Monthly 7_25 Page 1 - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Monthly 7_25 Page 1

Description:

Over the last period we continued with flight fabrication and prototype testing. ... with the higher than expected required voltage for the MCP bias, we only have ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 19
Provided by: johnsc4
Category:
Tags: monthly | page | period | spare | time

less

Transcript and Presenter's Notes

Title: Monthly 7_25 Page 1


1
Monthly Status Report Report due 7/25/00 Schedule
statused as of July 7, 2000
2
Project Status Summary
  • Technical
  • May Jun Jul

Programmatic May Jun Jul
Resources May Jun Jul
Schedule May Jun Jul
Detailed Description (for items identified as
yellow or red)
  • Over the last period we continued with flight
    fabrication and prototype testing. We continue
    to see no major show stoppers. Some of our
    biggest concerns continue to to be with outside
    purchases/subcontracts. We have already
    implemented some workarounds to maintain the
    schedule (with contingency). The current
    schedule does reflect all of the most recent
    delivery dates from outside vendors (as of
    7/24/00) and an update to the schedule to regain
    schedule slack.
  • Latest project photos are available on Aspera-3
    web site.

3
Problem and Concern Summary
PProblem CConcern RResolved
4
Accomplishments of the Last Month -ELS
  • Ran High Voltage breakdown test. Test was very
    straightforward with no problems.
  • Connected ELS end-to-end through GSE and tried to
    see electron beam. Successfully saw beam in all
    16 sectors. One sector seemed very noisy, one
    sector seemed very weak.
  • Examined pulse height distribution curves for
    flight MCP set. Threshold of ELS was set way to
    low. Pulled ELS out of the chamber and changed
    resistors to raise the threshold. Also cleaned
    up the wiring for the grounding of the ELS
    electronics.
  • Realized that with the higher than expected
    required voltage for the MCP bias, we only have
    about 150 volts headroom on the power supply
    for operations(current max voltage is 2800 v).
    We decided for flight build to increase max
    voltage to 3000 v. Flight and flight spare HVPS
    are now being fabricated for max voltage of 3000
    v.
  • Received 2nd of 5 flight MCP sets. Next
    possible set is at least a week away.

5
Accomplishments of the Last Month ELS (cont.)
  • Continued characterization testing. Spent lots
    of time chasing noise in the GSE and set up.
    This included reducing length of cables, adding
    shields, adjusting GSE s/w, characterizing the
    pulse shape at various locations in the test
    set-up, etc. When ELS is in the chamber without
    the housing, the background rate is approaching
    that of just the MCP after burn-in (cant do any
    better than that).
  • New Concern When the Housing and Grid are
    installed, the background count rate goes up
    considerably. We are currently trouble shooting.
  • Talked to Hyperfine They increased their
    estimated late delivery because their
    subcontractor who does rough machining is late.
    As of 7/14/00, it looked like Hyperfine would be
    8 weeks late on delivery of ELS mechanical parts.
    We have now pulled back rough machining and and
    are currently cutting metal on the flight and
    flight spare housing. High tolerance finish
    machining will still be done by Hyperfine. We
    have updated the schedule to reflect our current
    estimate for machining at SwRI, Hyperfine
    machining, and update on UV coating time needed.

6
Accomplishments of the Last Month - IMA
  • Completed fabrication of the Pogo alignment jig.
  • Disassembled IMA to examine problem of cracked
    MCP. It was determined that the failure was
    caused by a bending mode rather than crushing or
    a sharp bur. Have come up with a couple of
    possible reasons for failure. We are looking at
    modification of the design to correct the
    problem.
  • The threshold of IMA also needs to be tailored to
    the MCP. It is likely that we are currently set
    to sensitive
  • Started fabrication of FM and FS IMA anode
    boards. Stopped to work on ELS HVPS boards.
  • Began fabrication of test MCP that strain
    gauges will be mounted to for MCP holder
    evaluation.
  • We are focusing on ELS rather than IMA as it is
    critical path.

7
Accomplishments of the Last Month - Data
Reduction Software
  • Updated ASPERA-3.org Web Site Documentation
  • Continued Updates to the ASPERA-3 Data System
    Interface Document
  • Continued Formally Documenting APAF Software
    Requirements
  • Continued Providing Technical Assistance for EPO
    Web Information
  • Continued Defining and Implementing IDFS Web
    Tools
  • Provided Software Support for ELS
    Characterization
  • Held monthly ASPERA-3 Software Status Meeting
    (July 24, 2000)
  • Article Published in July 2000 Issue of NASA Tech
    Briefs, "A Standard for Scientific Data Files",
    that Briefly Describes the IDFS Paradigm

8
Planned Activities for the Next Month - ELS
  • (Hopefully) receive flight sets 3 and 4 of the
    MCPs
  • Finish rough machining of ELS parts and receive
    high tolerance parts back from Hyperfine.
  • Finish characterization testing of the ELS
    prototype.
  • Begin environmental testing of the ELS prototype.
  • Finish fabrication of the flight and flight spare
    HVPS and Amp boards.
  • Finalize test procedures.

