Title: Urban Infrastructure: Issues in structuring bankable projects
1Urban Infrastructure Issues in structuring
bankable projects
- ASCI-World Bank Programme on Strengthening Urban
Management (SUM) -
- January 23, 2003
2Often heard at seminars
- Small is beautiful
- Get your act together
- Firm up YOUR objectives first
- but recognize that others have their objectives
too - Experiment
- but be willing to correct yourself
- Stand by your commitments
- Do not ignore the ultimate customer/user
- Beware of smart/over-confident developers
Sounds like preaching? Read on ...
3Structure of the Presentation
- Select illustrations of PSP in infrastructure
- Urban Infrastructure projects
- Port sector projects
- Road sector projects
- Lessons from experience so far
- Objectives Concerns of various stakeholders
4Illustrations with wide coverage
- Sectors Covered
- Urban Infrastructure
- Ports
- Roads
- States Covered
- Power/Telecom omitted
- 14
- 10
- 12
- Projects from 10 states
- Kerala, Karnataka, Tamil Nadu, Andhra Pradesh
- Maharashtra, Goa, Gujarat, Madhya Pradesh,
Chhattisgarh - West Bengal, Orissa
- Rajasthan, U.P., Bihar
Well, there are lots of cases and a few good
lessons!
5Ahmedabad Municipal Corporation
- AMC became the countrys first municipality to
raise bonds from capital markets - Bond raising preceded by an internal
restructuring and revenue enhancement measures - Bond proceeds used for water supply schemes
- Bonds secured by a charge on octroi revenues of
AMC - Utilisation of bond proceeds have been slow as
project implementation has been delayed - Lesson Careful planning timing is necessary
for sustainable project implementation processes
6Bangalore Water Supply Project
- Private participation was sought for 500 MLD BOOT
project by BWSSB - Bidding preceded by technical and demand studies
- After pre-qualification, three consortia
submitted final proposals - The project was nearly awarded to a consortium
led by Biwater International but the bidding
process has been questioned and resulted in
delays - Lesson Clear bidding parameters required to be
stipulated process transparency to be ensured
7Chhattisgarh - Borai Water Supply Project
- Borai Bulk Water Supply Project is set up on BOOT
basis as an industrial bulk water supply for
Borai Industrial Growth Centre (BIGC) in Durg
district, Chattisgarh under concession from CIDC - It is a Project 30 MLD project with a cost of Rs.
420 mn. (including existing assets valued at Rs.
160 mn.) - Radius Water Ltd. promoted by Kailash Engineering
is the concessionaire - The first phase (12 MLD) of this project is
already operational but there are some hiccups as
to drawal rights and further expansion - Lesson Risk taking ability of the promoter
helped this project go quickly through the
initial stages.
8Chennai Desalination Project
- Chennai Metropolitan Water Supply and Sewerage
Board (CMWSSB) mooted a project for implementing
the tertiary treatment / Reverse Osmosis plant of
50 MLD capacity at Kodungaiyur, Chennai on a
Design, Build, Own and Operate basis - The submission dates were postponed a number of
times as CMWSSB was not sure of attractiveness to
investors - Ultimately it bid out both EPC DBOO as
alternate options - Result There were only two bids both on an EPC
basis (LT and BHEL). Meanwhile VA Tech Wabag
another party chose to bid for a limited size
project on captive basis for CPCL one of the
major clients of CMWSSB - Lesson There is no harm in experimenting but
first get your objectives right
9Cochin Industrial Water Supply
- Mooted by KSIDC, which invited IFC to assist
- Basic project preparation was carried out
including detailed technical studies as well as
demand estimates - Alternate project structures were evaluated
- Meanwhile KWA signed an agreement with Cochin
Refineries, a major user allowing an off-take of
water - Lesson Co-ordination among government agencies
required for project development
10Goa Salaulim Water Supply
- Goa PWD had invited proposals for water supply
project on a BOOT basis (with an option to bid in
