Operations Management Council Internal Controls Status Meeting - PowerPoint PPT Presentation

1 / 82
About This Presentation
Title:

Operations Management Council Internal Controls Status Meeting

Description:

The detailed plan will be provided in the Corrective Action Tracking System ... managerial issues within both the Space Shuttle Program and NASA as a whole that ... – PowerPoint PPT presentation

Number of Views:100
Avg rating:3.0/5.0
Slides: 83
Provided by: kcar94
Category:

less

Transcript and Presenter's Notes

Title: Operations Management Council Internal Controls Status Meeting


1
Operations Management Council Internal Controls
Status Meeting
  • Tuesday, February 14, 2006
  • 1230 pm - 230 pm
  • NASA Headquarters
  • Room 2X40

2
Status Meeting Agenda for February 14th
  • Introduction Ms. Dale 5 min.
  • Overview of NASA Internal Control Mr. Jedrey 10
    min.
  • Status of Actions from Nov. 9 Meeting Mr. Jedrey
    5 min.
  • Target
  • Corrective Actions on Internal Control
    Deficiencies Correction Date
  • Asset Management (MW) OCFO 10 min. 09/30/06
  • Financial Management System (MW) OCFO 10
    min. 11/15/06
  • Financial Management Data Integrity (MW) OCFO 10
    min. 09/15/06
  • Financial Mgmt. Policy Procedures (MC) OCFO
    5 min. 06/30/06
  • Financial Management Staffing (MC) OCFO 5
    min. 09/30/06
  • Full Cost Integration (OW) OCFO 5
    min. 12/31/06
  • Space Shuttle (MW) SOMD 10 min. 06/30/06
  • Shuttle Impact on ISS Operations (MC) SOMD 5
    min. 06/30/06
  • Information Technology Security (OW) OCIO 5
    min. Ongoing
  • NASA Declassification Program (MC) OIM 5
    min. 12/31/06
  • Open GAO Audit Recommendations (MC) OIM 5
    min. Ongoing
  • Mission Management Aircraft (OW) OIM 10
    min. 06/30/06

Key Material Weakness (MW) Other Weakness
(OW) Management Challenge (MC)
2
3
Reason for Senior Level Emphasis Internal
Control
  • Key Law Federal Managers Financial Integrity
    Act (1982) applies to programmatic, financial,
    and institutional controls
  • GAO Standards for Internal Control in the Federal
    Government (1999) provides 5 standards for
    implementing the law
  • Sarbanes-Oxley Act of 2002 prompted by
    enormous bankruptcy scandals of Enron in 2001 and
    WorldCom in 2002, this law requires strict rules
    on corporate governance
  • OMB Circular A-123, Managements Responsibility
    for Internal Control (revised 2004) responds to
    Sarbanes-Oxley thrust applied to federal
    government and to place more emphasis on GAOs
    standards
  • Revised NPD 1200, NASA Internal Control and
    Accountability (2006) presents Agency policy for
    implementing OMB Circular A-123 with tie into
    NASA Strategic Management Governance Handbook
    (NPD 1000.0)

3
4
Key NASA DefinitionsLevels of Internal Control
Deficiencies
  • Material Weakness (MW) a deficiency in
    internal controls that is significant enough to
    be reported outside the Agency.
  • Other Weakness (OW) a deficiency in internal
    controls that should be reported and monitored
    internally.
  • Management Challenge (MC) a concern about a
    challenge to management. There is insufficient
    information to confirm a serious systemic
    internal control weakness in this area. It may
    pertain to issues that are outside managements
    control or factors that may create an adverse
    condition. Close monitoring is required.

4
5
Examples of Internal Controls
  • Published policy, i.e., NASA Directives
  • Risk assessments on compliance with directives,
    standards, and other official NASA documents
  • Effective use of councils and teams to plan,
    perform, and monitor work
  • Regular assessments of physical security and
    information technology security compliance
  • Reviews of written delegations of authority for
    accuracy
  • Systematic reviews of physical asset inventories
  • Certification that products were received
    checked for possible defect or other problem
    before paying vendor
  • Reviews of Program Commitment Agreements to
    ensure that cost performance requirements are
    being met
  • Records of employee training
  • Tracking corrective/preventive actions
    assigning new/more actions as deemed prudent by
    management
  • ISO 90012000 based management system audits

5
6
Schedule for 2006 OMC Meetings Internal Controls
  • Feb. 14 1st Progress Meeting. Provide
    background on why internal control has become a
    high priority throughout government and the
    private sector. Assess actions taken to correct
    significant Agency deficiencies since Nov. 9
    Decision Meeting. Discuss any proposed new
    deficiencies to include on the councils watch
    list.
  • Apr. 12 2nd Progress Meeting to assess actions
    taken during the last quarter.
  • July 13 (tentative date) 3rd Progress Meeting
    of 2006
  • Oct. 5 (tentative date) Annual Decision Meeting
    for determining what deficiencies will be
    reported outside the Agency in the
    Administrators Statement of Assurance, which is
    required as part of the NASA Performance and
    Accountability Report, submitted to OMB, the
    Congress, and the President.

