F0 Lambertson Liner reviewJ Volk
  • WBS for Liner
  • Liner fabrication
  • Liner installation
  • Liner installation tests at MI-60
  • Vacuum tests at MI-60

2
F0 Lambertson Liner Fabrication
Aug 13 all liners ready
Jul 8 Expect first liner
Jul 21Approve making next 6
3
F0 Lambertson Liner installation
Aug 29 2 liners installed
Sep 3 all liners installed
Sep 14 Pump out begins
Sep 2 magnet mover To MI-60
4
Lambertson at MI-60
Field Region
Field Free region
Ledge
5
Liner Installation
  • ESH issues with Copper Beryllium
  • Be training for techs
  • No sanding, cutting, grinding, machining, ect.
  • Clean up afterward
  • Support of liner during installation
  • Push, Pull, or vacuum through the liner?
  • Ledge at entrance
  • Use of Stainless Steel strips to guide liner
  • Any special tools we may need

6
Vacuum Tests
  • Current vacuum at F0 on the order of 10-9
  • Need to bake out Lambertson with liner to assure
    that vacuum is good with the liner
  • If vacuum worse than 10-7 we cant install liners
    at F0
  • We are working with Bruce Hanna to get equipment
    at MI-60 to do full vacuum test
  • Also measure impedance after vacuum bake out

7
Conclusions
  • We have schedule for preparation and installation
    that fits with time constraints
  • We will test installation and vacuum before we
    commit to installation
  • There is slack time to make up for delay caused
    by any problems