an alternative innovative format) - BOOT bids were found very costly and then the GoG
thought of alternative concession route - The bidder questioned GoG's demand forecast
- At present due to successive changes in the
Government the process has been temporarily
suspended - Lesson Inadequate homework by the state
authorities
11Haldia Industrial Water Supply Scheme
- HDA has sought private participation and received
over 25 Expressions of Interest - Despite adequate demand many technical issues
(salinity, mix of ground water and river water,
etc.) remain unresolved - HDA decided against technical study, no project
parameters have been set up may instead go
directly for BOT or EPC/OM contracts (but may
not have funds) - Potential investors/bidders are unhappy as there
is no progress - Lesson Project has not been thought through
clearly
12Nagpur Municipal Bonds
- NMC proposed a Rs. 1.17 bn. capital expenditure
programme under Pench-III Stage-I project of the
Corporation, which envisages capacity creation in
the water supply services - Nagpur Municipal Corporation proposed to raise
Rs. 0.90 bn. from issue of Bonds to partially
meet its requirement, the balance coming from
from internal accruals and grants from State
Government - With a AA-(SO) rating by CRISIL SBI Capital
Markets as arranger could raise only Rs. 0.30
bn. even after extending dates several times. - NMC however carried through with its tariff
reforms (water property taxes) postponed the
implementation till it could generate adequate
internal accruals - Lesson Bhagwan ke pas der hai lekin Andher nahi.
13Pune Water Supply Project
- Water Supply Project conceived with structuring
assistance from USAID - Project conceived as EPCOM with funding from
funds raised by PMC - Also a separate contract for management of
billing limited collections - Project generated considerable investor interest
as careful planning had gone into the project
preparation - Bidding Process was terminated prematurely
- PMC is now implementing the project on its own
- Lesson Political risk (the power of lobbying
groups) in the project was underestimated
14Tiruppur Water Supply Project
- Project was conceived by ILFS with support from
GoTN, TACID and Industry - Proposed as a BOOT project for sourcing,
treatment and supply water mainly to industry
with some social coverage - Tiruppur industry comprises of garment exports
and willingness to pay is higher - However, the project has taken considerable time
to develop resulting in cost escalation - The cost of water for the commercial users has
more than doubled during this period - Reached financial closure 8 years after
conceiving! - Lesson Complex projects are difficult to
implement and subject to diverse risks
15Consider this the city of Ahmedabad
- GIDB has proposed an Integrated Public Transit
System for Ahmedabad (IPTS) and appointed a
consultant for the studies - AMC became the countrys first municipality to
raise bonds from capital markets for various
projects (primarily water) - Sabarmati Riverfront Development Corporation
(SRFDC) an organisation set up by AMC is
proposing a massive area development project with
the help of a local not-for-profit organisation
(EPC) - Lesson Lack of integrated project development
for the same city (and now watch out Mumbais
integrated development)
16Mumbai non-toll bridge within city
- Project conceived as self-financing bridge
- 1.5 kms long flyover bypassing three junctions at
Andheri on Western Express Highway. - To be financed by selling commercial property
under the bridge. - Underground car park, two storeys of commercial
property with a six lane carriageway on top. - Project delayed initially due to delay in
approvals and later due to litigation over
alleged environmental issues now real estate
prices not at high levels. - Lessons Lack of coordinated efforts,
insensitivity to local and environmental issues
and non-transparent procedures.
1750 flyovers in Mumbai
- 50 flyovers to be financed initially through bond
issue and recovery through an entry toll (Rs.
