Contractual Claims: Time - PowerPoint PPT Presentation

1 / 40
About This Presentation
Title:

Contractual Claims: Time

Description:

(b) necessary by reason of weather conditions affecting the safety or quality of work ... or injury: direct consequence of the Architect's design of the Works ... – PowerPoint PPT presentation

Number of Views:103
Avg rating:3.0/5.0
Slides: 41
Provided by: Reb112
Category:

less

Transcript and Presenter's Notes

Title: Contractual Claims: Time


1
Contractual ClaimsTime Money
6 September 2003 PQSL
  • Prepared by Mr. Louis Lee
  • LLB(Hons), MHKIS, MRICS, MCIArb, RPS(QS)

2
1. Contract
3
1. Contract
  • Essential Elements of a construction contract
  • 1. Product
  • Drawings, Specification
  • 2. Price
  • Type of contract, remeasurement, firm
    quantity, variation
  • 3. Time
  • Duration or specific date, Sectional
    possession and/or completion

4
Parties to the contract / parties concerned
  • 1. Employer
  • 2. Contractor
  • 3. Architect/Engineer/Surveyor
  • Relationships

Contractor
Employer
Architect/ Engineer/ Surveyor
5
Aims of the Parties
  • 1. Employer
  • product (the Works), on time, in accordance
    with requirements
  • 2. Contractor
  • satisfactorily complete the Works and get
    paid such sums as appropriate
  • 3. Architect
  • satisfactorily discharge its duties under the
    contract and get paid

6
Obligations of the Parties
  • 1. Employer
  • give possession of the Site, make payments
  • 2. Contractor
  • construct the Works in accordance with the
    requirements (quality and time)
  • 3. Architect
  • manage and supervise the project in various
    aspects (design, EOT, VO claim assessment)

7
Contractual Claims
  • 1. Situations
  • 2. Variation
  • 3. Time
  • 4. Cost

8
2. Contractual Claims Time
9
Time
  • 1. Timely completion of the Contract
  • 2. If delay occurred, what do the parties want?
  • - Compensation of time loss - to whom?
  • 3. Nature of events causing delay
  • - Caused by the Employer, Architect/ Engineer
  • - Caused by the Contractor
  • - Causes of neutral ground - e.g. caused by a
    third party, act of god, etc

10
Time
  • 4. Common law position
  • - time at large, general damages
  • 5. Mechanism in the Contract
  • - Liquidated damages - genuine pre-estimate
    of loss
  • - Extension of time

11
Time
  • Mechanism in the Contract
  • 1) Notice of delay event
  • 2) Time bar
  • 3) Grounds for extension of time
  • 4) Assessment and award of extension of time
  • Standard forms of contract adopted
  • i) HK Government GCC 1999 (for Building Works)
  • ii) HKIA Form 1986 (with quantities)

12
TimeNotice of Delay Event
  • i) Under Government Form 1999
  • - Clause 50(1)
  • a) within 28 days after the cause of delay
  • b) within 28 days after the Architect's
    instruction
  • ii) Under HKIA Form 1986
  • - Clause 23
  • Upon it becoming reasonably apparent

13
TimeTime bar
  • Under both of the standard forms
  • i) No extinction of rights if notification is
    served late
  •  
  • ii) Rights under common law

14
TimeGrounds for extension of time
  • i) Under Government Form 1999
  • - Sub-clause 50(1)(b)
  • (i) inclement weather and its effects
  • (ii) tropical cyclone warring signal No. 8 or
    above
  • (iii) Black Rainstorm Warning
  • (iv) variation under Clause 60
  • (v) substantial increase in quantity
  • (vi) not being given possession of the Site

15
TimeGrounds for extension of time
  • i) Under Government Form 1999
  • - Sub-clause 50(1)(b) (Contd)
  • (vii) disturbance for which the Employer/
  • Architect/Specialist Contractor responsible
  • including but restricted to Clause 63
  • (viii) suspension of Work (Clause 54)
  • (ix) utility undertaking
  • (x) Nominated Sub-Contractor
  • (xi) special circumstance

16
TimeGrounds for extension of time
  • i) Under Government Form 1999 (contd)
  • Causes not entitled for an extension of time
  • Sub-clause 50(1)(c)
  • (i) a suspension occasioned by circumstances
    under Clause 54(2)
  • (a) otherwise provided for in the Contract,
  • (b) necessary by reason of weather conditions
    affecting the safety or quality of work
  • (c) necessary by reason of default on the part
    of the Contractor

17
TimeGrounds for extension of time
  • i) Under Government Form 1999 (contd)
  • Causes not entitled for an extension of time
  • Sub-clause 50(1)(c)
  • (d) necessary for the proper execution of the
    Works or the safety of the Works or for the
    safety and health of any person of any property
    on or adjacent to the Site..
  • (ii) a shortage of Construction Plant or labour

18
TimeGrounds for extension of time
  • ii) Under HKIA Form 1986
  • Clause 23
  • (a) force majeure
  • (b) inclement weather or subsequent effects
    (gt20mm)
  • (c) clause 20A or B
  • (d) civil commotion, strike affecting the trades
  • (e) Architect's instruction under clause 1(2)
    discrepancies, clause 11(1) variation
    clause 21(2) postponement

