Title: Assorted VTS News Items
1Assorted VTS News Items
- Project subtasks
- Aseet Mukherjee is designing a thermometry system
for 9-cell cavities - RD stage
- Currently planning cryo test of cheaper
thermometers in ICB (with help from E. Barzi) - Andrei Lunin has preliminary RF design for a VTS
input coupler - Will prepare some plots showing operational range
in terms of measurement quantities - Valeri Poloubotko will design the radiation
shielding lid/movement - Communications with management
- VTS project progress report for GDE to be
submitted today - Only approved tasks appear
- Completed tasks FY06, and plans for remainder
FY06 and FY07 - Proposal for two additional VTSs (gtFY07) in
preparation (R. Kephart et al.) - VTS update to ILC/SRF RD meeting Thursday August
3 - Plan for MOU addendum with JLab for Tom Powers
time on RF commissioning - Plan for electronic logbook (M. Votava) meeting
today at 2 pm
2Update of ILC/FNAL RF responsibilities
NB Ralph Pasquinelli is overall responsible
person for ILC/FNAL RF
Generally AD is responsible for RF outside the
cryostat TD is responsible for RF inside
(cables, input couplers, etc.)
3RF System Design Review
- Charge to the committee
- Assess and comment on all technical aspects of
the IB1 VTS RF system design, and - Provide a written report.
- Committee members Ralph Pasquinelli (chair), Jim
Steimel, Brian Chase, Chuck Worel, John Reid,
Wolf-Dietrich Moeller - Time/date/location/deadlines
- Thursday, August 24, 830-1230
- IB1 Mezzanine conference room
- Background materials to committee by August 17
4VLCW06 News Gradient task force
Charge to the committee
- The RDB is asked to set up a task force to carry
out a closely coordinated global execution of the
work leading to the achievement of the
accelerating gradient specified in the ILC
Baseline (BCD) - A definition of the goals for the cavity
performance in terms of gradient and yield and a
plan for achieving them should be proposed by
this group, which should take account of the
global resources available and how they may be
used most rapidly and efficiently. - The accelerating gradient performance and yield
should be specified both for an individual 9-cell
cavity and for an individual cryomodule, and the
plan should cover the demonstration of this
performance in both cases. - The GDE will facilitate the coordination at the
global level to achieve this vital goal asap. - Members Hitoshi Hayano, Toshiyasu Higo, Lutz
Lilje, John Mammosser, Hasan Padamsee, Marc Ross,
Kenji Saito
5VLCW06 News Gradient task force
- Make tests more reproducible among labs
- Define tests needed on 9-cells
- complete documentation of prep/test process
- develop common set of parameters
- results more comparable
- Synchronize efforts globally
- model of international coordination of RD
efforts - distribute work load
6VLCW06 News Gradient task force
- Stage 1 Tight-loop (finish mid-2007)
- Start with 20 cavities globally. Carry out the
full treatment once - Pick out the best 9 cavities and distribute 3 per
location. These 9 cavities have a starting
average gradient and spread. - Show reproducibility of final process with 3
best cavities at each location by using the
tight-loop EP 20um/HPR/test. cavities x 3
cycles 9 tests per location - Determine spread and best gradient for final
treatment process - Stage 2 improved tight-loop (finish mid 2008)
- Include improvements from the parallel/coupled
RD program - Repeat the first stage with the same 9 cavities,
get smaller spread with higher gradient - Stage 3 Production Like (start 06)
- Order a large number of cavities starting asap in
06/07 - According to first assessment, total number of
cavities in hand by end of 2007 could be 50-60 - Stage 4 Final Production (finish mid-2009)
- Carry out full treatment. Apply best recipe from
stage 2 to large batch of cavities
7(Preliminary) set of common tests for 9-cells
VLCW06 News Gradient task force
- Check for hydrogen contamination of the niobium
material (Q-disease) - Stay at 100K for 8 hours during cooldown, cool
down curve should be provided - As this test significantly extends the testing
time for some labs, may be omitted after
confidence has been gained, that the processes
do not contaminate the niobium with hydrogen. - Common Q(T) measurement field level about 1 MV/m
for residual resistance measurement - p mode as a standard decision on the data, but
all 9 passband modes have to be measured in order
to interpret this right - information of the field flatness has to be added
(known) some times we see results, hard to
understand and not to explain with the bad field
flatness - Help to localize the problem - Checks of
fundamental mode spectrum for possible detuning
of the field flatness (instead of bead-pull) - Deformation in field flatness would lead to a
unusable information from the passband modes
measurement (if the field flatness is known, it
could be recalculated) - Further information to be provided with the data
above include - Continuous pumping during test or closed cavity
vacuum valve - If closed, pressure before closing valve
- Cooldown speed
- Temperature difference over cavity during
cooldown - Method of low-power processing if necessary
- pulsed or cw
- Coupler type (fixed or variable)
- Recorded quantities Eacc, Qo, Qext, Qtrans,
Qhom, Pfor, Prefl, Ptrans, Phom, Beta, frequency,
He bath temperature, X-ray flux, Comments
8RF Design Review Proposed Agenda
For discussion
- Introduction to VTS (Camille) 15 mins
- Introduction to the team members
- Project scope/progress/plans (copy/update talk
from July 6 ILC/SRF meeting) - Infrastructure (Cosmore) 15 mins
- Proposed instrumentation rack location, assembly
area, etc. - Drawings with shielding location and movement (as
known) - Technical parameters of the measurements (Joe)
30 mins - Test plans, testing capacity (including cryo
capacity) - Pages 1-5 of May 12 talk, with emphasis on what
is measured, and why. (motivate the design) - Required frequency range, phase and amplitude
stability, input power step size - Some data from JLab or DESY of measurement
ranges, as available/relevant - RF System Engineering Design (Tom) 45 mins
- Schematics
- Data acquisition and control
- RF System Implementation plans (Joe/Ruben) 30
mins - Instrumentation list
- Summary/status of purchases
- Project tasks/milestones/resources/schedule
9RF Design Background Materials
- Test plans, testing capacity