20/-) - Tolling commenced sometime back but was met with
stiff resistance from Transporters Associations
and court has put a stay on tolling - MSRDC is fast running out of funds (on account of
the flyovers as well as the Express way) but
revenues not as per expectations - Now MSRDC would be reimbursed through a fuel cess
on all Mumbai Petrol Pumps - Lesson Realistic assessment of willingness to
pay (also, pay for use principle flouted)
18Kolkata Car Park (Rowden Street)
- Kolkata Municipal Corporation (CMC) awarded
multi-level automated car park project to Simplex
Projects - Project details
- Location Rowden Street (in the vicinity of Park
Street) - Project Cost Rs. 90 mn. (CMC interest free
advance Rs. 30 mn.) - Car Parking 216 cars at Ground 2 levels
- Technology Machinefabriek Aarding BV of
Netherlands - Revenues from Car Parking Advertisements
- Performance Revised estimate for first full year
of operations are at 55 of projected as the no
parking zone has not been fully enforced
resulting in lower car parking revenue - Lesson The corporation needs to stand by its
commitments
19Mumbai - Car Park at Breech Candy
- Municipal Corporation of Greater Mumbai (MCGM)
has bid out Car Park cum Commercial Development
Project near Breech Candy Hospital on a BOOT
basis - Bidding Parameters
- Upfront payment of premium to MCGM
- No. of cars two wheelers that can be parked
- Bids received are a veritable mix of combinations
of no. of car parks promised and upfront premium
payment assured - Current Status Bidders have been asked to make
presentations on their project proposals
showcasing the technologies used (capital cost,
operating cost access time) - Lesson Lack of adequate project preparation to
ensure clear transparent bidding process
20Bidding Results (Mumbai Car Park)
21Structure of the Presentation
- Select experience of PSP in infrastructure
- Urban Infrastructure projects
- Port sector projects
- Road sector projects
- Lessons from experience so far
- Objectives Concerns of various stakeholders
22Container terminals at Chennai Kandla JNPT
- In the mid-90s a number of projects were bid out
in major ports for private sector - Privatisation of container terminals was awarded
to PO a large international Ports Shipping
group at Kandla, JNPT, Cochin Chennai - Despite some initial hiccups the JNPT project
went through to financial closure. - The Chennai Container Terminal took some further
time (in years!) while Kandla became a major
controversy leading to a showdown between the
Port Trust MoST. Cochin was not pursued by PO
as some comforts were not forthcoming. - Lesson The Government was unable to resolve key
issues and/or read the real issues in competitive
behaviour
23Container terminal at JNPT
- BOT Project with a world class facility at a
cost of Rs. 7.50 bn. - Promoted by one of the worlds leading maritime
business group. - JNPT did not allow first charge on project assets
to the lenders and other amendments to the
concession agreement.
- So project financing was not available and
ultimately the project was financed with the
support of sponsor guarantee. - Lesson Despite hurdles, strong promoters can
make project happen.
24Container Terminals current status
- As everyone is aware, JNPT (PO) is a major
success story - But despite this, and an aggressive lobbying
effort by PO, the new (revised) bidding
conditions for the proposed new container
terminal at JNPT explicitly disallows bidding or
investment by PO in any form - Cochin Container Terminal now comes as a package
of phased development (handing over of existing
terminal followed by development of Vallarpadam) - Kandla Container Terminal finally did not proceed
- Adani sponsored Mundhra Port is now developing a
Container Terminal which may be divested in
favour of PO - Lesson At times it is difficult for the
Government to understand the machinations of the
private sector
25Dharma port project in Orissa
- Proposed green-field port for dry bulk cargo at
an estimated cost of Rs. 15 bn. - To be developed on BOOST framework.
- Promoted by a JV of an Indian engineering company
and two foreign companies. - Significant delays in finalization of changes in
concession suggested by lenders. - Meanwhile both foreign sponsors have walked out
of the deal while one firm ran into financial
difficulties the other had lost interest due to
delays and disagreement with respect to its
potential role in OM for the project - Lesson Lack of application and push by all
parties.
26Chemical terminal at Dahej, Gujarat
- Greenfield liquid chemical handling facility at
an estimated cost of Rs. 8 bn. - Developed on a BOOT framework.