6
7
Actions from Nov. Internal Controls Meeting
  • The CFO, in collaboration with the Asst.
    Administrator for IA and the Asst. Administrator
    for Procurement, will develop a Corrective Action
    Plan (CAP) for the revised deficiency, Asset
    Management (MW). The detailed plan will be
    provided in the Corrective Action Tracking System
    (CATS) and a summary of the CAP will be presented
    by the next OMC meeting.
  • Status Open
  • The CFO, in collaboration with the CIO, Chief
    Engineer, IEMP Program Executive, Asst.
    Administrator for IA, and the Asst.
    Administrator for Human Capital, as appropriate,
    will develop CAPs for the four new deficiencies
    Financial Management System (MW), Financial
    Management Policy and Procedures (MC), Financial
    Management Data Integrity (MW), and Financial
    Management Staffing (MC). Detailed plans will be
    entered into the CATS and summaries of each CAP
    will be presented at the next OMC.
  • Status Open

7
8
Actions from Nov. Internal Controls Meeting
  • The Asst. Administrator for Procurement will
    coordinate with the OCFO and OIG to determine if
    acquisition oversight is a deficiency and, if so,
    to develop its scope (e.g., what aspects are
    included, who is responsible, etc). The Office
    of Procurement will present the results at the
    next OMC meeting.
  • Status Open (see next 3 charts)
  • The OCE will develop proposed changes to NPR
    7120.5 and bring to the PMC for approval by March
    31, 2006.
  • Status Open

8
9
Action Item from November 9th OMC Meeting
  • OMC Action 3 The Assistant Administrator for
    Procurement will coordinate with the OCFO and OIG
    to determine if acquisition oversight is a
    deficiency and, if so, to develop its scope (e.g.
    what aspects are included, who is responsible,
    etc). The Office of Procurement will present the
    results to the OMC.
  • Deadline Next OMC Internal Controls meeting.
  • Action Taken On Wednesday, January 11, 2006,
    representatives from the Office of General
    Counsel, the Office of the Chief Engineer, the
    Integrated Enterprise Management Program Office
    and the Office of Procurement met with the
    Inspector General to discuss the issue raised at
    the November OMC meeting. The issues discussed
    were similar to those that led to the inclusion
    of Contract Management on GAOs High-Risk list.
    It was agreed by all that the OCE would be the
    lead/POC/spokesperson for GAO on this activity,
    but that support would come from the most
    appropriate office. It was also agreed that
    since the OCE is going to be the lead for this
    activity, then Chris Scolese or his designee
    would report to the OMC quarterly.

9
10
OIGs Response to Procurement Integrity Issue
  • NASA does not have a Procurement Integrity
    Program. Responsibility for integrity in
    contracting is fragmented, with no clear lines of
    authority or responsibility for assuring
    integrity in NASA contracting.  We believe that
    NASA should have an internal control framework
    designed to assure integrity in Government
    contracts, to promote competition in contracting,
    to vigorously address wrongdoing by contractors
    through coordinated activities with the OIG and
    the NASA Office of General Counsel, the Office of
    Procurement, the centers and the program
    offices. 
  • We note that 10 USC 2307(i)(8) contemplates the
    establishment of remedy coordination officials
    within the Department of Defense and NASA and
    that NASA has not formally established such a
    position.  A remedy coordination official is a
    person or entity in that agency who coordinates
    within that agency the administration of
    criminal, civil, administrative, and contractual
    remedies resulting from investigations of fraud
    or corruption related to procurement
    activities.   10 USC 2307(i)(10)  We believe
    that the Agency should establish such a position,
    that it be in the Office of General Counsel, and
    that it be the same person as the Agency point of
    contact for addressing contract fraud and related
    matters.

10
11
OIGs Response to Procurement Integrity Issue
  • A contract integrity coordination program under
    10 U.S.C. 2307 is contemplated to contain the
    following elements to assure that all remedies
    are carefully considered by NASA when it has been
    victimized by fraud
  • Consideration of reduction or suspension of
    advance and progress payments as authorized under
    10 USC 2307(i), where appropriate
  • Consideration of termination of contracts and
    grants tainted by fraud in their performance or
    inducement
  • Consideration of proposed debarment and
    suspension under the FAR
  • Establishment of a full time Procurement
    Integrity unit to process suspension and
    debarment actions
  • Consideration of actions under the Program Fraud
    Civil Remedies Act (PFCRA), 31 U.S.C.
    3801-3812
  • Participation in the effectuation of  global
    settlements of criminal conduct, whereby
    contractual, administrative and civil remedies
    associated with a case are coordinated and
    resolved, when that is in NASAs interests
  • Consideration of disciplinary and other
    administrative actions against culpable
    individuals, including civil servants
  • We believe that a well-coordinated contract
    integrity program would result in a more
    structured and thoughtful consideration of
    remedies, identification of best practices and
    reform of regulations and internal controls,
    better education of NASA employees about
    potential fraud, and, in sum, better protection
    of NASA.

11
12
Asset Management(Material Weakness)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

13
Background
  • This deficiency was introduced in February 2003
    as a Material Weakness with planned actions to
    include monthly reporting by contractors
    publication of a Federal Management Regulation
    for Property, Plant, and Equipment and
    initiation of contractor and accountant training.
  • In October 2003, the deficiency was reduced to an
    Other Weakness when the OCFO completed the
    tasks of defining assets in space and issuing
    revised policy.
  • In October 2004, the deficiency was re-designated
    as a Material Weakness when the IG questioned the
    accuracy and reliability of property related
    accounting data.
  • During the 2005 Internal Control decision
    meeting, the Contractor-Held Property Material
    Weakness was renamed Asset Management, redefined
    to include Contractor-Held Property and NASA-Held
    Property, and designated as a Material Weakness.
  • Currently, the OCFO is sharing responsibility for
    this Material Weakness with the Programmatic
    Internal Control Team (PICT) and the
    Institutional Internal Control Team (IICT).
  • In January 2006, a Corrective Action Plan was
    developed for the FY 2005 Financial Audit, which
    defines the goal, objectives, strategies, and
    actions for improving NASAs internal controls
    over property, plant, and equipment.

