOP/PSP
- The airport project is for private sector
participation. - Recommended for BOT scheme (unsolicited
proposal).
Problems / Issues
- No private sector interested yet to do this BOT
project thus delaying its implementation.
38BULAN AIRPORT DEVELOPMENT PROJECT
Bulan, Sorsogon
As of 30 June 2008
a. SITE ACQUISITION FOR RUNWAY EXTENSION
Implementing Agency DOTC
TIMETABLE Orig Dec 2006 - Dec 2007 Rev Dec
2006 - Dec 2008
Project Cost P15.0 M,, Pump-priming CY 2005
- Development Bank of the Philippines (DBP) issued
a fair market value of lot amounting to Php
200,000/hectare.
b. UPGRADING OF RUNWAY
Implementing Agency DOTC
TIMETABLE Nov 2007 - May 2008
Project Cost P55.0 M, CY 2007
c. CONCRETE PAVING OF RUNWAY, CONSTRUCTION OF
APRON TAXIWAY, PERIMETER FENCE AND DRAINAGE
SYSTEM
Project Cost P85.0 M, CY 2008
- Submission and Opening of Bids is scheduled on 04
September 2008.
39SOUTHERN LUZON INTERNATIONAL AIRPORT DEVELOPMENT
PROJECT
(BICOL INTERNATIONAL AIRPORT )
Daraga, Camarines Sur
As of 30 June 2008
a. SITE ACQUISITION AND INITIAL CONSTRUCTION OF
AIRPORT ACCESS ROAD
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Dec 2006 - Dec 2008 Rev Feb 2008
- Jan 2009
COST P170.0 M,, CY 2007
- Awaiting the result of the determination of fair
market value by the Appraisal Committee.
b. ADVANCE ENGINEERING STUDY AND DETAILED
DESIGNED
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig May 2008 - Oct 2008 Rev May
2009 - Apr 2012
Project Cost P85.0 M, pump-priming, CY 2007
- On-going with 55 completed.
- Comments and recommendations on the Final Draft
Report was forwarded to the Consultant for
consideration.
c. ADVANCE ENGINEERING STUDY AND DETAILED
DESIGNED
Project Cost P300.0 M, CY 2008
- Under Detailed Engineering stage.
40KABANKALAN AIRPORT DEVELOPMENT PROJECT
Kabankalan City, Negros Occidental
As of 30 June 2008
a. FS/MP for AIRPORT
IMPLEMENTING AGENCY DOTC
DURATION 6 Months
Project Cost P7.5 M, CY 2007
- Notice to Proceed (NTP) issued Schema Konsult on
01 August 2008. Consultant commenced work on 11
August 2008.
b. SITE ACQUISITION OF ROW ( LGU funds)
IMPLEMENTING AGENCY DOTC
- On-going. LGU has already acquired 90 of the 110
lots to be acquired.
41KALIBO AIRPORT DEVELOPMENT PROJECT
Kalibo, Aklan
As of 30 June 2008
a. INSTALLATION OF INSTRUMENT LANDING SYSTEM
TIMETABLE Orig May 2006 - Mar 2007 Rev May
2006 - Sep 2007
IMPLEMENTING AGENCY ATO
Project Cost P55.0 M
- Awaiting completion of site acquisition by
Kalibo LGU on the three (3) remaining lots within
ILS critical area of operation. - As per 01 August 2008 letter of Gov. Carlito
Marquez of Aklan, the Provincial Government of
Aklan has initiated negotiations with the owners
of the property affected and draw some positive
terms from the lot owners. As per report from
Kalibo Airport Manager, a meeting with lot owners
was held on 05 August 2008, on which the lot
owners agreed to sell their lots. An additional
Php 16 Million is still needed for the ROW
acquisition. DOTC is now looking for the source
of funds to cover payment for lot acquisition. - Overall accomplishment is 91.18. These includes
site acquisition, site development,
rehabilitation and installation of ILS equipment,
construction of equipment shelter and
installation of runway/taxiway edge lights.