- Promoted by a JV of GMB, GIIC and four Indian
petrochemical and fertiliser PSUs. - Project physically complete and operational
without the concession being signed and without
financial closure. - Multiplicity of promoters and speed of response
is a key issue. - Lesson Too many cooks spoil the broth.
27Enron, Dabhol OWMSL
- Ocean Sparkle Ltd. based in Hyderabad formed a JV
with Weismueller of Netherlands to bid for and
win a mandate for providing port services to the
LNG Terminal at Dabhol - Project Comprising of state of the art 4 tugs
costing Rs. 800 mn. To be built to the
specifications of The DPCs OM operator (a
subsidiary of Enron) and operate for 20 years - Project reached financial closure despite
on-going problems at DPC and the tug-of-war with
MSEB - By the time the plant closed down, the tugs were
ready for delivery but no Enron to certify!
Weismueller agreed to buy the tugs for
redeployment and settled loans - Lesson In large projects, the smaller parties
fall by the wayside but are saved only if they
have some back-up.
28Haldia Berth 4A for coking coal
- Haldia Port bid out development of Berth 4A for
handling coking coal imports required by steel
plants - ISPL was awarded the contract and they
simultaneously approached project financiers and
Steel Authority (a likely major off-taker) - Despite considerable delays, ISPL was able to
reach a 20 year contract with SAIL for using
their facility for importing coking coal, an
important ingredient in Steel Production - Project lenders unsuccessfully sought a number of
amendments to the Concession Agreement
(essentially in line with the Model Agreement
drafted by IDFC for MoS) - Lesson Small project, long off-take contract,
viability beyond doubt a formula for success
29Structure of the Presentation
- Select experience of PSP in infrastructure
- Urban Infrastructure projects
- Port sector projects
- Road sector projects
- Lessons from experience so far
- Objectives Concerns of various stakeholders
30Noida Toll Bridge
- Project comprises a 6-lane bridge over Yamuna
river and approach roads costing Rs. 4.00
billion. - Flyover at Ashram road junction required for
smooth traffic flow from the project delayed. - Traffic significantly lower than appraisal
estimates. - Average daily collection is Rs. 0.27 million(Debt
service liability about Rs. 1.70 million/day) - Lesson Co-ordinated development of linkages and
accurate traffic estimation key for project
success.
31Coimbatore By-pass
- By-pass on NH-47 developed by LT on BOT basis
- Toll-free alternative available to local traffic
- Subsequent to the award of the project, scope
enlarged to include strengthening of Attupalam
bridge before the by-pass - Toll-free alternative no longer available
- Hence local opposition to toll collection
- Earlier, willingness to pay did not capture such
an event - Lesson Project structure should be sensitive to
local traffic
32Durg by-pass
- By-pass on NH-6 developed by Sancheti group on
BOT basis - Toll-free alternative available to local traffic.
- Project scope includes a river bridge and ROB.
- NHAI provided sub-debt and limited shortfall
guarantee. - Project completed almost as per schedule.
- No local opposition to toll collection.
- Project in operation for two years.
- Lesson Being first project, project reached
closure with help of financial support from NHAI.
33Delhi-Gurgaon Expressway Project
- Originally conceived in mid 1990s, CIDB, Malaysia
was to be mandated in 2000 to complete this
project as part of govt-to-govt initiative, but
the proposal sought a grant of Rs. 1.20 bn. from
NHAI, and was thus rejected. - This year the project bid out by NHAI for Capital
Subsidy (Grant) received a number of bids
promising premium instead and was awarded to
Jaiprakash Industries-D.S.Construction consortium
which offered the highest Rs. 615 mn. Premium - The project is adversely affected by recent Court
order on ban of polluting vehicles (non-CNG
trucks/busesa) entering New Delhi - Lesson Classic case of the nature of risks in
infrastructure projects. Who is right CIDB or
Jaiprakash?