2
14
Issue
  • NASA needs to improve its management controls for
    the financial reporting of property, plant and
    equipment, and materials including Theme Assets
    (formerly Assets-in-Space), contractor-held
    property, spare parts and assets under
    construction. Lack of proper management controls
    can result in inconsistent financial recording
    practices that can misstate asset values and
    period expenses.
  • Root cause
  • NASAs policies and procedures are not fully in
    conformance with federal requirements
  • There is inconsistent application of existing
    policies and procedures
  • Corrective action taken to date
  • Establishment of Financial Integration Team,
    subgroup on PPE composed of the Deputy Chief
    Financial Officer, Associate Administrator for
    Infrastructure and Administration, and Director
    of Procurement.
  • Presentation to and support received from the
    Senior Advisory Group on the overall plan to
    improve NASA's PPE internal controls and
    financial reporting.
  • Established PPE Compensating Controls Group
    comprised of HQs and Center representatives.
  • Prepared draft Theme Assets capitalization policy
    paper and submitted to OIG and external auditors
    for review and comment.
  • Defined Asset Categories and finalized how
    property will be classified (NASA Held and
    Contractor Held Program Related vs. Non-Program
    Related).
  • Defined appropriate accounting treatment per
    Asset category and use.

3
15
Recommendation
  • Recommend this issue remain as currently assigned
    (Material Weakness).

4
16
Planned Actions for Next Quarter
  • Provide OMB, GAO, FASAB, and OIG NASAs revised
    capitalization policy.
  • Adjust Capitalization policy as necessary.
  • Flowchart and document desired business processes
    and procedures, and define roles and
    responsibilities for effective PPE lifecycle
    management.
  • Identify and coordinate changes to existing
    policies Agency-wide.
  • The Institutional Internal Control Team (IICT),
    the Programmatic Internal Control Team (PICT),
    and the Financial Management Internal Control
    Team (FMICT) are addressing Asset Management as a
    priority area of focus.

5
17
Financial Management System(Material Weakness)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

18
Background
  • During the 2005 Internal Control decision
    meeting, the Management Operations Council
    granted the approval for the OCFO to close
    Material Weakness (MW-2004-02) Financial
    Management and open a new Material Weakness
    called Financial Management System that
    captures challenges related to
  • Confirming configuration
  • Validating the accounting
  • Validating construction of the financial reports
  • The recommendation was made to separately manage
    the OCFO deficiencies, ensure traceability to
    external audits, and show that progress has been
    made.
  • Currently, the OCFO is sharing responsibility for
    this Material Weakness with the Office of the
    Chief Information Officer and the Integrated
    Enterprise Management Program (IEMP) Office.
  • Developed the Corrective Action Plan for the FY
    2005 Financial Audit which addresses improving
    NASAs financial management system and processes
    to achieve accurate, reliable, timely financial
    information.

2
19
Issue
  • Since the completion of the rollout of the new
    system, challenges in system processing,
    configuration, and capabilities have surfaced and
    the current version of the SAP system has some
    capability limitations which have required the
    definition and implementation of compensating
    controls.
  • Root cause
  • Conversion from 10 disparate legacy financial
    systems supported by over 120 subsidiary systems,
    along with over a decade of historical data, to a
    single integrated financial management system
    highlighted long-standing data and process
    issues.
  • Corrective action taken to date
  • Submitted FY 2005 PAR to AGA for feedback on the
    construction, content, and applicability of the
    report, as part of the CEAR Award process.
  • Modified the statement of net cost to provide a
    breakdown of net costs consistent with strategic
    plan and in the Management Discussion and
    Analysis section by major line of business.
  • Established procedures to ensure that all system
    configuration changes are subject to regression
    tests and year-end test procedures which validate
    that changes made to the Core Financial System
    are valid, appropriate, and do not adversely
    impact end-to-end business processes, including
    external reporting.
  • Established safeguards to ensure that system does
    not pay cost in excess of obligations.
  • Formed cross-functional task team to review
    current funds control, cost collection, and
    accrual processes and identify opportunities for
    reengineering.
  • Conducted benchmarking sessions with Dept. of
    Education, Dept. of Agriculture, and others to
    identify best practices and lessons learned.
  • Drafted proposed process design and high level
    requirements.

3
20
Recommendation
  • Recommend this issue remain as currently assigned
    (Material Weakness).

4
21
Planned Actions for Next Quarter
  • Review results of CEAR review process.
  • Gather feedback on PAR from OMB and Mercatus.
  • Review latest revision of OMB Circular A-136 and
    incorporate required updates for FY 2006 PAR.
  • Review PARs from other Federal Agencies to
    identify potential areas of improvement for NASA.
  • Establish a cross-Agency task team to develop
    monthly schedule with due dates for data
    processing, reconciliations, verifications,
    feedback, and reports.
  • Develop compensating procedures to analyze
    Business Warehouse on a quarterly basis to ensure
    that liabilities are appropriately recorded.

5
22
Financial Management Data Integrity (Material
Weakness)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

23
Background
  • During the 2005 Internal Control decision
    meeting, the Management Operations Council
    granted the approval for the OCFO to close
    Material Weakness (MW-2004-02) Financial
    Management and open a new Material Weakness
    called Financial Management Data Integrity that
    captures challenges related to
  • Environmental Liabilities
  • Fund Balance with Treasury
  • Currently, the OCFO is sharing responsibility for
    this Material Weakness with the Offices of
    Infrastructure and Administration, Procurement,
    and the Integrated Enterprise Management Program
    (IEMP).
  • Developed the Corrective Action Plan for the FY
    2005 Financial Audit which addresses validating
    the tools and methodology used to prepare the
    unfunded environmental liability estimates and
    reconciling Fund Balance with Treasury and
    processing corrections in a timely manner.

2
24
Issue
  • NASA needs to continue to improve its current
    procedures to ensure that all reconciling items
    are thoroughly researched, timely resolved, and
    reviewed by appropriate Center and Headquarters
    OCFO personnel. NASA needs to improve existing
    environmental liability procedures and implement
    needed internal controls to assure the improved
    procedures are adhered to and followed.
  • Root cause
  • Relates to issues from data conversion system
    processing in the early stages of production
    operation.
  • Corrective action taken to date
  • Established Fund Balance with Treasury metrics.
  • Conduct ongoing monitoring to ensure monthly
    reconciliations are performed.
  • Conduct ongoing review and monitoring compliance
    with Fund Balance with Treasury policies,
    procedures, and practices.
  • Revised FMR policy for Monitoring Controls
    Procedures.
  • Implemented an automated tool to support FBWT
    reconciliations.

