Implementation of Transportation Management Plans (TMPs) - PowerPoint PPT Presentation

About This Presentation
Title:

Implementation of Transportation Management Plans (TMPs)

Description:

... the same roads on which agencies need to perform maintenance and rehabilitation. Has affects on: ... TMP training is important for all divisions involved in TMPs ... – PowerPoint PPT presentation

Number of Views:122
Avg rating:3.0/5.0
Slides: 40
Provided by: sym76
Learn more at: https://ops.fhwa.dot.gov
Category:

less

Transcript and Presenter's Notes

Title: Implementation of Transportation Management Plans (TMPs)


1
Implementation of Transportation Management Plans
(TMPs)
  • Presented by Tracy Scriba
  • Federal Highway Administration
  • AASHTO Design Meeting
  • July 15, 2008

2
Agenda
  • Work Zone Safety and Mobility Rule
  • TMP Basics
  • What Role do Designers Play in Developing TMPs?
  • State of the Practice for TMPs
  • TMP Development Resources

3
Work Zone Safety and Mobility Rule
  • Published Sept 9, 2004 in Federal Register (69
    FR 54562)
  • Updates and Renames 23 CFR 630 Subpart J
  • Effective Date of Oct 12, 2007
  • Establishes requirements and guidelines for
    consideration and management of WZ impacts
  • Requires development and implementation of TMPs
    for all Federal Aid highway projects (among other
    things)

4
TMP Basics What is a TMP?
  • A document that lays out a set of coordinated
    transportation management strategies and
    describes how they will be used to manage the
    work zone impacts of a road project

5
TMP Basics Why TMPs?
  • Traffic management efforts beyond temporary
    traffic control (TTC) plans are needed to deal
    with the increasing traffic volumes using the
    same roads on which agencies need to perform
    maintenance and rehabilitation
  • Has affects on
  • Safety
  • Mobility
  • Constructability
  • TMPs more comprehensive approach to managing WZ
    impacts

6
Basics TMP Components
  • A TMP may be a single document, or several
    documents/plans compiled together
  • Must always include a Temporary Traffic Control
    Plan (TTC)
  • For significant projects, TMPs must also contain
    a traffic operations (TO) component and a public
    information and outreach (PI) component

Simply stated, a significant project is a project
that the agency expects will cause a relatively
high level of disruption.
7
Basics When is a TMP Developed?
  • TMP development should begin during systems
    planning and progress through design
  • Conducting TMP analyses early in project
    development helps ensure
  • Systems planning and preliminary engineering TMP
    development and implementation costs are included
    in the project budget
  • Design Agencies consider WZ impacts in
    evaluation and selection of design alternatives ?
    For some projects it may be possible to choose a
    design alternative that alleviates many WZ
    impacts
  • Final TMP development occurs during DESIGN

8
TMP Development Process (from Developing and
Implementing TMPs for Work Zones)
9
What Role do Designers Play in Developing TMPs?
10
During Design
  • Final assessment of WZ impacts is done, which
    should affect the choice of
  • Best construction/staging option(s)
  • Most suitable design and contracting approach
  • Most appropriate WZ traffic management strategies

11
TMP Strategies to Manage WZ Impacts
Temporary Traffic Control (TTC) Strategies Public Information (PI) Strategies Transportation Operations (TO) Strategies
-Traffic control/design approaches -Traffic control devices -Project coordination, contracting, and innovative construction -Public awareness -Motorist information -Demand management -Corridor/network management -WZ safety management -Traffic/incident management enforcement
  • Designers are encouraged to consider these
    strategies early on in the process for all
    projects, even if they arent included in the TMP

12
Traffic Control/Design Approaches
  • Construction phasing/staging
  • Night work
  • Weekend work
  • Work hour restrictions for peak travel
  • Full roadway closures
  • Lane shifts or closures
  • Reduced lane widths to maintain of lanes
  • Lane closures to provide worker safety
  • Reduced shoulder width to maintain of lanes
  • Shoulder closures to provide worker safety
  • Lane shift to shoulder/median to maintain of
    lanes
  • One-lane, two-way operation
  • Two-way traffic on one side of divided facility
    (crossover)
  • Reversible lanes
  • Ramp closures/relocation
  • Freeway-to-freeway interchange closures
  • Pedestrian/bicycle access improvements
  • Business access improvements
  • Off-site detours/use of alternate routes

