Title: SISTEC Presentation July 3 2002
1Do SUDS Work? A Monitoring Overview at DEX
Chris Jefferies University of Abertay Dundee
2Presentation Content
- Overview of the DEX Monitoring Programme
- Hydrology and water quality
- Monitoring costs
- Observational monitoring
- Dissemination of outcomes
- Acknowledgements to Wilcon Homes Now Taylor
Woodrow
3Monitoring was a Condition of Planning Consent
- SUDS were virtually unknown when DEX was planned
- Many questions about planning, design and
operation had not even been asked, let alone
answered. - Clause in consent - main developer (Wilcon Homes)
should monitor performance for five years May
1999 April 2004 - UWTC bid for and won this work.
- Geek name Monitoring Urban Drainage Wilcon,
Abertay Dundee, Edinburgh (MUDWADE)
4MUDWADE Rationale
- Financial justification Commuted sum of 90k
per pond for 7 ponds sought by Fife Council for
maintenance monitoring much cheaper. Once
results available, then strength to negotiate! - Flows and loads monitoring both longer term and
event based. - Sediment surveys (Kate Heal)
- Visual inspections, photographs, reporting
problems - Maintenance cost monitoring
- Initially the remit was to examine all SUDS on
Duloch Park but by April 2004 this had reduced to
3 ponds and 1 wetland
5SUDS Maintenance Investigations DEX - The Ponds
6 Flows and loads monitoring
- Initially we wanted to monitor at 3 ponds and 2
detention basins - Pond 7 was control but development commenced very
quickly. - One of the detention basins outlet blocked for
18 months.
7Catchments Under Investigation
8Water Quality
Monitoring results - Linburn Pond inflow TSS
Monitoring results - Linburn Pond outflow TSS
Pollutant Budget Very difficult due to number of
inflows and duration of study needed. What would
be the purpose?
9Water Quality
Question - How do you decide if these treatment
ponds are satisfactory?
Answers -
Hydraulics - Well established principles set by
flow criteria Water quality - What should be the
basis of the decision? What time frame should
be used? How do you view episodes of poor
quality? Do you use a two tier consenting
approach? Should the outflow be stream water
quality?
10Flow Model Calibration using PCSWMM
- A number of continuous rainfall runoff sets
including flows, continuous sonde data and spot
sampling - Eyeball comparison of measured flows with
modelled.
11Conclusion from flow quality monitoring
- Detention basin with appropriate flow controls
could be a replacement for ponds if catchment
hydrology is the only concern. - Detention basins could replace the ponds and
allow for extra development space if catchment
hydrology is the only concern. - The Water Quality Performance of these ponds is
excellent and will probably remain so. - However, water criteria for treatment ponds must
be established. - Modelling and evaluation of the Halbeath and
Linburn pond catchments at Duloch Park is
continuing
Thanks to Adolf Spitzer
12SUDS Maintenance Investigations
- Monitor / Visually Inspect regional systems at
Duloch Park / DEX - Document observed maintenance activities and
system performance using simple tick sheets and
photography - Gather maintenance cost data from land based
contractors
Thanks to Gaye McKissock Alison Duffy
13SUDS Maintenance Investigations
- MUDWADE Project Cost Data
- UWTC received copies of
- Detailed invoices from project manager
- Payment certificates from project manager
- Inspection sheets from contractor
- Fax outlining monthly breakdown in activities
from contractor
14DEX Maintenance Activities
15 Observational Monitoring
- Regular visits to catalogue changes with time
- Photographic evidence supported by measurements
- Concurrent development information.
- Tick sheets completed at each visit.
- Focus on Detention Basins here
16 Linburn Pond (Kate Heal)
17Detention basins serve each site at DEX in
Dunfermline
18Detention Basins
19Basin D/M
Detention Basins
20NATS Car Park, Edinburgh
Outlet blocked by a polythene bag
21 Outcomes from observation programme
- Guidance on detention basin design detailing
- Sediment
- Mostly from the construction phase
- Detention basins trap much of the sediment
- Need far better construction site management
- Risks posed by sediment in ponds much less than
feared - Post development inspections essential prior to
adoption by Scottish Water - Whole life costing information (mostly
confidential)
22 Dissemination of performance information
- Engagement with academics at Scottish
Universities - SUDSnet developed from this group
- Report published by Sniffer Report SR 02(51)
- SUDS in Scotland The Monitoring Programme of
the Scottish Universities SUDS Monitoring Group - Obtained from SUDSnet Website
- Results reported regularly to SUDSWP
- Training
- Scottish Local Authorities
- Online SUDS Course
- Flows and qualities dataset soon available to
academics
23Thank You Acknowledgements to Taylor Woodrow
Detention Basin B Feb 2004