Title: World Bank Iraq Trust Fund
1World Bank Iraq Trust Fund
- The World Bank
- Dead Sea, July 19th, 2005
Dead Sea, July 19th, 2005
2World Bank Emphasizes Iraqi Leadership
- The comparative advantage of World Bank financing
- and the measure of its effectiveness
- is in the institution building associated with
its projects.
Dead Sea, July 19th, 2005
3ITF Project Initiation
- By end-December 2004 (nine months after ITF
inception) the World Bank and Iraqi counterparts
prepared, appraised, approved, and signed Grant
Agreements for nine projects - in all 18 governorates
- totaling US366 million
- obligating 93 of available ITF funds
to projects
Dead Sea, July 19th, 2005
4ITF Project Types
- Seven out of 9 investment projects for US355
million are grants to Iraqi institutions - Thus, 90 of ITF funds are managed, contracted
and disbursed by Iraqi agencies (5 line
ministries and the Municipality of Baghdad) - Two technical assistance projects for US10
million provide capacity building implemented by
World Bank on behalf of MoPDC - Less that 3 of ITF funds are managed, contracted
and disbursed by World Bank
Dead Sea, July 19th, 2005
5Profile of ITF Investment Projects
- Six ITF investment projects are grants for large
reconstruction and rehabilitation projects to be
implemented over 2-3 years by Iraqi agencies. - Five of the seven projects have been operational
only about 6 months. - Six out of the seven projects are geographically
spread throughout Iraq. - All of the projects finance goods and works that
require time for bidding, contracting, delivery,
and invoicing prior to disbursements.
Dead Sea, July 19th, 2005
6ITF Capacity Building Projects
- Capacity building is built into World Bank
investment projects - The ITF also finances two stand-alone capacity
building projects
Dead Sea, July 19th, 2005
7ITF Disbursement Overview
- ITF grants are disbursed in accordance with World
Bank procurement policies (in line with best
practice standards) - Disbursement follows project implementation
(disbursement occurs after satisfactory delivery
of goods/services)
Dead Sea, July 19th, 2005
8Implementation Status
- Implementation on the ground will continue to be
challenging - World Bank will provide on-going close and
pro-active assistance to implementing agencies
Dead Sea, July 19th, 2005