34Mattancherry Bridge at Cochin
- First BOT bridge project in Kerala State GCDA
acted as the sponsor authority - Other agencies involved - KSIDC, CPT, Cochin
Corporation and PWD - Project was offered on a BOT basis and bid for
concession period. At bidding stage Traffic
studies, technical studies draft concession
agreement was given to bidders - Project has been awarded to Gammon India
- Lesson Initial investment on project preparation
yields high returns
35PPP in NHDP
The NHDP has been partially successful in
attracting private sector investment.
36PPP or not to P(rivatise)
Mumbai Pune Expressway cost was Rs. 16 bn. (as
per contractors bids) and now on completion it
is Rs. 22 bn. Reliance had quoted Rs. 30 bn.
including 1000 hectares of land acquisition
- Construction Contract
- Rs. 280 mn. Per Km.
- This is an item rate contract (not FTFC EPC)
- Add a further Rs. 80 mn. (Pre-op, IDC, Fees,
etc.) - At Rs. 360 mn. per km. this is still far lower
than ..
- Annuity Project Cost
- Rs. 500 mn. per km.
- A typical BOT project (either annuity or toll
based) - Rs. 500 mn. per km.
- Now add Rs. 140 mn. for escalation due to extra
work to get Rs. 500 mn. - Add now for 15-20 years of repairs maintenance
- No further addition, Project cost still Rs. 500
mn. per km. - Project cost still Rs. 500 mn. per km.
37PPP in roads are maturing
- Toll-based BOT
- Annuity Scheme
- Grant/Capital Subsidy
- Reverse Grant/Premium
- OM/Tolling Contracts
- Real-estate linked project
- Many state level projects
- 6 projects awarded
- Jaipur-Kishengarh (NHAI)
- Many projects in M.P.
- Delhi-Gurgaon
- 4-lane NHDP stretches
- Mumbai-Pune Exp. Way
- Mahakali Flyover, Mumbai
- Vivekanand Flyover, Kolkata
- Bangalore-Mysore Infrastructure Corridor
38Comparison of Expressways dev.
39Structure of the Presentation
- Select experience of PSP in infrastructure
- Urban Infrastructure projects
- Port sector projects
- Road sector projects
- Lessons from experience so far
- Objectives Concerns of various stakeholders
40Some case studies ..1
- East Coast Road vs. Tiruppur Noida Toll Bridge
- Durg Bypass vs. Jaipur-Kishengarh
- Bhiwandi Bypass vs. Mumbai-Pune Expressway
- Dhamra vs. Haldia berth 4A Kakinada
- Small is beautiful
41Some case studies ..2
- Coimbatore Bypass (sensitivity to local traffic)
- Mumbai Entry Point Tolls (user pay principle
challenged) - Noida Toll Bridge (international class but low
turnout) - Do not ignore the ultimate customer/user
42Some case studies 3
- AMC Bonds (Utilisation of proceeds)
- City of Ahemedabad (GIDB vs. SRFDC)
- Cochin Industrial Water Supply (KSIDC vs. KWA)
- Haldia Development Authoritys Water Supply
Project - Get your act together
43Some case studies 4
- Goa Salaulim Water Project (BOOT or Concession)
- CMWSSBs Chennai Desalination Project (EPC or
BOT) - Mumbai Car Park (upfront payment or no. of cars)
- Firm up YOUR objectives first
44Some case studies 5
- Mattancherry Bridge (insisted on upfront payment
but later relented) - NHAIs Palasit Panagarh (rebid after initial high
bids) - Durg Bypass (selected weak promoter but later
extended guarantee sub-debt support) - MMRDAs Convention Centre (bidding failed twice)
- Experiment but be willing to correct yourself
45Some case studies 6
- Jaipur-Kotputli Toll Collection Operations
- Mahakali Flyover (PIL subsequent developments)
- NOIDAs Dadri Bridge (UPSBC upstages Simplex)
- Bidding for Container Terminals in the country
- Beware of smart/over-confident developers
46Some case studies 7
- Kolkata Car Park (enforcement of no-parking zone)
- BOT Roads in general (timely toll notification)
- Road Bypasses (enforcement of ban on through
traffic) - Tax benefits under 10-23 (g) (delays/denial of
Certificate) - Enron !!!!!