9
Planned Activities for the Next Month - IMA
  • Finalize investigation of the MCP holder and make
    necessary modifications to prototype and flight /
    flight spare units.
  • Finish fabrication of the Amp board and Digital
    Board.
  • Fix pogo alignment in prototype.
  • Change out FPGA on prototype.
  • Finalize test procedures.
  • Restart vacuum testing prototype, following ELS
    prototype testing to verify FPGA change.

10
Planned Activities for the Next Month - Data
Reduction Software Tasks
  • Deliver APAF Data System Interface Document (Due
    Aug. 18)
  • Continue Formally Documenting APAF Software
    Requirements
  • Continue Providing Technical Assistance for EPO
    Web Information
  • Continue Defining and Implementing IDFS Web Tools
  • Continue Providing Software Support for ELS
    Characterization as Needed
  • Provide Software Support for Upcoming ASPERA-3
    Team Meeting as Required

11
Problem and Concern Status
  • Delivery of MCPs from Burle
  • This is still a major concern. We have received
    2 sets of mechanical samples, 1 set of flight
    reject plates, and 2 sets of plates that meet
    flight specs. The next potential delivery of
    flight plates will be in two weeks. Our schedule
    is still not effected by the delivery slippage.
    We have been in close contact with the Burle test
    engineer and he has been very forthcoming about
    status and providing us information.

12
Problem and Concern Status (cont.)
  • Alignment of ELS
  • We found out that Hyperfine was projecting a
    delivery that was 8 weeks late largely due to
    their supplier being late. We have pulled the
    rough machining back in house and have
    prioritized the order of machining. Our goal is
    to have all parts needing UV coating (ie housings
    and inner deflection plates) completed by
    Hyperfine by mid-August.

13
Problem and Concern Status (cont.)
  • Alignment of Pogos in IMA
  • We have completed modification of the fixture
    that holds the pogos in place during their
    assembly and soldering process. We have also
    modified the assembly and test procedures to
    include resistance-to-ground measurements that
    will verify the electrical connection after
    assembly, and prior to and after each
    environmental test. We will keep this issue a
    concern until the prototype is corrected and the
    assembly procedure is verified. We feel that
    this is only a small concern because after our
    problem, we consulted with some non-ASPERA
    personnel who have more experience using pogos.
    We have since incorporated their proven expertise
    into our assembly process.

14
Problem and Concern Status (cont.)
  • MCP mount IMA
  • We are still in the process of determining the
    cause of the cracks in the IMA MCP. We have
    fabricated a test MCP out of thin aluminum that
    will be instrumented with strain gauges. We will
    reassemble the prototype with the psuedo MCP and
    measure the stress /strain during assembly. We
    will then make mods to the prototype mechanical
    pieces and verify stress / strain is reduced. We
    may also use this technique to verify flight
    parts.

15
Problem and Concern Status (cont.)
  • High background rate in ELS
  • After a lot of effort debugging GSE, shortening
    cables, modifying ELS GSE software, we have
    gotten the background noise of the ELS sensor
    (without the housing and grid) to a background
    level comparable with the count rate for the MCP
    by itself. Early testing, however in the housing
    with the grid, showed very high count rates. We
    are in the process of investigating this problem.
    The first step is to see if the problem still
    exists since we have debugged the GSE, test
    set-up etc.

16
Schedule Summary
  • ELS The July 7th version of the schedule
    continues to show that the flight HVPS is the
    critical path for ELS (0 days of float). We
    simply started the fabrication of the HVPS later
    than we should have.
  • The mechanical path is the second most critical
    caused by Hyperfine being late. ( 5 days of
    float)
  • We adjusted the schedule over the last month
    incorporating many workarounds (ie. more
    realistic durations for some tasks, weekend, and
    shift work etc.)
  • Note the schedule still has 21 days slack at the
    end (DEL0050) in addition to float shown for each
    task.
  • MCP delivery is still not effecting the schedule.

17
Schedule Summary (cont.)
  • IMA The IMA schedule still shows 5 days float,
    this is of course dependent on the MCP mount
    investigation. We feel that worst case however,
    we will only need to modify or remanufacture a
    small number of mechanical parts. This will
    occur in parallel with the stuffing and bench
    check out of the amp and digital PC boards thus
    not effecting the schedule.
  • Software activities continue to be on schedule.
  • The full-up schedule is available on the ASPERA-3
    Web site.

18
ASPERA-3 PHASE B/C/D MASTER SCHEDULE
Write a Comment
User Comments (0)
About PowerShow.com