13
Identification of TMP Strategies
  • Should be based on
  • project constraints
  • construction phasing/staging plan
  • type of work zone
  • anticipated WZ impacts
  • Some agencies use strict lane closure
    policies/strategies or permissible lane closure
    times that must be followed
  • Agencies may use analysis tools to predict
    delays, queues, and impacts of detours and
    compare these for various strategies

14
Decisions During Design Impact TMPs
  • Design-level decisions can influence the choice
    of WZ management strategies
  • As specific decisions are made, WZ management
    strategies should also be reassessed to determine
    if they still apply and whether they adequately
    mitigate the WZ impacts of the project

Example Preliminary engineering assessments may
result in the identification of 2 alternate
"construction and WZ management approaches" 1)
night work with a basic TMP, and 2) daytime work
option with a more complex TMP. As design
progresses, more information may become available
on the feasibility of each of the approaches,
leading to the elimination of the night work
option. Therefore, the day option would be chosen
and TMP strategies such as signal retiming and a
traffic incident management plan might be used.
15
Decisions During Design Impact TMPs
  • Detailed quantitative analysis during design may
    be the best way to get a clear understanding of
    the expected WZ impacts of a project
  • Most project decisions are finalized during
    design as the project design/construction team
    gains the best understanding of how exactly the
    project will be built
  • A quantitative analysis conducted during design
    can
  • Yield the best estimation of the magnitude,
    location, duration, and costs of the WZ impacts
  • Help identify the management strategies that
    best mitigate the impacts
  • Help avoid omission or oversight of WZ safety
    and mobility issues prior to final design
  • Help identify and address issues that may lead
    to a work stoppage during the construction stage
    (e.g., queue lengths or delays in excess of
    agency policy)

16
Decisions During Design Impact TMPs
  • During detailed design, quantitative analysis is
    more detailed and will lead to the development of
    the final design and TMP for the project

Example Early WZ impacts analysis done during
preliminary engineering using a sketch-planning
tool may indicate that traffic diversion to the
designated alternate route for the project would
be significant, leading to a preliminary decision
to upgrade and re-time the traffic signals on the
alternate route. In design a more detailed
analysis using a micro-simulation tool is
conducted to estimate actual diversion patterns,
the volume of traffic expected to divert to the
alternate, and the intersections that would be
affected. This analysis may then be used to
identify the number of traffic signals that need
to be upgraded and the exact nature of the
upgrades, and to develop the signal timing plans
and estimate the costs.
17
Caltrans I-15 Devore PCCP Reconstruction
Closure Schedule, Cost, Delay Comparison
Construction Scenario Schedule Comparison Schedule Comparison Cost Comparison (Millions) Cost Comparison (Millions) Cost Comparison (Millions) Cost Comparison (Millions) Max. Delay (Min)
Construction Scenario Total Closures Closure Hours User Delay Construction Traffic Handling Total Max. Delay (Min)
72-Hour Weekday 8 512 5.6 10.5 2.1 18.2 75
55-Hour Weekend 10 550 14.2 12.5 2.6 29.3 196
1 Roadbed Continuous 2 400 6.9 8.9 1.0 16.8 196
10-Hour Night-time 220 2,200 4.9 19.1 1.3 25.3 36
18
TMP State of the Practice
19
TMP Beginnings
  • Idea for TMP provision in WZ Rule came from
    Caltrans
  • Caltrans began requiring TMPs in 2000 for all
    planned activities on the State highway system
  • Implementation of TMPs in California has helped
    to significantly reduce delays in work zones

