Title: SIPs: A Critical Component of Zero Energy Homes
1SIPs A Critical Component of Zero Energy Homes
April 21, 2009 2009 SIPA Annual Meeting, Chicago,
IL
2From 5 small Habitat test Houses to medium spec
and Custom near ZEH developments
- TVA demographically selected house size, builder,
developer, location, 225- 260K price range, - Builder house, 2400 ft2, HERS 90, 5.7 ACH_at_50
Pascals - Retrofit house, 2400 ft2, HERS 66, 3.2 ACH_at_50
Pascals - nZEH, 2500 ft2, HERS 34, 2.63 ACH_at_50 Pascals
- Lead Builder in East Tennessee
- 3600 ft2, HERS 37, SIP
- 3600 ft2, HERS 39, Optimum Value Engineered
Framing - Two 2700 ft2, Exterior Insulated Finish System,
Phase Change Materials
3US DOE Goal to develop an Affordable Zero Energy
Home by 2020
- Produces annually on-site solar energy equal to
the energy requirements. - Provides standard energy services typical
expected energy using features (National
Averages) - Net ZEH is defined as HERS index 0 US
- Added first cost 30 year mortgage incremental
payment off set by energy cost savings at end of
first year
4(No Transcript)
5Motivation
- In the U.S.
- 40 of US CO2 comes from buildings
- 71 of electric grid serves buildings
- Grid will be shared with plug-in-hybrids
- In developing countries, standards of living
improving and energy demand increasing world wide - 34 out of 37 Countries polled believe the US is
the major contributor to Climate Change
6Energy Consumption of 5 Habitat for Humanity near
ZEH kWh and /day
20000
29-41 Solar
15000
kWh
SOLAR
10000
GRID
5000
0
3.36
1.04
0.91
0.81
0.77
0.69
Base
ZEH1
ZEH2
ZEH3
ZEH4
ZEH5
7ZEHcor
Premanufacture and ship to site, Just like SIPS
First cost savings potential 1000 to 3000
Energy savings 5 to 10
8Blower Door study of sticks with blown foam vs
SIPs in identical 1200 ft2 Habitat houses
9Envelope Air-tightness of sticks with foam as
good as SIPS
1.35 ACH50
4.0 ACH50
1.15 ACH50
1.7 ACH50
1.09 ACH50
1.64 ACH50
10Future ZEH will be aggregated to dispatchable
green power plants
11August 2007 The Hottest on Record
12In August 2007 TVA (Electric Utility servicing
Tennessee) all time Top 10 System Peaks
13(No Transcript)
1439 oC
23 oC
15(No Transcript)
1623.6 C
17TVA all time Critical Peak Period
18Summary of peak load savings from near zero
annual energy homes in East Tennessee
19100/mo mortgage
20Campbell Creek near Zero Energy House
21- Campbell Creek Research House, 2,500 ft2, HERS
34 (Incl. Solar) - Advanced framing (2 x 6) with DOWsis (R-2.74)
sheathing rather than OSB - R-49 attic with LP Techshield radiant barrier
sheathing - R-6 triple-pane gas-filled windows
- One 2-ton air-source heat pump, SEER 16, HSPF
9.5, air-side zone control - Fantech energy recovery ventilator (ERV)
- Advanced appliances, waste heat recovery, HPWH,
2.5 kW solar PV, etc.