19
TimeGrounds for extension of time
  • ii) Under HKIA Form 1986 (Contd)
  • (f) late instruction
  • (g) delay by Nominated Sub-Contractors or
    Suppliers
  • (h) delay on tradesmen or others engaged by the
    Employer
  • (i) opening up for inspection for testing
  • (j) (i) to secure essential labour
  • (ii) to secure essential goods or materials
  • Note only if so stated in the Contract Bills

20
TimeAssessment and award of extension of time
  • i) Under Government Form 1999
  • - Sub-clause 50(2) Architect shall within a
    reasonable time determine, grant and notify in
    writing such extension
  • ii) Under HKIA Form 1986
  • - as soon as he is able to estimate the
    length of the delay make in writing a fair and
    reasonable EOT

21
TimeOther points on extension of time
  • Under Government Form 1999
  • a) Sub-clause 50(3) Architect may require full
    and detailed particulars, if fails.
  • b) Sub-clause 50(5) except as provided elsewhere
    in the Contract, EOT granted shall be deemed to
    be in full compensation and satisfaction for any
    loss or injury

22
TimeEOT in application
  • 1) Criticality
  • For the completion of the Works or any section
    thereof
  • 2) Causes of delay
  • As specified under the provisions of the
    Contract
  • 3) Guideline / base programme for assessment

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
3. Contractual ClaimsMoney
29
Money
  • Mechanism in the Contract
  • 1) Notice for additional payment
  • 2) Time bar
  • 3) Grounds for additional payment

30
MoneyNotice for additional payment
  • i) Under Government Form 1999
  • - Clause 64(2) within 28 days after the
    happening of the events
  • ii) Under HKIA Form 1986
  • - Clause 24(1) written application within a
    reasonable time of it becoming apparent

31
MoneyTime bar
  • i) Under Government Form 1999
  • No extinction of rights if notification is served
    late,
  • however subject to
  • Clause 59(9)
  • if fails to submit written representation or
    any required information after the expiry of 90
    days from the date of service of the Bills of
    Variations, the Surveyor shall not obliged to
    take into account
  • ii) Under HKIA Form 1986
  • No explicit/strict terms

32
MoneyGrounds for additional payment
  • i) Under Government Form 1999
  • A) Clause 48(2) - Involved in expenditure,
    progress of the Works having been affected by the
    failure of the Employer to give possession under
    Clause 48

33
MoneyGrounds for additional payment
  • B) Clause 54(2) - Involved in additional
    expenditure by reason of a suspension order given
    by the Architect under Clause 54, unless the
    suspension order is
  • (a) otherwise provided for in the Contract
  • (b) necessary by reason of weather conditions
    affecting the safety or quality of work
  • (c) necessary by reason of default on the part
    of the Contractor
  • (d) necessary for the proper execution of the
    Works or the safety of the Works or for the
    safety and health of any person of any property
    on or adjacent to the Site

34
MoneyGrounds for additional payment
  • C) Clause 63 - Involved in expenditure, progress
    of the Works having been affected by
  • (a) late instruction from the Architect
  • (b) variation
  • (c) opening up for inspection
  • (d) delay caused by any person or company, not a
    utility undertaking, engaged by the Employer
  • (e) late delivery of material, plant or
    equipment by the Employer

35
Money Grounds for additional payment
  • D) Clause 21(4), excepted risks
  • (a) - (e) outbreak of war, invasion of Hong
    Kong, act of foreign terrorist, civil war,
    commotion etc
  • (f) occupation by the Employer, his agents
    employees
  • (g) damage, loss or injury direct consequence
    of the Architect's design of the Works
  • (h) neglect or default by the Architect or the
    Employer or their employees or agent in the
    course of their employment

36
Money Grounds for additional payment
  • D) Clause 21(4), excepted risks (Contd)
  • (i) ionsing radiations or contamination by
    radioactivity from any nuclear fuel
  • if instructed by the Architect, repair and make
    good the same at the expense or proportionate
    expense of the Employer valued by the Surveyor
    in the same manner as valuing variation

37
Money Grounds for additional payment
  • ii) Under HKIA Form 1986
  • A) Clause 11(6) - loss and expense caused by a
    variation, provisional sum or prime cost sums
  • - upon written application by the Contractor
  • - would not be reimbursed by payment in made
    in accordance with the rules contained in 11(4)

38
Money Grounds for additional payment
  • ii) Under HKIA Form 1986 (contd)
  • B) Clause 24 - loss and expense caused by
    disturbance of regular progress of the Works
  • (a) late instruction
  • (b) opening up for inspection
  • (c) discrepancy in Contract Drawings and.or in
    Contract Bills
  • (d) delay on the part of artists, tradesmen or
    others engaged by the Employer
  • (e) Architect's instruction in regard to the
    postponement of work

39
MoneyHeads of Claim
  • a) Direct Cost of resources utilised, idling
    costs
  • b) Loss of productivity
  • c) General items or preliminaries - insurance
  • d) Site overheads
  • e) Head office overheads
  • f) Profit
  • g) Escalation of costs as a result of inflation
  • h) Financial charges - for delayed recovery of
    fixed contributions, delayed recovery of the
    additional costs being claimed

40
  • Questions Answers
Write a Comment
User Comments (0)
About PowerShow.com