Title: Enforcement Case EC 0534


1
Enforcement Case EC 05-34
  • Respondent Moose River Docking Association
  • Location Rockwood Strip Twp T1 R1 NBKP,
  • Somerset County

2
Location MapRockwood Strip Twp. T1 R1
NBKPSomerset County
3
Location Map
4
Zoning Map and Property Information
Taxation Lots 4.1 and 4.2 on Plan 06 0.6
acres with 295 feet of frontage on the Moose
River (D-RS) Residential Development
Subdistrict
5
Background
  • Pre-1971 Property was developed with a
    single-family residence, commercial retail store,
    commercial marina, and parking facilities (all
    non-conforming).
  • January 2005 Development Permit DP 4706 was
    issued to the Moose River Docking Association
    authorizing conversion of property to a private,
    shareholder-owned marina.

6
Development Permit DP 4706Authorized
  • Removal of retail store and residence.
  • Removal of pre-LURC cribwork boat slips and
    shoreline fill.
  • Rip-rap along entire shoreline.
  • Creation of 60 ft. by 190 ft. gravel parking area
    (approx. 1/3 of lot would be planted with grass
    and used for overflow parking only).
  • Replacement of existing fuel tank and containment
    structure
  • Installation of three floating finger docks to
    accommodate 36 boats, not to exceed one-third the
    width of the river.

7
Description of Activities and Violations
  • Activity
  • Installed riprap along shoreline during a period
    of high water in May 2005.
  • Violation
  • Condition 11 of DP 4706Any excavation or
    construction related to the alteration of the
    shoreline must be done when the water level is
    lower than the work area.

8
Photos
Photo taken May 5, 2005, within a week of when
the riprap was installed High water is evident
9
Description of Activities and Violations, cont.
  • Activity
  • Installed three docks in summer 2005, length of
    docks were 88 ft., 90 ft., and 109 ft.
  • Violation
  • Condition 8 of DP 4706The authorized docking
    structures must not extend into the Moose River
    at a length greater than one-third the width of
    the river.

10
Site Diagram of Docks
11
Photos
Photo taken July 7, 2005, shortly after the
floating docks were placed in the river
12
Photos
13
Description of Activities and Violations, cont.
  • Violation
  • Both activities are also violations of 12
    M.R.S.A. Section 685-B,5
  • Commission authorization pursuant to this section
    shall permit only the arrangement and
    construction set forth in the approval as issued,
    change in use, arrangement or construction shall
    be considered a violation of this chapter and
    punishable as provided in this chapter.

14
Terms of Settlement
  • Pay 2,000 civil penalty
  • Comply with all terms and conditions of
    Development Permit DP 4706 and any subsequent
    amendments
  • Note Docks had been removed from river as of
    October 2005 for winter storage. Operation of
    the marina has not yet started. The respondent
    must obtain a Certificate of Compliance (COC) for
    the property before operations may commence.

15
Staff Recommendation
  • Staff believe that this agreement is in keeping
    with your Compliance and Enforcement Response
    Policy and recommend ratification of the
    agreement.