3
25
Recommendation
  • Recommend this issue remain as currently assigned
    (Material Weakness).

4
26
Planned Actions for Next Quarter
  • Host a joint OCFO and Environmental Management
    Division (EMD) training course to expedite the
    overall resolution of the action plan.
  • Develop and have available for auditor review,
    the Environmental Liability estimates based on
    2nd quarter data.
  • Jointly assess the effectiveness of UEL internal
    controls, cost estimation process and data
    gathering procedures.
  • Develop review/internal control checklist.
  • Perform a Central Resources Control System (CRCS)
    to SAP reconciliation and resolve differences.
  • Assess compliance with Fund Balance with Treasury
    policies, procedures, and practices.

5
27
Financial Management Policy and
Procedures(Material Weakness)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

28
Background
  • During the 2005 Internal Control decision
    meeting, the Management Operations Council
    granted the approval for the OCFO to close
    Material Weakness (MW-2004-02) Financial
    Management and open a new Management Challenge
    called Financial Management Policies and
    Procedures that captures challenges related to
  • Completion of the Financial Management
    Requirements (FMR)
  • Reengineering targeted business processes
  • Developed the Corrective Action Plan for the FY
    2005 Financial Audit which addresses developing
    core standard Agency-wide procedures and tools
    consistent with authoritative guidance issued by
    FASAB, Treasury, and OMB .

2
2
29
Issue
  • NASA needs to continue to improve its current
    policy to ensure improvement existing procedures
    and implement needed internal controls to assure
    the improved procedures are adhered to and
    followed.
  • Root cause
  • NASAs policies and procedures are not fully in
    conformance with federal requirements
  • Implementation of the Integrated Enterprise
    Management Program required revision of policies
    and procedures
  • Corrective action taken to date
  • Provided OMB, GAO, FASAB, and OIG NASAs revised
    NASA Asset Management capitalization policy.
  • Recently published five FMRs
  • Travel (4/29/05)
  • Internal Controls (04/29/05)
  • Special Accounts and Funds (04/29/05)
  • Cash Management (09/30/05)
  • Payroll (12/30/05)

3
30
Recommendation
  • Recommend this issue remain as currently assigned
    (Management Challenge).

4
31
Planned Actions for Next Quarter
  • Adjust the Asset Management capitalization policy
    as necessary.
  • Flowchart and document desired business processes
    and procedures, and define roles and
    responsibilities for effective PPE lifecycle
    management, to include valuation of Assets.
  • Incorporate OIG comments in the flow charts as
    appropriate and disposition.
  • Identify and coordinate changes that must be made
    to existing policies Agency-wide.
  • Engage working groups to identify process and
    system(s) gaps between current processes and
    desired processes, as well as, identifying
    solutions.
  • Publish four remaining FMRs
  • Budget Formulation (05/01/06)
  • Reimbursables (04/28/06)
  • Information Systems (06/30/06)
  • Overview (05/26/06)

5
32
Financial Management Staffing (Management
Challenge)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

33
Background
  • During the 2005 Internal Control decision
    meeting, the Management Operations Council
    granted the approval for the OCFO to close
    Material Weakness (MW-2004-02) Financial
    Management and open a new Material Weakness
    called Financial Management Staffing that
    captures challenges related to
  • Staffing Levels
  • Personnel Skill Mix
  • Workforce Development
  • Currently, the OCFO is sharing responsibility for
    this Management Challenge with the Office of
    Institutions and Management/Human Capital
    Management.
  • Developed the Corrective Action Plan for the FY
    2005 Financial Audit which addresses workforce
    development.

2
34
Issue
  • NASA needs to ensure adequate staffing for
    financial management functions across
    Headquarters and the Centers and to continually
    provide additional handson training for
    financial personnel to ensure that they
    understand their roles in financial reporting.
  • Root cause
  • With the implementation of the Integrated
    Enterprise Management Program (IEMP), additional
    training was required due to new processes.
  • The implementation of the IEMP Core Financial
    system represented a major transformation of
    NASA's financial management systems and
    processes.
  • Corrective action taken to date
  • Issued quarterly report documenting all training
    conducted during the 1st quarter of FY 2006.
  • Increased staffing to support financial
    management activities.
  • In May 2005, NASAs OCFO received relief from a
    NASA-wide hiring freeze and approval to increase
    its headcount in FY 2006 at Headquarters by 34
    positions (including 2 Senior Executive Service
    leadership positions) and at Field Centers by 50
    positions.
  • As of February 1, 2006, 90 of these positions
    have been filled.

3
35
Recommendation
  • Recommend this issue remain as currently assigned
    (Management Challenge).

4
36
Planned Actions for Next Quarter
  • Utilize a needs assessment and develop a training
    plan for providing the following training
  • Processing transactions
  • Performing account analyses and reconciliations
  • Maintenance of supporting documentation
  • Financial reporting requirements
  • Hire from anticipated job announcements.

5
37
Full Cost Integration (Other Weakness)
  • Office of the Chief Financial Officer
  • Terry Bowie
  • February 14, 2006

38
Background
  • In Feb 2003, the Associate Administrator for
    Earth Science recommended that full cost
    accounting be monitored as a Management
    Challenge (MC).
  • In Feb 2005 the OCFO recommended closing the
    Full Cost Accounting MC based on FC Steering
    Committee actions. It was replaced with a new MC,
    Full Cost Integration.
  • In May 2005, Full Cost Integration was elevated
    from an MC to an Other Weakness (OW), due to
    lack of understanding of full cost policies and
    procedures.
  • In Dec 2005, a new Full Cost Reform Initiative
    Team was established to recommend changes to
    simply full cost policies and procedures,
    including developing an implementation plan for
    the recent PAE Full Cost Simplification
    Proposal.

