Title: Monthly 7_25 Page 1
1Monthly Status Report Report due 7/25/00 Schedule
statused as of July 7, 2000
2Project Status Summary
Programmatic May Jun Jul
Resources May Jun Jul
Schedule May Jun Jul
Detailed Description (for items identified as
yellow or red)
- Over the last period we continued with flight
fabrication and prototype testing. We continue
to see no major show stoppers. Some of our
biggest concerns continue to to be with outside
purchases/subcontracts. We have already
implemented some workarounds to maintain the
schedule (with contingency). The current
schedule does reflect all of the most recent
delivery dates from outside vendors (as of
7/24/00) and an update to the schedule to regain
schedule slack. - Latest project photos are available on Aspera-3
web site.
3Problem and Concern Summary
PProblem CConcern RResolved
4Accomplishments of the Last Month -ELS
- Ran High Voltage breakdown test. Test was very
straightforward with no problems. - Connected ELS end-to-end through GSE and tried to
see electron beam. Successfully saw beam in all
16 sectors. One sector seemed very noisy, one
sector seemed very weak. - Examined pulse height distribution curves for
flight MCP set. Threshold of ELS was set way to
low. Pulled ELS out of the chamber and changed
resistors to raise the threshold. Also cleaned
up the wiring for the grounding of the ELS
electronics. - Realized that with the higher than expected
required voltage for the MCP bias, we only have
about 150 volts headroom on the power supply
for operations(current max voltage is 2800 v).
We decided for flight build to increase max
voltage to 3000 v. Flight and flight spare HVPS
are now being fabricated for max voltage of 3000
v. - Received 2nd of 5 flight MCP sets. Next
possible set is at least a week away.
5Accomplishments of the Last Month ELS (cont.)
- Continued characterization testing. Spent lots
of time chasing noise in the GSE and set up.
This included reducing length of cables, adding
shields, adjusting GSE s/w, characterizing the
pulse shape at various locations in the test
set-up, etc. When ELS is in the chamber without
the housing, the background rate is approaching
that of just the MCP after burn-in (cant do any
better than that). - New Concern When the Housing and Grid are
installed, the background count rate goes up
considerably. We are currently trouble shooting. - Talked to Hyperfine They increased their
estimated late delivery because their
subcontractor who does rough machining is late.
As of 7/14/00, it looked like Hyperfine would be
8 weeks late on delivery of ELS mechanical parts.
We have now pulled back rough machining and and
are currently cutting metal on the flight and
flight spare housing. High tolerance finish
machining will still be done by Hyperfine. We
have updated the schedule to reflect our current
estimate for machining at SwRI, Hyperfine
machining, and update on UV coating time needed.
6Accomplishments of the Last Month - IMA
- Completed fabrication of the Pogo alignment jig.
- Disassembled IMA to examine problem of cracked
MCP. It was determined that the failure was
caused by a bending mode rather than crushing or
a sharp bur. Have come up with a couple of
possible reasons for failure. We are looking at
modification of the design to correct the
problem. - The threshold of IMA also needs to be tailored to
the MCP. It is likely that we are currently set
to sensitive - Started fabrication of FM and FS IMA anode
boards. Stopped to work on ELS HVPS boards. - Began fabrication of test MCP that strain
gauges will be mounted to for MCP holder
evaluation. - We are focusing on ELS rather than IMA as it is
critical path.
7Accomplishments of the Last Month - Data
Reduction Software
- Updated ASPERA-3.org Web Site Documentation
- Continued Updates to the ASPERA-3 Data System
Interface Document - Continued Formally Documenting APAF Software
Requirements - Continued Providing Technical Assistance for EPO
Web Information - Continued Defining and Implementing IDFS Web
Tools - Provided Software Support for ELS
Characterization - Held monthly ASPERA-3 Software Status Meeting
(July 24, 2000) - Article Published in July 2000 Issue of NASA Tech
Briefs, "A Standard for Scientific Data Files",
that Briefly Describes the IDFS Paradigm
8Planned Activities for the Next Month - ELS
- (Hopefully) receive flight sets 3 and 4 of the
MCPs - Finish rough machining of ELS parts and receive
high tolerance parts back from Hyperfine. - Finish characterization testing of the ELS
prototype. - Begin environmental testing of the ELS prototype.