GLIDESLOPE ANTENNA ELEMENTS AND DME ANTENNA
MOUNTED
LOCALIZER ANTENNA INSTALLATION COMPLETED
Problem Issues
- Prolonged negotiation by LGU-Province of
remaining lots critical to operation of the ILS. - Late acquisition of remaining Three(3) lots
critical to the operation of the ILS
42KALIBO AIRPORT DEVELOPMENT PROJECT
Kalibo, Aklan
As of 30 June 2008
b. CONSTRUCTION OF PASSENGER TERMINAL BUILDING
( realigned from Asphalt Overlay of Runway)
IMPLEMENTING AGENCY DOTC
TIMETABLE Jul 2008 - May 2009
Project Cost P50.0 M, CY 2006
- Suspended effective 2 June 2008 due to revision
of plans and with 8.34 actual accomplishment.
d. IMPROVEMENT OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P30.0 M, CY 2008
- Advertisement was posted on 08 August 2008.
c. ASPHALT OVERLAY OF RUNWAY, EXPANSION OF APRON
AND CONSTRUCTION OF DRAINAGE CANAL
Project Cost P294.0 M, CY 2008
- Notice to Proceed (NTP) issued to the Contractor
on 07 August 2008. Contractor to commence work on
22 August 2008.
43KALIBO AIRPORT DEVELOPMENT PROJECT
Kalibo, Aklan
As of 30 June 2008
f. IMPROVEMENT OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P3.0 M, CY 2008
e. REHABILITATION OF FIRE STATION BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P1.0 M, CY 2008
g. PURCHASE OF CFR VEHICLE
IMPLEMENTING AGENCY ATO
Project Cost P60.0 M, CY 2008
44PANGLAO BOHOL INTERNATIONAL AIRPORT DEVELOPMENT
PROJECT
Panglao, Bohol
As of 30 June 2008
a. CONSTRUCTION OF NEW AIRPORT
IMPLEMENTING AGENCY MIAA/DOTC
Project Cost P108.686 M,
PANGLAO AIRPORT PERSPECTIVE
- Capsule laying was held on 20 May 2008 led by
her Excellency PGMA. ECC was issued to DOTC on 3
June 2008 and transferred to MIAA on 6 June 2008.
b. SITE ACQUISITION (195 ha.)
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Sept 2006 - Dec 2007 Rev Sep
2006 - June 2008
Project Cost P100.686 M,
pump-priming, CY 2005 2006
P45.0 M ( CY 2008 additional funds)
- On-going with 88.97 accomplishment
45PANGLAO BOHOL INTERNATIONAL AIRPORT DEVELOPMENT
PROJECT
Panglao, Bohol
As of 30 June 2008
c. FEASIBILITY STUDY MASTER PLANNING
IMPLEMENTING AGENCY MIAA
TIMETABLE April - October 2007
Project Cost P8.0 M,
d. DETAILED ENGINEERING DESIGN
TIMETABLE Jan 2009 - Apr 2010
IMPLEMENTING AGENCY MIAA
Project Cost P8. 0 M, MIAA
- Accomplished eligibility forms submitted and
opened on 18 April 2008. - Five (5) consulting firms responded and under
evaluation for short-listing.
46DUMAGUETE AIRPORT DEVELOPMENT PROJECT
Dumaguete City, Negros Oriental
As of 30 June 2008
a. REHABILITATION OF PASSENGER TERMINAL BUILDING
IMPLEMENTING AGENCY MIAA
TIMETABLE Orig May 2007 - Dec 2007 Rev 01
Oct 2007 - Feb 2008
Project Cost P2.0 M, CY 2006
- 100 completed as of 25 February 2008.
(4.5m both side)
b. RUNWAY WIDENING AND ASPHALT OVERLAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig 16 Nov 2007 - 17 June
2008Rev 16 Nov 2007 - 13 July 2008
Project Cost P73.192 M, CY 2007
- 100 COMPLETED. Completed ahead of schedule.
47DUMAGUETE AIRPORT DEVELOPMENT PROJECT
Dumaguete City, Negros Oriental
As of 30 June 2008
c. UPGRADIGN OF AIRFIELD LIGHTING SYSTEM
IMPLEMENTING AGENCY ATO
TIMETABLE Orig Aug 2007 - Mar 2007 Rev Aug
2007 - May 2008
Project Cost P102.24 M, CY 2007
- On-going with 97 accomplishment.
- Suspended to give way to the on-going asphalt
overlay of runway.
d. COMPLETION OF ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P85M, CY 2008
- Notice of Award approved on 30 July 2008.
Contract for the project is being facilitated for
approval.