2
39
Issue
  • Full Cost concepts need to be better integrated
    into NASA operations. Despite implementing a Full
    Cost accounting system and many Full Cost
    processes, NASA still lacks the level of cultural
    change needed to fully transition to Full Cost
    management.
  • Root cause
  • Insufficient stakeholder training
  • Unintended consequences and behaviors realized
    from initial full cost approaches
  • Some policies and planned processes were based on
    insufficient experience and need to be refined to
    reflect lessons learned
  • Corrective action taken to date
  • Completed Full Cost Assessment delivered
    recommendations to Financial Integration Team on
    improving full cost implementation.
  • Improve policy to resolve operational issues.
  • Full Cost Reform Team meeting held from Jan 31st
    through Feb 1st to recommend steps to implement
    revised full cost policies and procedures,
    including PAE Full Cost Simplification Proposal.

3
40
Recommendation
  • Recommend this issue remain as currently assigned
    (Other Weakness).

4
41
Planned Actions for Next Quarter
  • Implement recommendations from Full Cost team for
    FY 2008 POP Budget cycle and FY 2007 execution to
    the extent practical. The initial steps include
  • Combine IT and Facility service pools with Center
    GA into a single Center Management and
    Operations account per Center
  • Eliminate budget and cost allocations between
    overhead pools
  • Eliminate allocations of Center overhead to
    Corporate tasks
  • Create control accounts for Center MO budgeted
    and funded like direct projects allocated to
    projects in final steps of budgeting and
    reporting
  • Allocate overhead costs on a projects pro-rata
    share of each Centers direct budget (NOA)

5
42
Space Shuttle
  • Space Operations Mission Directorate
  • Lynn F. H. Cline
  • February 14, 2006

43
Background
  • Following the loss of Columbia and her crew, the
    Deputy Associate Administrator for International
    Space Station and Space Shuttle Programs
    established a formal "Return-to-Flight Planning
    Team," to provide direction to the team for
    addressing actions required before a safe return
    to flight could be assured, as well as other
    actions determined necessary to comply with the
    formal recommendations of the CAIB. Options and
    recommendations from the Return-to-Flight
    Planning Team were assessed by the Space Flight
    Leadership Council, co-chaired by the Associate
    Administrator for Space Operations and the Deputy
    Chief Engineer for Independent Technical
    Authority. Return-to-Flight actions were
    implemented through normal Space Shuttle Program
    management. The Council was abolished on June 28,
    2005, and all actions are now conducted through
    Space Shuttle Program management.
  • Progress on implementation of Return to Flight
    actions is documented in periodic updates to the
    NASA "Implementation Plan for Space Shuttle
    Return to Flight and Beyond."

2
44
Issue
  • Technical Deficiencies
  • Modeling was not as accurate when the Shuttle
    system was originally certified in the late
    1970s Debris Transport Analysis was more art
    than science (point to point transport) and the
    analyses that was done was rarely supported with
    rigorous testing (e.g., wind tunnel testing,
    impact testing).
  • All pre-STS-107 flight history seemed to support
    the initial certification analyses.
  • Foam damage to the Orbiter failed to show
    positive correlation between liberated debris
    mass and TPS (tile) damage.
  • Post-STS-107 modeling told us where debris might
    strike the Orbiter, however, it was impact
    testing that defined critical debris (mass)
    thresholds for return to flight. This testing
    showed us how fragile the Orbiter was to
    different materials and masses. At that point,
    we knew we would have to eliminate all the
    critical debris sources, provide much improved
    debris impact monitoring, and determine to what
    extent we needed to harden the Orbiter before we
    could Return to Flight.
  • While STS-114 proved we had done a very credible
    job of eliminating critical debris, five In
    Flight Anomaly foam loss events made it clear
    additional work is required before the second RTF
    mission to increase our understanding of the
    cause of these foam debris events and taking the
    appropriate corrective actions. This work is
    currently on-going.
  • Other Deficiencies
  • The Final Report of the Columbia Accident
    Investigation Board (CAIB) identified a number of
    systemic cultural, organizational, and managerial
    issues within both the Space Shuttle Program and
    NASA as a whole that contributed to the loss of
    Columbia on February 1, 2003.

3
45
Issue
  • Root cause
  • The physical cause of the loss of Columbia and
    her crew was a breach in the Thermal Protection
    System on the leading edge of the wing, caused by
    a piece of insulating foam which separated from
    the left bipod ramp section of the External Tank
    at 81.7 seconds after launch, and struck the wing
    in the vicinity of the lower half of Reinforced
    Carbon-Carbon panel number 8.
  • The Final Report of the Columbia Accident
    Investigation Board (CAIB) identified a number of
    systemic cultural, organizational, and managerial
    issues within both the Space Shuttle Program and
    NASA as a whole that contributed to the loss of
    Columbia on February 1, 2003.
  • Fifteen Return-to-Flight and fourteen continuing
    to fly recommendations are in the CAIB Report.
    Four dealt explicitly with management issues, and
    many of the other recommendations have important
    organizational as well as technical implications.
  • The CAIB Report also calls on NASA to prepare a
    detailed plan for defining, establishing,
    transitioning, and implementing these
    recommendations prior to Return to Flight, with
    the understanding that the implementation of the
    fundamental management changes will continue
    beyond the first Shuttle flight after Columbia.