In Caltrans District 7, on the I-10 Long-Life
Pavement Project, the TMP helped reduce traffic
demand by an estimated 57 percent, queue lengths
to 2 miles from the originally projected 44
miles, and projected delays from an estimated
1,000,000 to 16,000 total vehicle hours of delay.
20
TMP Findings - 2007 WZ Self Assessment
  • TMPs are still a developing area
  • Has the agency established a policy for the
    development of TMPs to reduce WZ congestion and
    crashes?
  • Average score for this item increased by 14 in
    2006 and by 20 in 2007
  • Average score was 8.5, indicating agencies are in
    the execution stage of adopting TMPs into their
    WZ practices
  • Two-thirds (67) of agencies are implementing a
    policy for developing TMPs

21
Caltrans TMP Fact Sheet
  • Provides information about Caltrans TMP
    Development Process
  • Discusses TMP categories, roles and
    responsibilities, and lessons learned for Caltrans

22
Caltrans TMP Development Process
23
Caltrans TMP Levels
24
What Worked for Caltrans?
  • Encourage design and project staging that
    minimizes potential traffic impacts
  • Have District Traffic Manager and TMP Manager
    sign off on TMP just prior to bid to make sure
    strategies reflect current traffic conditions -
    especially for "shelved" projects
  • Produce standardized forms for blanket and minor
    projects
  • Produce a brief, standardized report for each
    major project
  • Standardize practices for monitoring the
    effectiveness of TMPs in the field

25
Missouri DOT TMP Strategies Database
The TMP Database is meant to be used at the very
beginning of WZ planning to choose the most
effective methods from the start, with
re-evaluation occurring in the design stage.
26
Virginia TMP Requirements
  • VDOT has extended TMP requirements to all WZ
    activities within State right of way and on all
    streets and highways that have been accepted into
    the State Highway System - regardless of funding
    source
  • VDOT TMP Guide
  • Provides guidelines for acquiring the information
    to develop TMPs
  • Contains guidance on each Project Team member's
    role and responsibilities in the development of
    TMPs
  • Applies to Project Managers, Roadway Designers,
    Traffic Engineers, WZ Safety Coordinators, Public
    Affairs Managers

27
Virginia TMPs Design Role
  • The Roadway Designer
  • Preliminary Field Inspection
  • Incorporates the recommended TMP into the
    projects initial roadway plans
  • Public Hearing Meeting
  • Incorporates all recommendations/corrections into
    the preliminary TMP prior to the Public Hearing
  • Field Inspection Meeting
  • Completes TMP for review by Project Team during
    the Constructability Review stage for the Detail
    Roadway Design and Roadway Design phases of
    Concurrent Engineering Process (CEP)
  • Incorporates into the TMP all accepted
    recommendations/corrections submitted by Project
    Team
  • Pre-Advertisement Conference
  • Completes final TMP for review by
    Constructability Review Team during
    Constructability and Bidability Review stage of
    CEP
  • Incorporates all recommendations/corrections
    submitted by Project Team into final TMP prior to
    proceeding to the next phase

28
Pennsylvania Sample TMP
  • PennDOT includes a sample TMP in its Traffic
    Engineering Manual

29
WisconsinTMP Process
  • Process
  • Work Zone Impacts Assessment
  • Determine Type of TMP
  • Prepare Initial TMP
  • Update, Implement, Monitor
  • Evaluate After Project

30
Wisconsin TMP Components
  • Type 1
  • Traffic Control Plan
  • Public Information and Outreach
  • Type 2, 3, 4
  • Traffic Control Plan
  • Public Information and Outreach
  • Transportation Operations
  • Incident Management

31
When are TMPs developed in Wisconsin?
TMP
TMP
TMP
32
North Dakota TMP Development
  • NDDOT has TMP development guidelines in its WZ
    policy
  • For significant projects, NDDOT compiles a TMP
    team to develop and implement the TMP
  • Has members from Planning and Programming
    Division, Maintenance and Engineering Services
    Division, Construction Services Division, Design
    Division, District, FHWA, local municipality, and
    others as necessary
  • For non-significant projects
  • Reconstruction project the Project Designer,
    Design Division, and District will develop the
    TMP
  • Other than reconstruction projects - Project
    Designer will consult with Design Division and
    District

33
Considerations
  • Agency WZ policies
  • E.g., Maximum WZ queue lengths/delays allowed
  • Lane Closure policies/charts that specify when a
    lane closure is permitted
  • Analytical/modeling tools used by the agency