48DUMAGUETE AIRPORT DEVELOPMENT PROJECT
Dumaguete City, Negros Oriental
As of 30 June 2008
e. IMPROVEMENT OF TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P2.0 M, CY 2008
f. IMPROVEMENT OF FIRE STATION BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P1.0, CY 2008
g. PURCHASE/INSTALLATION OF LIGHTING AND SURGE
POWER PROTECTION
IMPLEMENTING AGENCY ATO
Project Cost P1.2, CY 2008
h. COMPLETION OF AIRFIELD LIGHTING
IMPLEMENTING AGENCY ATO
Project Cost P23.0, CY 2008
49GUIUAN AIRPORT DEVELOPMENT PROJECT
Guiuan, Eastern Samar
As of 30 June 2008
a. UPGRADING OF APRON TAXIWAY (PCCP)
IMPLEMENTING AGENCY DOTC
TIMETABLE 20 May 2007 - 15 September 2007
Project Cost P10 M, CY 2006
- The project is 100 completed last 10 September
2007. - Already accepted by DOTC.
b. CONCRETING OF APRON AND TAXIWAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Dec 2007 - April 2008 Rev
Oct 2007 - Jan 2008
COST P10 M, CY 2007
- The project is 100 completed.
50GUIUAN AIRPORT DEVELOPMENT PROJECT
Guiuan, Eastern Samar
As of 30 June 2008
c. REHABILITATION OF PASSENGER TERMINAL BLDG.
CONSTRUCTION OF ELEVATED WATER TANK AND SECURITY
FENCE
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Dec 2007 - May 2008 Rev Nov
2007 - Aug 2008
Project Cost P5.0 M, CY 2007
51GUIUAN AIRPORT DEVELOPMENT PROJECT
Guiuan, Eastern Samar
As of 30 June 2008
d. ASPHALT OVERLAY OF RUNWAY, COMPLETION OF APRON
TAXIWAY AND CONSTRUCTION OF PERIMETER FENCE
IMPLEMENTING AGENCY DOTC
Project Cost P110 M, CY 2008
e. SITE ACQUISITION AND CONSTRUCTION OF ACCESS
ROAD
IMPLEMENTING AGENCY DOTC
COST P20 M, CY 2008
52REDEVELOPMENT OF TACLOBAN AIRPORT
Tacloban City, Leyte
As of 30 June 2008
a. FEASIBILITY STUDY MASTER PLANNING
IMPLEMENTING AGENCY DOTC
TIMETABLE December 2007 - May 2008
Project Cost P 8.5 M , Pump-priming, CY 2006
- Notice of Award (NOA) was approved on 29 July
2008. For Consultant's compliance on the
requirements of NOA.
b. ASPHALT OVERLAY OF RUNWAY CONSTRUCTION OF
SHORE PROTECTION WITH SHOULDER GRADE CORRECTION
IMPLEMENTING AGENCY DOTC
Project Cost P 75.0M, CY 2007
TIMETABLE Dec 2007 - Aug 2008
- On-going with 21.33 accomplishment.
53REDEVELOPMENT OF TACLOBAN AIRPORT
Tacloban City, Leyte
As of 30 June 2008
c. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY,
STRIP GRADE CORRECTION AND CONSTRUCTION OF SHORE
PROTECTION, PERIMETER FENCE AND SECURITY FENCE
IMPLEMENTING AGENCY DOTC
Project Cost P130 M, CY 2008
- BAC Resolution recommending the Award of Contract
to winning bidder for approval by BAC members.
d. SITE ACQUISITION OF NEW TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
COST P130 M, CY 2008
e. SITE DEVELOPMENT AT NEW TERMINAL COMPLEX AREA
INCLUDING ACCESS ROAD
IMPLEMENTING AGENCY DOTC
COST P280.0 M, CY 2008
f. CONSTRUCTION OF PERIMETER FENCE FOR VOR STATION
IMPLEMENTING AGENCY ATO
COST P1.5 M, CY 2008
54REDEVELOPMENT OF TACLOBAN AIRPORT
Tacloban City, Leyte
As of 30 June 2008
g. REHABILITATION OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P10 M, CY 2008
- Detailed Engineering is on-going.
h. IMPROVEMENT OF ATC INTER-FACILITY DATA
COMMUNICATIONS
IMPLEMENTING AGENCY ATO
COST P5 M, CY 2008
i. PURCHASE / INSTALLATION OF VLS
IMPLEMENTING AGENCY ATO
COST P2.5 M, CY 2008
55SIARGAO AIRPORT DEVELOPMENT PROJECT
Siargao, Surigao Del Norte
As of 30 June 2008
a. CONTINUATION OF APRON EXPANSION, TAXIWAY
PERIMETER FENCE
IMPLEMENTING AGENCY DOTC
Project Cost P10 M, CY 2006
- COMPLETED -10 August 2007
b. CONSTRUCTION OF PERIMETER FENCE (CHB)
IMPLEMENTING AGENCY DOTC
Project cost P2.5M, CY 2006
- Notice to Proceed (NTP) signed on 12 August 2008,
for issuance to the contractor.