- Stand by your commitments
47Summary Some practical lessons
- Small is beautiful
- Do not ignore the ultimate customer/user
- Get your act together
- Firm up YOUR objectives first
- but recognize that others have their objectives
too - Experiment
- but be willing to correct yourself
- Beware of smart/over-confident developers
- Stand by your commitments
Still sounds like preaching?
48Some practical approaches
- Institutionalize your approach through a vehicle
- PIDB, GIDB, I-Deck, I-Kin, I-Win, APIIF, MPIDB,
CIDC - Find a champion give him a long tenure
- First develop small medium projects to
demonstrate success - then replicate
- Give importance to good project preparation
- and not just to announcing good sounding
projects - Keep the bidding simple evaluate on just one
key parameter - Hire advisors to help!
49Need for PSP
- Private Sector Participation is sought to
essentially bring in - Private capital
- Private management
- New better technology
- The modality of PSP critically depends on exact
objectives sought to be achieved
50Why private sector participation?
- Economic/Political Reasons
- Policy of privatisation
- Fostering competition
- Commercial principles
- Pay-for-use culture
- Political bottlenecks in tariff restructuring or
reduction in subsidies - Management Reasons
- Better management of all resources operational
efficiency - Improved level of service and responsiveness to
users
- Financial Reasons
- Budgetary priorities and constraints
- Additionality of funds
- Better utilisation of financial resources
- Other reasons
- New and better technology
- Involvement of users and other stake holders
- Environmental requirements
51Different modes of PSP can be explored
52Lessons from past experience
- Reasons for failure attributable to one or more
of the following - Inadequate framework for PSP
- Insufficient project preparation development
- Failure to address concerns of all stakeholders
53Framework for PSP
- Clarity in objectives of PSP
- Institutional restructuring to coincide with PSP
initiatives - Regulatory framework to be put in place
- Managing political risk and willingness to pay
issues
54Project preparation development
- Co-ordination issues Identification of nodal
agency and defining roles of other agencies - Establishing independent commercial viability of
the project demand, revenues costs - Identification of risks, allocation mitigation
- Project structuring role of private sector
- Comprehensive information memorandum covering
studies draft contract agreements - Designing transparent competitive bidding process
- Transparent fair procurement process
55Stakeholder concerns
- Capacity building of government / public agencies
- Interest and capacity among private sector
operators - Building awareness for pay for use principle
among consumers and communities within society - Addressing financing issues of lenders and
investors - Ensuring adequacy of services at affordable rates
to the urban poor
56Structure of the Presentation
- Select experience of PSP in infrastructure
- Urban Infrastructure projects
- Port sector projects
- Road sector projects
- Lessons from experience so far
- Objectives Concerns of various stakeholders
57Government/Local Authority
- Sustained improvement in provision of
Infrastructure - Conserving scarce public resources
- Creation of facilities and provision of efficient
services - Transparency and fair process
- Protection of Social/Developmental commitments
58Developer/Investor
- Commercial viability of project
- Freedom flexibility in conduct of business
- Avoidance of risks beyond control
- Fairness in transaction
- Delays in approvals
59Project Financiers/Lenders
- Financial viability of project
- Acceptable concession framework
- Freedom to exercise step-in-and-cure-rights
- Protection against defaults by Government and
developer
60Consumers/Users
- Availability of facilities services
- Acceptable levels of tariffs/taxes/tolls
- Appropriate grievance redress system
61Thank You
62Feedback Ventures Ltd.e-mail contactus_at_feedbackv
entures.comInternet http//www.feedbackventures.
