HOOVER DAM - PowerPoint PPT Presentation

About This Presentation
Title:

HOOVER DAM

Description:

HOOVER DAM By Project Monsters Presenters: Nazimah Abdul Rahim Hakki Isik HOOVER DAM Concrete dam in Black Canyon, on the border between Arizona and Nevada Named ... – PowerPoint PPT presentation

Number of Views:461
Avg rating:3.0/5.0
Slides: 18
Provided by: webAugsb
Learn more at: https://web.augsburg.edu
Category:
Tags: dam | hoover

less

Transcript and Presenter's Notes

Title: HOOVER DAM


1
HOOVER DAM
  • By Project Monsters
  • Presenters Nazimah Abdul Rahim
  • Hakki Isik

2
HOOVER DAM
  • Concrete dam in Black Canyon, on the border
    between Arizona and Nevada
  • Named after Herbert Hoover, who played an
    important role in its construction
  • Built by Six-Companies, Inc.
  • Operated by Bureau of Reclamation of the US Dept.
    of the Interior
  • Lake Mead is the reservoir constructed behind the
    dam

3
The Need for a Dam
  • Turbulent Colorado River periodically flood vast
    areas of California and Arizona
  • The flood destroyed canals built for irrigation
    and drinkable water
  • Herbert Hoover proposed construction of the high
    dam to solve the problems

4
Who is Herbert Hoover?
  • Was Secretary of Commerce under President
    Coolidge
  • Graduated from Stanford University
  • A successful mining engineer, humanitarian
  • Elected as the 31st President of the United
    States

5
Questions That Were Raised
  • What would be the location of the dam?
  • Who would build the dam?
  • How would the dam going to be financed?
  • Which states would get the water and electricity?

6
Scope
  • Construction of the high dam would control the
    periodic floods, store water for irrigation,
    municipal and industrial use
  • The customers would be the people getting water,
    electricity from the dam

7
Resources
  • 5200 workers on the construction with 3
    shifts/day
  • 5 millions barrel of cement used in the concrete
  • 9,000 tons of structured steel components
  • 44,000 tons of large steel pipe and fittings
  • Giant cooling towers

8
Time Management
  • Hoover met with the 7 state governors
    (AZ,CA,CO,NV,NM,UT,WO) to work out suitable
    arrangement for their states use
  • November 1922, Colorado River Compact was signed
  • In 1928, the Congress passed the Boulder Canyon
    Act, allocating 175 million for the dam
    construction

9
Time Management
  • Composite bid was accepted for 50 mil by Six
    Companies in March 6 1931
  • Construction began in April 20 1931
  • June 1931, sufficient housing facilities were in
    place
  • Construction was completed in March 1, 1936
  • The construction was completed 2 years ahead of
    schedule

10
Cost Management
  • The most difficult part of the project period
    of Great Depression
  • It cost a total of 165 million - 49 million to
    build the Hoover Dam
  • Unskilled labor paid 4/day and minimum wage cost
    was lt6/hr
  • Paid back over a period of 50 years to Federal
    Treasury by selling electricity

11
Project Management
  • One of the biggest engineering project at that
    time - also the greatest testimony to functional
    organizations and old fashioned management
    control techniques
  • Active management was left in 4 hands Henry J.
    Kaiser, Charles A. Shea, Felix Kahn and S.D.
    Bechtel

12
Project Management
13
Project Management
  • Frank Crowe (a.k.a Hurry Up) worked under Shea
    acted as the man point between Board of Directors
    and the operations personnel
  • It was Sheas responsibility to carry out the
    construction on time and budget
  • Each department was headed by a manager and held
    accountable for their work

14
Project Management
  • Dam construction was divided into 3 areas
  • Diversion tunnels and penstocks
  • Concrete arched structure
  • Power plant

15
Problems
  • Workers strike (August 1931) triggered by
    deaths of many of the workers wives and children
    due to extreme heat and lack of sanitation in the
    campsite area
  • Huge dam size required a lot of cement and
    engineers predicted it would take 125 years to
    dry and cure
  • Heat generated in the chemical rxns in the drying
    process would physically alter the landscape

16
Solutions to the Problem
  • Housing facilities were built, known as Boulder
    City
  • Giant cooling tower/plant built to cool the
    entire dam pumped ice water (37oF) at 1000
    gal/min as the concrete was poured
  • With this approach, the dam was cooled in 20
    months

17
FAQs
  • Height 726.4 ft
  • Weight 6.6 million tons
  • Total storage capacity 30.5 million acre ft
  • Power generating capacity 2.8 million kW
  • Has 17 generators
  • Part of a system that provides water to over 25
    million people in Southwest United States
Write a Comment
User Comments (0)
About PowerShow.com