22TVA Three House Study House 3 Near Zero Energy,
HERs Index 34
- Advanced 2 X 6 Framing with DOWsis
- R-49 attic with LP Techshield radiant barrier
sheathing - R-7. Triple layer windows from Serious Materials
- R-10 vertical slab stem wall insulation
- One Amana 2-ton HP, SEER 16, HSPF9.5, zone
control - Fantech Energy Recovery Ventilator
- Advanced GE appliances
- Energy Star pin based High performance lighting
design - Solar drain-back water heater
- 2.5 kWh Solar PV system
- Greywater waste heat recovery
- Appliance waste heat recovery
- 70 heating energy savings
23House 3 Advanced Framing
2424 inch on center Advanced Framing
25Insulated headers above windows
26DOWsis, R-2.74/ ½ inch, 3 in. nail spacing at
perimeter, 6 in in the field, avoid ladder marks
27Two stud corners rather than 3 or 4
28Two inches vertical XPS Slab insulation
29Before the wall is pushed up 1. stable sill seal
to pressure treated bottom plate
302. Stable 6 inch aluminum flashing
313. Stable second layer of sill sealer
32Air seal, termite barrier and capillarity break
sandwich
33Knee walls Classic over sight
34Bonus knee walls all foamed up ready for spider
35Added 2X6s to allow R-41 in bonus cathedral
36(No Transcript)
37Bonus Room means lots of extra blocking
Bonus Room Floor above Garage
Knee walls
38Blocking behind tub and shower
39Master bath well sealed insulated and ventilated
40Blocking adds costs back in
41Behind the fireplace chase
42Foam at least air sealling framing trouble spots
still leaves thermal shorts
43Cantilevered floor
44Flash all sides of cantilevered floor truss cavity
45Cantilevered floor remaining space filled up
with Spider
46Blocking between garage and dining
47Blocking needed to air seal
48Blocking between garage and kitchen
49Taped DOWsis board and flash serves as the air
barrier for this house
50Spider men
51Envelope Air-tightness of the Builder, Retrofit
and the NZEH
5.7 ACH_at_50
3.27 ACH_at_50
2.6 ACH_at_50
52Envelope Air-tightness of other NZEH prototypes
1.35 ACH50
1.64 ACH50
4.0 ACH50
2.6 ACH50
1.15 ACH50
1.7 ACH50
1.09 ACH50
53Retrofit is 4/ft2 floor area more than the
Builder and NZEH is 21/ft2 more?
Total cost K
Includes some cost of installing instrumentation
54Insulation alone in the NZEH is 1.67/ft2 more
than the Builder
55Measured heating energy kWh from January 24 until
February 4, 2009
35 Saver
kWh
65 Saver
56Projected energy costs per year 0.65/ft2
savings for NZEH compared to Builder
Save 444/yr
Save 1544/yr
- Assumes TVA solar buy back is 0.10 kWh
- more than residential rate
57Key Features for near ZEH
- SIPS with drainage plane or Optimum Value
Engineered 2X6 with foam sheathing air barrier - High Performance Windows (U-value 0.2-0.34, SHGF
0.35) - Air tight (1.5 ACH_at_50) infiltration)
- Ducts inside the conditioned space
- ASHRAE 62.2 mechanical ventilation
- Raised metal seam roof (no roof penetrations)
- Geothermal\Exterior Foundation insulation
- 2.5 kW PV Solar system
- House daily reminds you how precious it is to
collect energy from the sun and how easy it is to
shut of a light U.S. News World Report April
22, 2008
58Schaad, DOE Builder Challenge, 4 HERS 40-30
energy saver test houses
59SIPS vs Optimum Value Framing (framing fraction
13)
60Seeking Affordable 50 Energy Saving Envelope
61- RD lineage springs from SIPA and ORNL
partnership - Purpose of projects
- Low-HERS Research affordable ways to go lower
(new/retrofit) - Low-HERS Education build consumer demand,
builder/contractor capacity
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68Double layer of papers eliminates cost for
furring strips and ½ inch drainage layer over SIPS
69Foundation geothermal loop
Electrical
Water
Sewer Line
70ZEHcor
71ZEHcor for basement of 3 story ZEH
72FHX
ZEHcor
73ZEHcor Interior Utility Wall
- Saves energy
- Imposes floor plan discipline
- Reduces hot water distribution losses
- Enables integration that could never be done
reliably on-site - ERV-to-FHX
- Appliances grey water to FHX
- Reduces cost
- Pre-fabrication in a controlled environment
- Greater labor productivity
- Less materials waste
ZEHcor
74Thank you!
?
- Jeff Christian
- ChristianJE_at_ORNL.gov