56SIARGAO AIRPORT DEVELOPMENT PROJECT
Siargao, Surigao Del Norte
As of 30 June 2008
c. CONSTRUCTION OF VPA (PCCP) AND PERIMETER
FENCE (CHB)
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig 28 Oct 2007 - 31 Mar 2008 Rev
28 Oct 2007 - 24 May 2008
Project cost P10.68 M, CY 2007
d. ESTABLISHMENT OF FSS FACILITY - Construction
of FSS Building Rehabilitation of Powerhouse -
Purchase/installation of Communications
Equipment - Purchase/installation of MET
Equipment
IMPLEMENTING AGENCY DOTC
Project Cost P12.50 M, CY 2007
- Bidding process on-going with 35.46 overall
accomplishment.
57SIARGAO AIRPORT DEVELOPMENT PROJECT
Siargao, Surigao Del Norte
As of 30 June 2008
e. LOT ACQUISITION FOR THE EXPANSION OF LANDSIDE
FACILITIES
IMPLEMENTING AGENCY DOTC
Project Cost P5.0 M, CY 2008
f. CONSTRUCTION OF PERIMETER FENCE, VPA AND
TURN-AROUND PAD
IMPLEMENTING AGENCY DOTC
Project Cost P24.82M, CY 2008
- Contract approved on 11 August 2008. For issuance
of Notice to Proceed (NTP).
taxiway
g. CONSTRUCTION OF TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P10.0 M, CY 2008
h. CONSTRUCTION OF FIRE STATION
IMPLEMENTING AGENCY DOTC
Project Cost P3.0 M, CY 2008
58Dinagat Island
MINDANAO AGRI-BUSINESS
Surigao del Norte
BUTUAN Airport project
AIRPORT PROJECTS
Agusan Del Norte
LAGUINDINGAN Airport project
Surigao del Sur
Misamis Or.
Agusan Del Sur
Misamis Occ.
OZAMIS Airport project
DIPOLOG Airport project
Bukidnon
Lanao Del Norte
Zamboanga del Sur
Zamboanga del Norte
Lanao Del Sur
Davao
PAGADIAN Airport project
Zamboanga Sibugay
Cotabato
Davao City
COTABATO Airport project
Davao Or.
Maguindanao
ZAMBOANGA Airport project
Basilan
Sultan Kudarat
Davao del Sur
South Cotabato
Sarangani
Sulu
Tawi-Tawi
59LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
PERSPECTIVE
PROPOSED LAGUINDINGAN PASSENGER TERMINAL BUILDING
a. CONSTRUCTION OF MAIN AIRPORT CIVIL WORKS
IMPLEMENTING AGENCY DOTC-PMO
TIMETABLE Orig Dec 2007 - Dec 2011 Rev 18
Jan 2008 - Jan 2012
Project Cost P 5.386 B
- On-going with 4.336 actual accomplishment, ahead
of schedule by 1.4746.
60LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
b. CONSTRUCTION OF ACCESS ROAD
IMPLEMENTING AGENCY DOTC-PMO
TIMETABLE Orig 11 Jul 2007 - Apr 2008
Rev 11 Jul 2007 - 10 Nov 2008
PHASE 1 - Project Cost P 188.77 M
- On-going with 52.405 actual accomplishment,
ahead of schedule by 9.726
PHASE 2 - Project Cost P 50.00 M
- On-going with 8.50 actual accomplishment, ahead
of schedule by 3.25
61LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
c. CONSTRUCTION OF PERIMETER FENCE
IMPLEMENTING AGENCY DOTC-PMO
TIMETABLE Orig 11 Jul 2007 - Apr 2008
Rev 11 Jul 2007 - 10 Nov 2008
PHASE 1 - Project Cost P 17.846 M
- 76.81 completed.
- Project is suspended due to lot acquisition
problem.
PHASE 1 - Project Cost P 23.50 M
- On-going with 15.12 actual accomplishment, ahead
of schedule by 2.62
62LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
d-1 CONSTRUCTION of RELOCATION SITE Phase II
(Site Development)
IMPLEMENTING AGENCY NHA
TIMETABLE Orig 22 April -18 Oct 2007 Rev 22
April -10 Apr 2008
Project Cost P 44.0 M ( Funds fully transferred
to NHA)
Site Development
- Actual accomplishment is 96.24.
63LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
d-2) CONSTRUCTION of RELOCATION SITE Phase II
(Construction of 109 Duplex Core Housing Units)
TIMETABLE 22 April 2008 -19 Aug 2007
Project Cost P25.50 M ( Funds fully transferred
to NHA)
- On-going with 92.00 actual accomplishment.
- 69 Duplex Core Housing Units are substantially
completed as of 15 July 2008, 36 housing units
on-going construction and 4 housing units to be
started for construction.
64LAGUINDINGAN AIRPORT DEVELOPMENT PROJECT
Laguindingan, Misamis Oriental
As of 30 June 2008
e. LOT ACQUISITION
IMPLEMENTING AGENCY DOTC-PMO
a. Main Airport - Total affected lot is 387.29
has., Acquired/donated is 289.97 has or 74.87.,
For donation of Ayala Corp is 94.04 has. For
acquisition is 3.28 has.
Land Use Conversion issued by DAR on 15
July 2008.
Problems / Issues
MOA between Ayala Corp., DAR, and DOTC was signed
on 31 Aug. 2007 which stipulates that Ayala will
donate 94.04 has. after the approval of land use
conversion in which DOTC act as co-petitioner.
Collation of pertinent documents already
completed. The LUC Application was already
submitted to DAR Central Office on 07 January
2008. DAR Central Office officials had conducted
site inspection on 21-23 May 2008. DAR requested
additional documents from DOTC prior to the
approval of LUC. On 30 June 2008, DOTC Secretary
forwarded the statement required by DAR to the
Office of DAR Secretary Nasser R. Pangandaman.
b. Access Road - 100 of the total lots
(24.11has.) were already acquired.
- On-going titling activities for
the acquired properties.
65BUTUAN AIRPORT DEVELOPMENT PROJECT
Bancasi, Butuan City, Agusan Del Sur
As of 30 June 2008
a. EXTENSION OF RUNWAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Aug 2007 - Dec 2007
Rev 03 Oct 2007 - 30 Apr 2008
Project Cost P10.0 M, CY 2007 GAA
- Substantially completed, For Final Inspection.
Extension of Runway (CY 2007 GAA)
66BUTUAN AIRPORT DEVELOPMENT PROJECT
Bancasi,Butuan City, Agusan Del Sur
As of 30 June 2008
b. IMPROVEMENT OF AIR NAVIGATION FACILITIES
IMPLEMENTING AGENCY ATO
TIMETABLE Orig Aug 2007 - Mar 2008
Rev 01 Dec 2007 - 28 Aug 2008
Project Cost P102.24 M, CY 2007 GAA
- 98 actual accomplishment.
c. RUNWAY EXTENSION, WIDENING OF RUNWAY AND
RESEALING OF JOINTS
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Sept 2007 - May 2008 Rev 28
Nov 2007 - 27 Sep 2008
Project Cost P50.0 M, CY 2006 GAA
( Realignment from ENT )
- On-going with 83.15 actual accomplishment ahead
of schedule by 1.50
Resealing of Joints (CY 2006 GAA)
67BUTUAN AIRPORT DEVELOPMENT PROJECT
Bancasi,Butuan City, Agusan Del Sur
As of 30 June 2008
d. SUPPLY AND INSTALLATION OF CAROUSEL CONVEYOR
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig 15 February 2008 - 30 July
2008 Rev Aug 2008 - October 2008
Project Cost P5.0 M, CY 2006 GAA re alignment
from LADP
- Installation of carousel COMPLETED on 26 July
2008.
e. ASPHALT OVERLAY OF RUNWAY, EXTENSION OF RUNWAY
PAVEMENT AND COMPLETION OF SHOULDER GRADE
CORRECTION
IMPLEMENTING AGENCY DOTC
Project Cost P135.00 M, CY 2008, GAA
f. REHABILITATION OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
TIMETABLE D.E. Jun 2008 - Aug. 2008
Project Cost P9.0 M, CY 2008 GAA
- Detailed Engineering is on-going.
