Assorted VTS News Items - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Assorted VTS News Items

Description:

Plan for MOU addendum with JLab for Tom Powers' time on RF commissioning ... RF System Engineering Design (Tom) [45 mins] Schematics. Data acquisition and control ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 10
Provided by: gins3
Category:

less

Transcript and Presenter's Notes

Title: Assorted VTS News Items


1
Assorted VTS News Items
  • Project subtasks
  • Aseet Mukherjee is designing a thermometry system
    for 9-cell cavities
  • RD stage
  • Currently planning cryo test of cheaper
    thermometers in ICB (with help from E. Barzi)
  • Andrei Lunin has preliminary RF design for a VTS
    input coupler
  • Will prepare some plots showing operational range
    in terms of measurement quantities
  • Valeri Poloubotko will design the radiation
    shielding lid/movement
  • Communications with management
  • VTS project progress report for GDE to be
    submitted today
  • Only approved tasks appear
  • Completed tasks FY06, and plans for remainder
    FY06 and FY07
  • Proposal for two additional VTSs (gtFY07) in
    preparation (R. Kephart et al.)
  • VTS update to ILC/SRF RD meeting Thursday August
    3
  • Plan for MOU addendum with JLab for Tom Powers
    time on RF commissioning
  • Plan for electronic logbook (M. Votava) meeting
    today at 2 pm

2
Update of ILC/FNAL RF responsibilities
NB Ralph Pasquinelli is overall responsible
person for ILC/FNAL RF
Generally AD is responsible for RF outside the
cryostat TD is responsible for RF inside
(cables, input couplers, etc.)
3
RF System Design Review
  • Charge to the committee
  • Assess and comment on all technical aspects of
    the IB1 VTS RF system design, and
  • Provide a written report. 
  • Committee members Ralph Pasquinelli (chair), Jim
    Steimel, Brian Chase, Chuck Worel, John Reid,
    Wolf-Dietrich Moeller
  • Time/date/location/deadlines
  • Thursday, August 24, 830-1230
  • IB1 Mezzanine conference room
  • Background materials to committee by August 17

4
VLCW06 News Gradient task force
Charge to the committee
  • The RDB is asked to set up a task force to carry
    out a closely coordinated global execution of the
    work leading to the achievement of the
    accelerating gradient specified in the ILC
    Baseline (BCD)
  • A definition of the goals for the cavity
    performance in terms of gradient and yield and a
    plan for achieving them should be proposed by
    this group, which should take account of the
    global resources available and how they may be
    used most rapidly and efficiently.
  • The accelerating gradient performance and yield
    should be specified both for an individual 9-cell
    cavity and for an individual cryomodule, and the
    plan should cover the demonstration of this
    performance in both cases.
  • The GDE will facilitate the coordination at the
    global level to achieve this vital goal asap.
  • Members Hitoshi Hayano, Toshiyasu Higo, Lutz
    Lilje, John Mammosser, Hasan Padamsee, Marc Ross,
    Kenji Saito

5
VLCW06 News Gradient task force
  • Make tests more reproducible among labs
  • Define tests needed on 9-cells
  • complete documentation of prep/test process
  • develop common set of parameters
  • results more comparable
  • Synchronize efforts globally
  • model of international coordination of RD
    efforts
  • distribute work load

6
VLCW06 News Gradient task force
  • Stage 1 Tight-loop (finish mid-2007)
  • Start with 20 cavities globally. Carry out the
    full treatment once
  • Pick out the best 9 cavities and distribute 3 per
    location. These 9 cavities have a starting
    average gradient and spread.
  • Show reproducibility of final process with 3
    best cavities at each location by using the
    tight-loop EP 20um/HPR/test. cavities x 3
    cycles 9 tests per location
  • Determine spread and best gradient for final
    treatment process
  • Stage 2 improved tight-loop (finish mid 2008)
  • Include improvements from the parallel/coupled
    RD program
  • Repeat the first stage with the same 9 cavities,
    get smaller spread with higher gradient
  • Stage 3 Production Like (start 06)
  • Order a large number of cavities starting asap in
    06/07
  • According to first assessment, total number of
    cavities in hand by end of 2007 could be 50-60
  • Stage 4 Final Production (finish mid-2009)
  • Carry out full treatment. Apply best recipe from
    stage 2 to large batch of cavities

7
(Preliminary) set of common tests for 9-cells
VLCW06 News Gradient task force
  • Check for hydrogen contamination of the niobium
    material (Q-disease)
  • Stay at 100K for 8 hours during cooldown, cool
    down curve should be provided
  • As this test significantly extends the testing
    time for some labs, may be omitted after
    confidence has been gained, that the processes
    do not contaminate the niobium with hydrogen.
  • Common Q(T) measurement field level about 1 MV/m
    for residual resistance measurement
  • p mode as a standard decision on the data, but
    all 9 passband modes have to be measured in order
    to interpret this right
  • information of the field flatness has to be added
    (known) some times we see results, hard to
    understand and not to explain with the bad field
    flatness
  • Help to localize the problem -    Checks of
    fundamental mode spectrum for possible detuning
    of the field flatness (instead of bead-pull)
  • Deformation in field flatness would lead to a
    unusable information from the passband modes
    measurement (if the field flatness is known, it
    could be recalculated)
  • Further information to be provided with the data
    above include
  • Continuous pumping during test or closed cavity
    vacuum valve
  • If closed, pressure before closing valve
  •     Cooldown speed
  • Temperature difference over cavity during
    cooldown
  • Method of low-power processing if necessary
  • pulsed or cw
  • Coupler type (fixed or variable)
  • Recorded quantities Eacc, Qo, Qext, Qtrans,
    Qhom, Pfor, Prefl, Ptrans, Phom, Beta, frequency,
    He bath temperature, X-ray flux, Comments

8
RF Design Review Proposed Agenda
For discussion
  • Introduction to VTS (Camille) 15 mins
  • Introduction to the team members
  • Project scope/progress/plans (copy/update talk
    from July 6 ILC/SRF meeting)
  • Infrastructure (Cosmore) 15 mins
  • Proposed instrumentation rack location, assembly
    area, etc.
  • Drawings with shielding location and movement (as
    known)
  • Technical parameters of the measurements (Joe)
    30 mins
  • Test plans, testing capacity (including cryo
    capacity)
  • Pages 1-5 of May 12 talk, with emphasis on what
    is measured, and why. (motivate the design)
  • Required frequency range, phase and amplitude
    stability, input power step size
  • Some data from JLab or DESY of measurement
    ranges, as available/relevant
  • RF System Engineering Design (Tom) 45 mins
  • Schematics
  • Data acquisition and control
  • RF System Implementation plans (Joe/Ruben) 30
    mins
  • Instrumentation list
  • Summary/status of purchases
  • Project tasks/milestones/resources/schedule

9
RF Design Background Materials
  • Test plans, testing capacity
Write a Comment
User Comments (0)
About PowerShow.com