4
46
Issue
  • Corrective action taken to date
  • In response to the CAIB report, NASA developed
    the Implementation Plan for Space Shuttle Return
    to Flight and Beyond. The Implementation Plan is
    an evolving blueprint for safely and reliably
    returning to flight. It explains how NASA is
    complying with the recommendations of the CAIB
    and other corrective actions. These additional
    corrective actions may include other CAIB
    observations, self-imposed Shuttle program
    initiatives or input from other sources. Edition
    11 of the Implementation Plan is scheduled for
    release on February 17, 2006.
  • On August 17, 2005, the Return to Flight Task
    Group released its Final Report. In it, the Task
    Group unanimously closed all but three of the
    Board's Return-to-Flight recommendations. The
    Task group noted NASA had made substantial
    progress relative to these recommendations, and
    emphasized that, "The ability to fully comply
    with all of the Board's recommendations does
    not imply that the Space Shuttle is unsafe." The
    first three Return-to-Flight missions (STS-114,
    STS-121, and STS-115) will provide the data and
    flight experience needed to address the remaining
    open issues in these recommendations. This work
    will be documented in future updates to the
    Implementation Plan.
  • Post-flight analysis of STS-114 indicated that,
    except for one event, the thermal protection
    system on the External Tank performed within
    expected parameters. Most of the small foam
    shedding events that were observed with the newly
    upgraded imagery and sensor capabilities posed
    little or no threat to the Orbiter. The one
    event of concern was the loss of an approximately
    one pound piece of foam from the area of the
    External Tank's liquid hydrogen protuberance air
    load (PAL) ramp. NASA commissioned two teams
    (one led by the Space Shuttle propulsion manager,
    the other an independent "Tiger Team" reporting
    directly to the Associate Administrator for Space
    Operations) to analyze these foam loss events and
    recommend any forward work that would have to be
    done prior to the launch of the next mission,
    STS-121. The final report is expected to be
    released in March 2006.

5
47
Issue
  • Corrective action taken to date
  • After a thorough engineering review, it was
    determined to proceed with removal of the
    External Tanks PAL ramp to eliminate this source
    of debris. While all testing and analysis to
    support this action is not yet complete, there is
    a high degree of certainty based on the extensive
    work done to date that removing the PAL ramp has
    no operational or safety impacts to flight. All
    testing and validation associated with the PAL
    ramp removal will be completed prior to the
    launch of STS-121.
  • NASA will make the decision to proceed with the
    launch of STS-121 based on the totality of
    improvements made to the Space Shuttle system
    during Return to Flight, and the vetting of these
    improvements through a rigorous and multilayered
    engineering review process, which includes the
    successful completion of the External Tank
    Systems Design Certification Review, the Systems
    Debris Verification Review, as well as other
    Program reviews, culminating in the approved
    Certificate of Flight Readiness.

6
48
Recommendation
  • Until successful completion of STS-121, this item
    should remain a material weakness.
  • Target Completion Date June 30, 2006

7
49
Planned Actions for Next Quarter
  • The STS-121 launch window is May 3 22, 2006. A
    decision on the target launch date is still
    pending. The STS-300 Launch On Need (LON) date
    is currently expected to be No Earlier Than (NET)
    August 1, 2006, based on an External Tank
    delivery to KSC in early June 2006. The STS-115
    launch window is August 29 to September 14, 2006.
  • The Space Shuttle Program has identified the gap
    filler replacement work required for all three
    Orbiters prior to their next flights. Discovery
    (OV-103) has currently completed approximately
    3100 of 3800 gap filler installations (82)
    mandatory for STS-121, and is on schedule for
    supporting the May 2006 launch window. Atlantis
    (OV-104) gap filler work is approximately 10
    complete, and remains on schedule for supporting
    either a STS-300 LON or STS-115 mission.
  • The production of the External Tank (ET-119) at
    Michoud Assembly Facility (MAF) continues to
    progress as planned for supporting a STS-121
    launch in the May 2006 launch window. Shipment
    of ET-119 to KSC is targeted for March 3, 2006.
    The production of ET-118 to support a
    STS-300/STS-115 launch also proceeds on schedule,
    to be ready for a shipment to KSC on May 30, 2006.

8
50
Shuttle Impact on ISS Operations
  • Space Operations Mission Directorate
  • Lynn F. H. Cline
  • February 14, 2006

51
Background
  • Following the Shuttle Columbia accident, February
    2003, the ISS Partnership agreed to an interim
    operational plan that would allow continued
    crewed operation. The plan called for a
    reduction of the crew size to two, with the crew
    exchanges to be conducted on the scheduled
    semi-annual Soyuz flights. Cargo re-supply would
    be provided by Russian Progress vehicles. This
    is an interim measure until the Space Shuttle
    returns to flight.
  • The first of two Shuttle Return to Flight
    missions has been completed, STS-114, launched on
    July 26, 2005 and landed on August 9, 2005.

2
52
Issue
  • Description of deficiency
  • The International Space Station (ISS) was
    designed with the Space Shuttle as its prime
    support for crew transport, assembly of on-orbit
    elements, utilization and operations. Additional
    crew and cargo transport is provided by Russia.
    Following the Space Shuttle Columbia accident,
    the Shuttle fleet was grounded. This has impacted
    the number of crew that can be supported onboard
    the ISS, temporarily halted assembly of the
    Station, and significantly reduced the available
    up and down mass support for Station operations
    and utilization.
  • Root cause
  • The grounding of the STS fleet resulted in this
    impact on ISS operations.