- Finish fabrication of the flight and flight spare
HVPS and Amp boards. - Finalize test procedures.
9Planned Activities for the Next Month - IMA
- Finalize investigation of the MCP holder and make
necessary modifications to prototype and flight /
flight spare units. - Finish fabrication of the Amp board and Digital
Board. - Fix pogo alignment in prototype.
- Change out FPGA on prototype.
- Finalize test procedures.
- Restart vacuum testing prototype, following ELS
prototype testing to verify FPGA change.
10Planned Activities for the Next Month - Data
Reduction Software Tasks
- Deliver APAF Data System Interface Document (Due
Aug. 18) - Continue Formally Documenting APAF Software
Requirements - Continue Providing Technical Assistance for EPO
Web Information - Continue Defining and Implementing IDFS Web Tools
- Continue Providing Software Support for ELS
Characterization as Needed - Provide Software Support for Upcoming ASPERA-3
Team Meeting as Required
11Problem and Concern Status
- Delivery of MCPs from Burle
- This is still a major concern. We have received
2 sets of mechanical samples, 1 set of flight
reject plates, and 2 sets of plates that meet
flight specs. The next potential delivery of
flight plates will be in two weeks. Our schedule
is still not effected by the delivery slippage.
We have been in close contact with the Burle test
engineer and he has been very forthcoming about
status and providing us information.
12Problem and Concern Status (cont.)
- Alignment of ELS
- We found out that Hyperfine was projecting a
delivery that was 8 weeks late largely due to
their supplier being late. We have pulled the
rough machining back in house and have
prioritized the order of machining. Our goal is
to have all parts needing UV coating (ie housings
and inner deflection plates) completed by
Hyperfine by mid-August.
13Problem and Concern Status (cont.)
- Alignment of Pogos in IMA
- We have completed modification of the fixture
that holds the pogos in place during their
assembly and soldering process. We have also
modified the assembly and test procedures to
include resistance-to-ground measurements that
will verify the electrical connection after
assembly, and prior to and after each
environmental test. We will keep this issue a
concern until the prototype is corrected and the
assembly procedure is verified. We feel that
this is only a small concern because after our
problem, we consulted with some non-ASPERA
personnel who have more experience using pogos.
We have since incorporated their proven expertise
into our assembly process.
14Problem and Concern Status (cont.)
- MCP mount IMA
- We are still in the process of determining the
cause of the cracks in the IMA MCP. We have
fabricated a test MCP out of thin aluminum that
will be instrumented with strain gauges. We will
reassemble the prototype with the psuedo MCP and
measure the stress /strain during assembly. We
will then make mods to the prototype mechanical
pieces and verify stress / strain is reduced. We
may also use this technique to verify flight
parts.
15Problem and Concern Status (cont.)
- High background rate in ELS
- After a lot of effort debugging GSE, shortening
cables, modifying ELS GSE software, we have
gotten the background noise of the ELS sensor
(without the housing and grid) to a background
level comparable with the count rate for the MCP
by itself. Early testing, however in the housing
with the grid, showed very high count rates. We
are in the process of investigating this problem.
The first step is to see if the problem still
exists since we have debugged the GSE, test
set-up etc.
16 Schedule Summary
- ELS The July 7th version of the schedule
continues to show that the flight HVPS is the
critical path for ELS (0 days of float). We
simply started the fabrication of the HVPS later
than we should have. - The mechanical path is the second most critical
caused by Hyperfine being late. ( 5 days of
float) - We adjusted the schedule over the last month
incorporating many workarounds (ie. more
realistic durations for some tasks, weekend, and
shift work etc.) - Note the schedule still has 21 days slack at the
end (DEL0050) in addition to float shown for each
task. - MCP delivery is still not effecting the schedule.
17Schedule Summary (cont.)
- IMA The IMA schedule still shows 5 days float,
this is of course dependent on the MCP mount
investigation. We feel that worst case however,
we will only need to modify or remanufacture a
small number of mechanical parts. This will
occur in parallel with the stuffing and bench
check out of the amp and digital PC boards thus
not effecting the schedule. - Software activities continue to be on schedule.
- The full-up schedule is available on the ASPERA-3
Web site.
18ASPERA-3 PHASE B/C/D MASTER SCHEDULE