com
Delhi Feedback House7, Local Shopping
CentrePanchsheel ParkNew Delhi
110017India Tel (011) 2649 5766-68 Fax (011)
2649 5762/65
Mumbai Bengal Chemicals Bhavan,3rd Floor,502,
Veer Savarkar Marg, PrabhadeviMumbai
400025 Tel (022) 5661 3632 Fax (022) 5661 3631
Hyderabad 7, Amruta Business Complex,
2nd Floor Ameerpet Hyderabad 500 016 India Tel
(040) 2375 6481 Fax (040) 2375 6482
63What is project finance
- Project Finance is a technique of non-recourse or
limited recourse financing in which the project
lender principally look to the cash flow of a
single project as security for their long-term
loans. - In India the term Project Finance was generally
applied to long term loans given by Term Lending
institutions (Fis) to new (or modernisation/
upgradation) industrial projects as compared to
working capital facility extended by commercial
banks.
64Extent of sponsor recourse
- Full-recourse
- Akin to corporate finance
- Non-recourse finance
- Extremely rare
- Limited recourse finance
- Completion guarantees
- Undertakings to cover cost overruns
65Limited recourse financing...
- Insulates sponsors from project debt and risk of
project failure - Enables them to share some risks in a large
project with other participants - Overcome the inability to borrow through a
corporate loan as balance sheet cannot support
the project debt
66Project finance is cash flow based
- Cash flow based financing for infrastructure
projects - Significant value of the project is derived from
intangibles and not from the assets created - Estimation of debt requirement of the project
depends on the future cash flows of the project
as against the capital expenditure incurred in
conventional projects - Telecom/ Ports based on peak cash negative
- Power/Roads cash requirement till project
completion
Future cash flows from the project are the
primary source of debt repayment
67Project finance needs strong security structure
- Security structure needs to be more stringent
than a normal project assistance and typically
includes - - Legal mortgage of all assets, including
receivables (as opposed to the normal equitable
mortgage) - Pledge of promoter shareholdings in the project
company - Escrow mechanism for cash flows of the company
- Assignment in favour of lenders of all the
project contracts
68Project finance vs. corporate finance
69Lenders approach to financing
- Focus on economically strong projects
- Back strong sponsors with successful track record
in implementing large projects - Comprehensive due diligence on all counterparties
(incl. EPC contractor, OM contractor, Licensor,
etc) - Insist on complete financial closure before
commitment of any funds - Arranging project finance requires substantial
time and cost
70Basis for lenders risk aversion
- Lenders have the maximum money on a project rated
at BBB and the minimum returns - whereas
- The developers put a small money as equity and
aspire for supernormal profits - The Users get a facility for which they can pay
if they so wish (or protest/use alternatives,
etc.) - The Government puts no money but has the right to
intervene, take over if it is dissatisfied - yet
- the lenders lenders are not so easy on them and
besides expecting a AAA rating also face
stringent RBI/SEBI regulations
71Risks over the 3 project phases
- Lenders identify three separate phase of risk
over the life of the project
Engineering Construction Phase
Operation Phase
Start-up Phase
Physical Completion
COD
72Project finance lifecycle
Arranger Mandate
Disbursements
73FIMMDA Annualised Spreads
Source http//www.fimmda.org
74Different modes of PSP can be explored
Project Financing required
75Common Project Structures 1
- Build-Operate-Transfer (BOT)
- New Asset/facility against collection of user fee
- investor rights revert back to the public
authority at the end of the concession - ownership vests with the public authority
- used for highways, utilities and ports
- Build-Own-Operate (BOO)
- similar to BOT but without the transfer of rights
- may also stipulate payment of some fee to the
public authority for the right to operate the
facility - used for telecom and power projects
76Common Project Structures...2
- Built-Own-Lease-Transfer (BOLT)
- assured revenue through lease rentals
- proposed for Indian Railways
- Built-Own-Operate-Share-Transfer (BOOST)
- revenue shared with the public authority
- Minor ports proposed in some states
- Annuity structure
- Concessionaire responsible for construction and
OM - Concessionaire receives fixed annuity over the
concession - Proposed for National Highways projects
- Likely to replace Railways BOLT scheme