3
53
Issue
  • Corrective action taken to date
  • Established an understanding with the ISS
    partnership to (1) rely on Russian vehicles for
    crew and cargo support until Shuttle returns to
    flight and (2) reduced the crew size from 3 to 2
    to reduce the logistics burden, given the reduced
    capability of the Russian vehicles compared to
    the Space Shuttle.
  • Until STS-115, ISS crew transfer and resupply
    will rely on Russian Soyuz and Progress
    spacecraft.
  • Since 2003, there have been 6 crew exchanges
    using Soyuz and 10 crew exchanges using Progress
    for resupply flights.
  • Successfully completed the ISS objectives for the
    STS-114 mission
  • Flew the combined Space Shuttle/ISS stack in a
    new configuration designed to minimize the threat
    of orbital debris and micrometeorite impact
    damage.
  • Transferred more than 15,000 pounds worth of
    supplies and hardware to the ISS, including food,
    water, nitrogen, lithium hydroxide canisters, and
    scientific equipment.
  • Returned more than 7,200 pounds worth of expended
    hardware and unneeded supplies from the ISS back
    to Earth. Returning this hardware allows for
    failure analysis and possible reuse of Russian
    Elektron (oxygen generation) and Kurs (for
    docking of Russian Soyuz and Progress vehicles)
    hardware, as well as U.S. components like a
    Control Moment Gyroscope (CMG), Global
    Positioning System sensor, and spacesuit.

4
54
Issue
  • Repaired and/or replaced two of the ISSs four
    CMGs (which provide attitude control for ISS),
    restoring the Station to its full capability.
  • Installed the External Stowage Platform-2, an
    external platform for storing components and
    assisting astronauts in conducting EVAs from the
    ISS, transferred the Human Research Facility-2
    rack to the U.S. Destiny module on the ISS
    (increasing the scientific capabilities of the
    Station), and deployed and retrieved the
    Materials International Space Station Experiment
    Passive Experiment Containers from the outside of
    the ISS.
  • Reboosted the orbit of the ISS and conducted a
    fly-around and completed photographic survey of
    the ISS prior to reentry.
  • Current Status
  • As of February 2, 2006, the ISS has 182 days of
    food, 281 days of water (with a functional
    Elektron), and 215 day days of Oxygen (without
    Elektron). Nitrogen and Propellant are not an
    issue at their current levels.
  • Since arriving at ISS in October 2005, the
    Expedition 12 crew has successfully completed two
    EVAs and performed maintenance and utilization
    activities.
  • ISS assembly will resume with STS-115.

5
55
Recommendation
  • Until successful completion of STS-121, this item
    should remain a management challenge.
  • Target Correction Date June 30, 2006

6
56
Planned Actions for Next Quarter
  • ISS Crew Exchange
  • Soyuz TMA-8/12S launch with Expedition 13 (with
    Marcos Pontes of Brazil) on March 30, 2006
  • Soyuz TMA-7/11S undocking and reentry with
    Expedition 12 (with Marcos Pontes of Brazil) on
    April 9, 2006
  • STS-121 launch is currently scheduled for NET May
    2006, and STS-115 is scheduled NET July 2006.
    ISS assembly will resume with STS-115.

7
57
Information Technology Security
  • Office of the Chief Information Officer
  • Scott Santiago
  • February 14, 2006

58
IT Security Objectives
  • NASA information management meets or exceeds
    Federal and NASA policy and requirements.
  • All access to NASA information and information
    systems follows consistent, well defined and
    understood paths.
  • Utilize trusted electronic identities to control
    access to all NASA information and information
    systems.
  • NASA can verify that its internal controls and
    safeguards are working as intended.

2
59
Background
  • The NASA OIG through their audits of NASAs IT
    Security Program had identified a large number of
    deficiencies over the years that led them to
    recommend IT Security to be declared a Material
    Weakness.
  • NASA has been working since FY 2003 to correct
    those deficiencies found as a result of those
    audits and to correct systemic problems with the
    ITS Program.

3
60
Issue
  • Root Cause
  • NASA IT Security, while improving, needs more
    effective implementation, monitoring, and
    enforcement. In addition, NASAs policy and
    procedures have not kept up with OMB direction
  • OMB Continues to focus attention on IT Security
    which requires NASA to make significant changes
    in how IT Security is managed.

4
61
Issue
  • Corrective action taken to date
  • Rewrote NASA IT Security policy and requirements
    documents to reflect NIST Guidance as directed by
    OMB, pending approval. Waiting on final approval.
  • Establishing a central database of all NASA
    systems and IT Security plans status and added a
    module to CATS for tracking all IT Security
    weaknesses according to FISMA.
  • Established a certification and accreditation
    (CA) program as Directed by OMB NIST SP 800-37
    Guide for the Security Certification and
    Accreditation of Federal Information Systems
  • Expanded the NASA ITS training Program

5
62
Issue
  • Corrective action taken to date
  • Improved Incident reporting and tracking
  • Establishing centrally managed monitoring of the
    NASA network
  • Establishing centrally managed security services
    to correct known security weaknesses in managing
    sensitive information and to meet HSPD-12
    requirements.
  • Established Agency metrics (ITS Scorecard) based
    on external and internal ITS performance
    requirements.

6
63
Recommendation
  • Continue to categorize NASAs IT Security Program
    as an Other Weakness (OW) until new policy is
    approved and changes are implemented and they
    begin to demonstrate the required results.

7
64
Declassification Review ProcessManagement
Challenge (MC)
  • Office of Security and Program Protection
  • Clint Herbert, Deputy Assistant Administrator
  • February 14, 2006

65
Background
  • NASA had a significant backlog of permanent
    records containing classified national security
    information (CNSI) that needed to be reviewed for
    continued classification pursuant to EO 12958
    amended.
  • NASA faces a December 2006 deadline to insure
    that all permanent records containing CNSI that
    are 25-years old or older are subjected to
    classification review.
  • Poor records management practices prevented the
    identification of records subject to Section 3.3
    of EO 12958 amended, resulting in NASAs
    inability to identify its total universe to be
    considered for declassification
  • The identified root causes had significantly
    impeded the classification review programs
    efforts.
  • EO 12958 as amended contains a sliding-window
    requirement for NASA to conduct yearly
    classification reviews of permanent records
    containing CNSI.