68COTABATO AIRPORT DEVELOPMENT PROJECT
Cotabato, Maguindanao
As of 30 June 2008
a. ASPHALT OVERLAY OF RUNWAY AND RESEALING OF
RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P20.0 M, CY 2005, GAA
COMPLETED - 05 October 2006
b. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY ATO
Project Cost P25.0 M, Pump-priming, CY 2005
COMPLETED - 08 June 2007
c. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P15.0 M, CY 2006 GAA
COMPLETED -13 December 2008
69COTABATO AIRPORT DEVELOPMENT PROJECT
Cotabato, Maguindanao
As of 30 June 2008
d. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Aug 2007 - Dec 2007
Rev 03 Oct 2007 - 22 Mar 2008
Project Cost P25.0 M, CY 2007 GAA
70COTABATO AIRPORT DEVELOPMENT PROJECT
Cotabato, Maguindanao
As of 30 June 2008
e. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY
(Realignment from ENT)
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Oct 2007 - Dec 2007 Rev June
2008 - Nov 2008
Project Cost P15.0 M, CY 2006 GAA
- COMPLETED - 15 August 2008
f. SUPPLY INSTALLATION OF O-SHAPED CAROUSEL
CONVEYOR
IMPLEMENTING AGENCY DOTC
Project Cost P5.0 M, CY 2007 GAA
g. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY,
WIDENING OF RUNWAY, CONSTRUCTION OF CHB FENCE AND
RELOCATION OF RUNWAY LIGHTS
IMPLEMENTING AGENCY DOTC
Project Cost P134.0 M, CY 2008
71COTABATO AIRPORT DEVELOPMENT PROJECT
Cotabato, Maguindanao
As of 30 June 2008
h. REHABLITATION OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P15.0 M, CY 2008 GAA
- Detailed Engineering is on-going.
i. AIR NAVIGATIONAL FACILITIES (ANF)
IMPLEMENTING AGENCY ATO
Project Cost P68.0 M, CY 2008 GAA
- POW for Awaiting approved ABM from DBM.
j. REHABILITATION OF AIRFIELD LIGHTING SYSTEM
IMPLEMENTING AGENCY ATO
Project Cost P25.0 M, CY 2008 GAA
72DIPOLOG AIRPORT DEVELOPMENT PROJECT
Dipolog City, Zamboanga Del Norte
As of 30 June 2008
a. SHORE PROTECTION (145m )
IMPLEMENTING AGENCY DOTC
Project Cost P20.0 M, CY 2006 Pump-priming
COMPLETED 20 AUGUST 2007
b. ASPHALT OVERLAY OF RUNWAY (109 m x 45 m) and
WIDENING OF RUNWAY (814 m x 7.5 m) both sides
IMPLEMENTING AGENCY DOTC
Project Cost P40.0 M, CY 2006, Pump-priming
COMPLETED - 15 June 2007
(Northern Side)
(Southern Side)
Completed Runway Asphalt overlay
Completed Runway Widening Works
Completed Runway Widening Works
73DIPOLOG AIRPORT DEVELOPMENT PROJECT
Dipolog City, Zamboanga Del Norte
As of 30 June 2008
c. CONTINUATION OF WIDENING OF RUNWAY (765 m x
7.5 m) both side and SHORE PROTECTION (200 lm)
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Aug 2007- Mar 2008
Rev 23 Sep 2007 - 24 June 2008
Project Cost P52.88 M, CY 2006
Pump-priming ( realignment from ENT )
d. CONTINUATION OF WIDENING OF RUNWAY SHORE
PROTECTION AND ASPHALT OVERLAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Oct 2007 - May 2008 Rev
28 Feb 2008 - 04 Nov 2008
Project Cost P55.0 M, CY 2007, GAA
- 90.43 actual accomplishment, ahead of schedule
by 23.61.
74DIPOLOG AIRPORT DEVELOPMENT PROJECT
Dipolog City, Zamboanga Del Norte
As of 30 June 2008
e. PROPOSED EXTENSION OF RUNWAY, CONSTRUCTION OF
PERIMETER FENCE AND CONTINUATION OF SHORE
PROTECTION
IMPLEMENTING AGENCY DOTC
Project Cost P169.97 M, CY 2008 GAA
- Notice to Proceed (NTP) for issuance to the
contractor.
f. CONSTRUCTION OF ADMINISTRATION BUILDING,
REHABILITATION OF EXISTING TERMINAL BUILDING AND
FIRE STATION BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P169.97 M, CY 2008 GAA
- Detailed Engineering is on-going.
g. AIR NAVIGATIONAL FACILITIES
IMPLEMENTING AGENCY ATO
Project Cost P169.97 M, CY 2008 GAA
- Funds for transfer to CAAP.
