Title: CHAPTER 12 Other Topics in Capital Budgeting
1CHAPTER 12Other Topics in Capital Budgeting
- Evaluating projects with unequal lives
- Identifying embedded options
- Valuing real options in projects
2Evaluating projects with unequal lives
- Projects S and L are mutually exclusive, and
will be repeated. If k 10, which is better? - Expected Net CFs
- Year Project S Project L
- 0 (100,000) (100,000)
- 1 59,000 33,500
- 2 59,000 33,500
- 3 - 33,500
- 4 - 33,500
3Solving for NPV, with no repetition
- Enter CFs into calculator CFj register for both
projects, and enter I/YR 10. - NPVS 2,397
- NPVL 6,190
- Is Project L always better - NO?
- Need replacement chain analysis.
- Reason Unfair to compare to projects with
unequal lives.
4Replacement chain
- Use the replacement chain to calculate an
extended NPVS to a common life. - Since Project S has a 2-year life and L has a
4-year life, the common life is 4 years.
0
1
2
3
4
10
-100,000 59,000 59,000
59,000 59,000 -100,000
-41,000
NPVS 4,377 (on extended basis) L still better?
5Replacement Chain Approach
- See example in book, p. 455.
- Project F (3-year) has a lower NPV over 3 years,
but higher NPV over 6 years. - Furthermore, Project F has another advantage over
Project C?
6What is real option analysis?
- Real options exist when managers can influence
the size and riskiness of a projects cash flows
by taking different actions during the projects
life. - Real option analysis incorporates typical NPV
budgeting analysis with an analysis for
opportunities resulting from managers decisions.
7What are some examples of real options?
- Investment timing options
- Abandonment/shutdown options
- Growth/expansion options
- Flexibility options
81. Investment timing option
- Project L costs 100,000, its annual CFs are
33,500 for 4 yrs, k 10, and NPV is 6,190. - However, if we wait one year, we will find out
some additional information regarding output
prices and the cash flows from Project L. - If we wait, the up-front cost will remain at
100,000 and there is a 50 chance the subsequent
CFs will be 43,500 a year (vs. 33,500), and a
50 chance the subsequent CFs will be 23,500 a
year (vs. 33,500).
9Investment timing decision tree
-100,000 43,500 43,500 43,500
43,500
50 prob.
-100,000 23,500 23,500 23,500
23,500
50 prob.
0 1 2 3 4
5
Years
- At k 10, the NPV at t 1 is
- 37,889, if CFs are 43,500 per year (vs. NPV of
6,190 before), or - -25,508, if CFs are 23,500 per year, in which
case the firm would not proceed with the project.
10Should we wait or proceed?
- If we proceed today, NPV 6,190.
- If we wait one year, Expected NPV at t 1 is
0.5(37,889) Accept - 0.5(0) Reject 18,944, which is worth 18,944
/ (1.10) 17,222 in todays dollars (assuming a
10 discount rate). - Therefore, it makes sense to wait.
11Issues to consider with investment timing options
- Whats the appropriate discount rate?
- Note that increased volatility makes the option
to delay more attractive. - If instead, there was a 50 chance the subsequent
CFs will be 53,500 a year, and a 50 chance the
subsequent CFs will be 13,500 a year, expected
NPV next year (if we delay) would be - 0.5(69,588) 0.5(0) 34,794 gt 18,944.57
- Accept Reject
12Factors to consider when deciding when to invest
- Delaying the project means that cash flows come
later rather than sooner. - It might make sense to proceed today if there are
important advantages to being the first
competitor to enter a market (first mover
advantage). - Waiting may allow you to take advantage of
changing market and economic conditions.
13Investment Timing Options
- See Example in text on p. 461.
142. Abandonment option
- Project Y has an initial, up-front cost of
200,000, at t 0. The project is expected to
produce after-tax net cash flows of 80,000 for
the next three years. - At a 10 discount rate, what is Project Ys NPV?
15Abandonment option
- Project Ys net CFATs depend critically upon
customer acceptance of the product. - There is a 60 probability that the product will
be wildly successful and produce CFATs of
150,000, and a 40 chance it will produce annual
CFATs of -25,000. - .60 (150,000) .40 (-25,000) 80,000
16Abandonment decision tree
150,000 150,000 150,000
60 prob.
-200,000
-25,000 -25,000 -25,000
40 prob.
0
1 2 3
Years
- If the customer uses the product, CF 150,000
- NPV is 173,027.80 at 10 (blue).
- If the customer does not use the product,
- NPV is -262,171.30 (red).
- E(NPV) 0.6(173,027.8) 0.4(-262,171.3)
- -1,051.84
17Issues with abandonment options
- The company does not have the option to delay the
project now or never. - However, the company can abandon the project
after a year, if the customer has not adopted the
product. - If the project is abandoned, there will be no
operating costs incurred nor cash inflows
(outflows) after the first year.
18NPV with abandonment option
150,000 150,000 150,000
60 prob.
-200,000
-25,000
40 prob.
0
1 2 3
Years
- If the customer uses the product, NPV is
173,027.80 (same as before). - If the customer does not use the product,
- NPV is -222,727.27 (vs. -262,171 before)
- E(NPV) 0.6(173,027.8) 0.4(-222,727.27)
- 14,725.77 (vs. -1051 from before)
19Is it reasonable to assume that the abandonment
option does not affect the cost of capital?
- No, it is not reasonable to assume that the
abandonment option has no effect on the cost of
capital. - The abandonment option reduces risk, and
therefore reduces the cost of capital.
203. Shutdown Options
- See example in text on p. 458.
214. Growth option
- Project Z has an initial up-front cost of
500,000. - The project is expected to produce A-T cash
inflows of 100,000 at the end of each of the
next five years. Since the project carries a 12
cost of capital, it clearly has a negative NPV. - There is a 10 chance the project will lead to
subsequent opportunities that have a NPV of
3,000,000 at t 5, and a 90 chance of a NPV of
-1,000,000 at t 5.
22NPV with the growth option
3,000,000
100,000 100,000 100,000 100,000
100,000
10 prob.
-1,000,000
-500,000
100,000 100,000 100,000 100,000
100,000
90 prob.
1 2 3 4 5
0
Years
- At k 12,
- NPV of top branch (10 prob) 1,562,758
- NPV of lower branch (90 prob) -139,522
23NPV with the growth option
- If it turns out that the project has future
opportunities with a negative NPV, the company
would choose not to pursue them. - Therefore, the NPV of the bottom branch should
include only the -500,000 initial outlay and the
100,000 annual cash flows, which lead to an NPV
of -139,522.38. - Thus, the expected value of this project should
be - NPV 0.1 (1,562,758) 0.9 (-139,522)
- 30,706.
245. Flexibility options
- Flexibility options exist when its worth
spending more money today, which enables you to
maintain flexibility (and lower costs and/or
higher revenues) down the road. - See BMW and Power Companies examples on p. 464.
25Optimal Capital Budget
- Optimal Capital Budget
- Capital Rationing
- See p. 465-466
- Problem 12-2 on p. 469