2
66
Issue
  • Deficiency Description
  • NASA has a significant backlog of permanent
    records containing classified national security
    information (CNSI) that must be reviewed for
    continued classification pursuant to EO 12958
    amended. NASA faces a December 2006 deadline to
    insure that all permanent records containing CNSI
    that are 25-years old or older are subjected to
    classification review. Poor records management
    practices prevents the identification of records
    subject to Section 3.3 of EO 12958 amended
    resulting in NASAs inability to identify its
    total universe to be considered for
    declassification. The identified root causes have
    significantly impeded the classification review
    programs efforts. EO 12958 as amended contains
    a sliding-window requirement for NASA to conduct
    yearly classification reviews of permanent
    records containing CNSI.
  • Root Causes
  • Insufficient staffing
  • Historically poor records management
  • Insufficient funding
  • Lack of Declassification Guides
  • Insufficient resident expertise to perform
    classification reviews for older programs
  • Insufficient support from senior management
    (commitment of resources)
  • Corrective Action Plan (CAP)
  • A comprehensive CAP has been developed and has
    been distributed to the OC, all Mission
    Directorates, and Center Security Offices on
    11/205

3
67
Recommendation
  • Closeout. NASA has made significant progress in
    declassification efforts and is now positioned to
    meet the December 31, 2006 deadline. Only
    approximately 1.5 million pages, from an original
    17 million pages, remain under this initial
    deadline.

4
68
Planned Actions for Next Quarter
  • Continue declassification efforts
  • Maintain monthly accountability

5
69
Government Accountability Office Open Audit
Recommendations
  • Office of Infrastructure and Administration
  • Chris Jedrey
  • February 14, 2006

70
Background
  • History or information leading up to this issue
    being designated as a deficiency
  • August 2005 As a result of an increase in GAO
    audit activity highly visible and politically
    sensitive GAO audits (e.g., Mission Management
    Aircraft) and continued congressional interest
    in the health of NASA's financial management, the
    Operations Council agreed to add the status of
    GAO audit recommendations as a Management
    Challenge (MC)

2
71
Issue
  • Description of deficiency
  • GAO audit recommendations remain unimplemented.
  • Of the 58 outstanding GAO audit recommendations
    issued to NASA, 42 (72) were issued more than 1
    year ago.
  • OMB Circular A-50 encourages implementation
    within 1 year of issuance of the recommendation.

3
72
Issue
  • Root cause (1)
  • August 2005 GAO issues audit report on Mission
    Management Aircraft (GAO-05-818) which highlights
    significant control deficiencies with respect to
    the management of NASA's MMA.
  • GAO assessed (1) the relative cost of NASA
    passenger aircraft services in comparison with
    commercial costs, (2) whether NASA aircraft
    services were retained and operated in accordance
    with government-wide guidance, and (3) the
    effectiveness of NASA's oversight and management
    of this program.

4
73
Issue
  • Root cause (2)
  • GAO has issued several audit reports focusing on
    inadequate controls over financial management
    specially relating to the agency's implementation
    of an Integrated Enterprise Management Program.
    These reports focus on fundamental problems with
    NASA's financial operations that undermine the
    agency's external financial reporting ability and
    impair efforts to effectively manage and oversee
    major programs.
  • GAO's recommendations relating to these IEMP
    audit reports and NASA's inability to timely and
    effective implement GAO's recommendation were
    addressed during the confirmation hearing of the
    NASA's nominee for Deputy Administrator on
    November 1, 2005.

5
74
Issue
  • Root cause (3)
  • Since 1990, GAO has identified NASA's contract
    management function as an area at high risk,
    principally because the agency lacks accurate and
    reliable financial and management information on
    contract spending, and it has not placed enough
    emphasis on end results, product performance, and
    cost control.
  • Since financial and contract problems threaten
    the success of NASA's major programs, GAO
    believes that contract management continues to be
    an area of high risk. To further improve contract
    management, GAO recommends that NASA successfully
    complete its design and implementation of a new
    financial management system (IEMP). GAO
    recommends that NASA transform its operations to
    better support its core mission.

6
75
7
76
Recommendation
  • Continue to monitor as a Management Challenge (MC)

8
77
Planned Actions for Next Quarter
  • Management continues to work toward the timely
    implementation of GAO audit recommendations.

9
78
Mission Management Aircraft
  • Infrastructure and Administration
  • Chris Jedrey
  • February 14, 2006

79
Background
  • GAO audit of Agencys FY03 and FY04 Mission
    Management Aircraft (MMA) operations highlighted
    control deficiencies with respect to management
    of NASAs MMA.
  • MMA operations were also questioned in several
    prior GAO and NASA IG audit reports.

2
80
Issue
  • Inadequate documentation and periodic review of
    MMA mission requirements - Resolved
  • Issued NPR 7900 Interim Change to comply with OMB
    A126
  • PAE review complete, mission requirements
    identified Implementing approved recommendations
  • Insufficient HQ oversight - Resolved
  • Augmented HQ AMD staff for MMA
  • Instituted annual HQ review of Center MMA
    operations
  • Lack of integrated IT system to capture and
    report aircraft cost utilization
  • NASA Aircraft Information System (NAMIS) being
    implemented for MMA utilization data. To be in
    place Spring 2006 (6 months early).
  • Core Financial BW unable to provide accurate
    aircraft cost allocation and reporting to comply
    with OMB A126. Assisting OCFO Aircraft Cost
    Accounting PAT.

3
81
Recommendation
  • The aircraft utilization and cost accounting
    issues should continue to be carried and reported
    as Other Weakness.

4
82
Planned Actions for Next Quarter
  • Implement NAMIS at all centers that operate MMA
    by June 2006 to provide visibility into
    utilization and comply with OMB A126.
  • Continue to support OCFO with aircraft cost
    accounting process action team

5
Write a Comment
User Comments (0)
About PowerShow.com