75OZAMIS AIRPORT DEVELOPMENT PROJECT
Ozamis City, Misamis Occidental
As of 30 June 2008
a. CONSTRUCTION OF RIVER BANK PROTECTION ( 90
L.m. ) CONCRETING OF RUNWAY ( 84M X30M )
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig 17 Dec 2006 25 Nov 2007
Rev 17 Dec 2006 - 31 Jan 2008
Project Cost P40.0 M, Pump-priming, CY 2006
COMPLETED - 31 January 2008
COMPLETED CONCRETING WORKS
ON GOING RIVER BANKS PROTECTION WORKS
b. RUNWAY MARKING AND OBSTRUCTION REMOVAL
IMPLEMENTING AGENCY ATO
Project Cost P3.0 M, CY 2006 GAA
TIMETABLE Orig June 2007 - Aug 2007 Rev
June 2007 - 08 Jul 2008
COMPLETED - 05 July 2008
76OZAMIS AIRPORT DEVELOPMENT PROJECT
Ozamis City, Misamis Occidental
As of 30 June 2008
c. REHAB/EXPANSION OF EXISTING TERMINAL BUILDING
TIMETABLE Orig Oct 2007 - Dec 2007 Rev 25 May
2008 - 28 Sept 2008
IMPLEMENTING AGENCY DOTC
Project Cost P5.0 M, Pump-priming, CY 2006
- Actual accomplishment is 76.39, ahead of
schedule by 15.03.
d. RUNWAY EXTENSION, APRON EXPANSION
CONSTRUCTION OF TAXIWAY (Sta. 0423 to Sta 0507)
IMPLEMENTING AGENCY DOTC
TIMETABLE Sept 2007 - Dec 2007 Rev 18 January
2008 15 Sep 2008
(Realignment from ENT)
COST P30.0 M, Pump-priming, CY 2006
- On-going with 73.39 actual accomplishment, ahead
of schedule by 3.82.
e. CONTINUATION OF REHABILITATION OF EXISTING
TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P4.125 M, CY 2008 pump priming
TIMETABLE D.E. June - Aug 2008
(Realignment from LADP)
- Detailed Engineering is on-going.
- For bidding.
77OZAMIS AIRPORT DEVELOPMENT PROJECT
Ozamis City, Misamis Occidental
As of 30 June 2008
f. WIDENING / EXTENSION OF RUNWAY, CONTINUATION
OF RIVERBANK PROTECTION, CONSTRUCTION OF BARBED
WIRE FENCE, RESEALING OF CRACKS JOINTS AND
RELOCATION OF WEATHER INSTRUMENT
Project Cost P43.0 M, CY 2008 GAA
g. ASPHALT OVERLAY OF EXISTING RUNWAY AND RUNWAY
WIDENING
IMPLEMENTING AGENCY DOTC
TIMETABLE D.E. June - Aug 2008
Project Cost P93.50 M, CY 2008 GAA
- Detailed Engineering is on-going.
h. REHABILITATION OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
Project Cost P1.50 M, CY 2008 GAA
TIMETABLE D.E. June - Aug 2008
- Detailed Engineering is on-going.
78PAGADIAN AIRPORT DEVELOPMENT PROJECT
Pagadian City, Zamboanga Del Sur
As of 30 June 2008
a. ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
COST P12.0 M, CY 2006
COMPLETED - 06 July 2007
b. CONCRETING OF RUNWAY, TAXIWAY AND APRON
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Aug 2007 - Dec 2007 Rev 07
June 2008 - 31 Apr 2009
Project Cost P57.76 M, CY 2007 GAA
- On-going with 18.35 actual accomplishment, ahead
of schedule by 14.63
79PAGADIAN AIRPORT DEVELOPMENT PROJECT
Pagadian City, Zamboanga Del Sur
As of 30 June 2008
c. EXTENSION OF RUNWAY
TIMETABLE Orig Sept 2007 - Jan 2008
Rev 01 May 2008 - 28 Sep 2008
IMPLEMENTING AGENCY DOTC
( Realignment from ENT )
Project Cost P30.0 M, CY 2006, GAA
- On-going with 46.25 actual accomplishment, ahead
of schedule by 12.10.
d. CONTINUATION OF CONCRETING OF EXISTING RUNWAY
AND APRON, EXTENSION OF RUNWAY CONSTRUCTION OF
PERIMETER FENCE
IMPLEMENTING AGENCY DOTC
Project Cost P181.0M, CY 2008, GAA
TIMETABLE D.E. June - Aug 2008
e. CONSTRUCTION OF ADMINISTRATION BUILDING AND
REHABILITATION OF EXISTING TERMINAL BUILDING
TIMETABLE D.E. June - Aug 2008
IMPLEMENTING AGENCY DOTC
Project Cost P11.5 M, CY 2008, GAA
- Under Detailed Engineering.