34
Colorado Region 6 Lane Closure Strategy
Scenario State Highway 121 (Wadsworth
Boulevard), Northbound Direction, Milepoint 22.0,
weekday. Solution Referring to the Decision
Tree, Wadsworth is an arterial facility.
Following the right side of the chart, the
appropriate schedule may be found in the table.
Look up SH 121 in the left-most column and
locate MP 22.0 between 84th Avenue and 100th
Avenue. The weekday schedule indicates that a
lane may be closed at night between 700pm and
800am and during the midday between 1000am and
200pm.
35
TMP Development Resources
36
Tips for Developing TMPs
  • Estimate and budget for TMP development and
    implementation early in project development
    (update as appropriate throughout project)
  • Include funding for monitoring traffic conditions
    during construction to track TMP effectiveness in
    case strategies need to be modified and for
    future WZs
  • Consider and address WZ impacts from a broader
    transportation management perspective, rather
    than solely a traffic control perspective
  • Balance constructability and construction staging
    requirements with WZ management strategies
  • Coordinate phasing/staging with other strategies
    in TMP (TTC, TO, and PI plans)
  • Coordinate with other key parties to jointly
    identify WZ impacts issues to account for and
    management strategies to address them
  • Preliminary engineering - Design team should work
    with other technical specialists, including
    construction, traffic engineering, and public
    outreach/relations personnel
  • Designers/construction engineers - Develop
    phasing and staging plans in consultation with
    safety experts, traffic engineers, other
    technical specialists
  • Construction - Maintain close coordination with
    local agencies on detours and signal timings

37
Tips for Developing TMPs (cont.)
  • Use strategies that keep lanes open, especially
    during peak traffic times
  • E.g., narrowing lanes or using shoulders to
    maintain number of lanes contract
    incentives/disincentives lane rental damages
    for late lane opening night work
  • Use "Triggers" - e.g. when 75 of max delay is
    approached, lane(s) are opened to accommodate
    traffic
  • Consider using extended closures or full closures
    versus numerous night closures
  • Use strategies that facilitate decision-making by
    the public to avoid the WZ (e.g., public
    awareness, advance signage in locations prior to
    key motorist decision points) these tend to be
    highly effective
  • Update the TMP, as needed, throughout project
    development and implementation
  • TMP training is important for all divisions
    involved in TMPs
  • Management support is needed for effective TMP
    efforts

38
TMP Resources
  • Caltrans TMP Resources Web Site -
    http//www.workzones.ucdavis.edu/index.php?titleT
    MPMain
  • Fact Sheet Caltrans TMPs Reduce WZ Congestion
    http//www.ops.fhwa.dot.gov/wz/practices/factsheet
    s/factsheet11.htm
  • Virginia DOT TMP Requirements -
    http//www.extranet.vdot.state.va.us/locdes/electr
    onic20pubs/iim/IIM241.pdf
  • Missouri DOT TMP Strategy Database -
    http//www.modot.org/Safety/TMPStrategyMatrixVer6j
    .mdb
  • Presentation on Californias TMP Development
    Process - http//www.ntoctalks.com/webcast_archive
    /to_feb_17_05/to_feb_17_05jg.ppt
  • Presentation on Virginias TMP Development
    Guidelines - http//www.ntoctalks.com/webcast_arch
    ive/to_mar_19_07/to_mar_19_07_pk.ppt

39
TMP Resources
  • WZ Safety and Mobility Rule Web Site -
    http//www.ops.fhwa.dot.gov/wz/resources/final_rul
    e.htm
  • Contains sample TMPs, presentations, and TMP
    development resources
  • Developing and Implementing TMPs for Work Zones -
    http//www.ops.fhwa.dot.gov/wz/resources/publicati
    ons/trans_mgmt_plans/index.htm
  • Contains a TMP Checklist and matrix of TMP
    strategies
  • Advanced Work Zone Management and Design Course
    (NHI) - http//ops.fhwa.dot.gov/wz/outreach/nhi_wz
    _courses.htm
Write a Comment
User Comments (0)
About PowerShow.com