80PAGADIAN AIRPORT DEVELOPMENT PROJECT
Pagadian City, Zamboanga Del Sur
As of 30 June 2008
f. CONSTRUCTION OF FSS POWERHOUSE BUILDING
Project Cost P7.0 M, CY 2008, GAA
- Funds for transfer to CAAP
g. PURCHASE/INSTALLATION OF MET INSTRUMENT
Project Cost P1.70 M, CY 2008, GAA
- For funds transfer to CAAP
81ZAMBOANGA AIRPORT DEVELOPMENT PROJECT
Zamboanga City, Zamboanga Del Sur
As of 30 June 2008
1. IMMEDIATE IMPROVEMENT
IMPLEMENTING AGENCY DOTC
a. ASPHALT OVERLAY OF RUNWAY
Project Cost P35.0 M, CY 2005, pump-priming
COMPLETED - 30 November 2006
b. CONSTRUCTION OF ELEVATED WATER TANK AND POWER
HOUSE AND REHAB OF TERMINAL BUILDING
Project Cost P3.0 M, CY 2006
COMPLETED - 03 May 2007
82ZAMBOANGA AIRPORT DEVELOPMENT PROJECT
Zamboanga City, Zamboanga Del Sur
As of 30 June 2008
c. CONTINUATION ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig June 2007 - Sept 2007
Rev 21 June 2007 - 15 Dec 2007
Project Cost P13.0 M, CY 2006 GAA
- Completed - 12 December 2007.
d. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY
IMPLEMENTING AGENCY DOTC
Project Cost P64.0 M, CY 2007
TIMETABLE Orig Aug 2007 - Jan 2008
Rev 19 Sept 2007 - 10 July 2008
- 56.50 actual accomplishment, ahead of schedule
by 8.70
83ZAMBOANGA AIRPORT DEVELOPMENT PROJECT
Zamboanga City, Zamboanga Del Sur
As of 30 June 2008
e. REHABILITATION OF COMFORT ROOM AT TERMINAL
BUILDING
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Nov 2007 - Feb 2008 Rev 29 May
2008 23 Feb 2009
Project Cost P6.0 M, CY 2006 (Realignmnet
from ENT)
- On-going with 18.50 actual accomplishment, ahead
of schedule by 1.70.
f. SUPPLY AND INSTALLATION OF BAGGAGE CONVEYOR AT
THE ARRIVAL AREA
IMPLEMENTING AGENCY DOTC
TIMETABLE Orig Nov 2007 - Feb 2008 Rev Apr
2008 - Aug 2008
Project Cost P6.0 M, GAA CY 2006 (Realignment
from ENT)
g. CONTINUATION OF ASPHALT OVERLAY OF RUNWAY,
IMPROVEMENT OF DRAINAGE SYSTEM CONSTRUCTION OF
CHB FENCE.
IMPLEMENTING AGENCY DOTC
Project Cost P110.0 M, GAA CY 2008
84ZAMBOANGA AIRPORT DEVELOPMENT PROJECT
Zamboanga City, Zamboanga Del Sur
As of 30 June 2008
h. REHABILITATION OF EXISTING TERMINAL BUILDING
IMPLEMENTING AGENCY DOTC
TIMETABLE D.E. June - Aug 2008
Project Cost P23.0 M, CY 2008 GAA
- Under Detailed Engineering.
i. AIR NAVIGATIONAL FACILITIES
IMPLEMENTING AGENCY ATO
Project Cost P8.7M, GAA CY 2008
- SARO received 12 June 2008. For revision of POW
approving authority.
j. NEW ZAMBOANGA INTERNATIONAL AIRPORT
(Feasibility Study)
IMPLEMENTING AGENCY DOTC
Project Cost P15.0 M, GAA CY 2008
85ZAMBOANGA AIRPORT DEVELOPMENT PROJECT
Zamboanga City, Zamboanga Del Sur
As of 30 June 2008
k. NEW ZAMBOANGA INTERNATIONAL AIRPORT
(Feasibility Study)
IMPLEMENTING AGENCY DOTC
TIMETABLE D.E. June - Aug 2008
Project Cost P15.0 M, CY 2008 GAA
- Under Detailed Engineering.
l. REHABILITATION OF SALS
IMPLEMENTING AGENCY ATO
Project Cost P12.0M, CY 2008 GAA CAAP
- SARO received 12 June 2008.
86D O T C OFFICE OF UNDERSECRETARY FOR ROAD
TRANSPORT/ PROJECT IMPLEMENTATION OFFICER MIS /
ISD-PROJECT MONITORING GROUP