Extensions of Time Claims - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Extensions of Time Claims

Description:

... 'the Main Contractor shall forthwith give written notice of the cause of the delay' HK Government 'the Contractor shall forthwith give notice in writing to ... – PowerPoint PPT presentation

Number of Views:1508
Avg rating:3.0/5.0
Slides: 22
Provided by: hkis1
Category:

less

Transcript and Presenter's Notes

Title: Extensions of Time Claims


1
Extensions of Time Claims
Nicholas Longley Consultant JSM 852 2843
2599 nicholas.longley_at_mayerbrownjsm.com
17 November 2008
2
  • Mayer Brown is a global legal services
    organisation comprising legal practices that are
    separate entities ("Mayer Brown Practices"). The
    Mayer Brown Practices are Mayer Brown LLP, a
    limited liability partnership established in the
    United States Mayer Brown International LLP, a
    limited liability partnership incorporated in
    England and Wales and JSM, a Hong Kong
    partnership, and its associated entities in
    Asia. The Mayer Brown Practices are known as
    Mayer Brown JSM in Asia.

3
Introduction
  • Uncertainty with
  • What can be claimed?
  • How to claim?
  • When to claim?
  • Two Central Themes
  • Clear drafting
  • Clear thinking Do not overly restrict EoT
    grounds

4
What is Completion?
  • Practical or Substantial Completion
  • Mariner International Hotels v Atlas (2007)
  • Watts v McLeay (1911)
  • Balfour Beatty v Chestermount (1993)

5
Prevention Principle
  • Essentially it is that a party to the contract
    has been prevented from fulfilling its
    contractual obligations by virtue of conduct of
    the other party
  • Turner Corp v Co-ordinated Industries

6
Peak v McKinney
  • Facts
  • A Fault in the Perimeter Piles
  • The Employer had to appoint an expert but there
    were delays in doing so
  • The works were suspended for 58 weeks
  • The Contract contained an extension of time
    clause but it did not allow the Employer to
    extend time for its own delays

7
Peak v McKinney
  • Decision
  • There was no date from when liquidated damages
    could run
  • If a failure to complete on time is due to the
    fault of both the employer and the contractorthe
    clause does not bite. I cannot see howthe
    employer can insist on compliance with a
    condition if it is partly his own fault that it
    cannot be fulfilled.

8
Hong Kong Government Building Contract
  • Clause 50 (1) (a) Grounds for a EoT claim
  • Inclement weather and/or its consequences
    adversely affecting the progress of the Works
  • Variations under Clause 60
  • A substantial increase in the quantity of any
    item of work
  • Late possession or being deprived of possession
    of the Site at a later date
  • Disturbance to the progress of the Works
  • Any special circumstance of any kind whatsoever

9
HKIA/RICS Building Contract
  • Clause 23 Grounds for an EoT Claim
  • Force majeure
  • Inclement weather or the subsequent effects of
    such inclement weather which is expressly
    defined
  • Civil commotion, local combination of workmen,
    strikes and lockouts affecting any of the trades
    employed upon the Works
  • Variations under the contract
  • Delays by the Architect in providing
    instructions, drawings, details or levels
  • Delays by artists, tradesmen or others engaged by
    the Employer

10
HKIA/RICS Building Contract
  • by reason of the Main Contractor not having
    received in due time, necessary, instructions,
    drawings, details or levels from the Architect

11
HKIS/HKIA Building Contract (2005)
  • Clause 25.1 - Grounds for an EOT Claim
  • Excepted risks
  • Act of prevention, a breach of contract or other
    default by the Employer
  • Late issue of drawings, details, descriptive
    schedules or other similar documents

12
When to Claim?
  • Notification Clauses
  • RICS the Main Contractor shall forthwith give
    written notice of the cause of the delay
  • HK Government the Contractor shall forthwith
    give notice in writing to the ArchitectSuch
    notice shall not in any event be given later than
    28 days after the Architect has issued the
    relevant order or instruction
  • KCRC cl 45.11 it shall be a condition
    precedent to the Contractor being granted
    extensions of time that he complies strictly with
    the notification requirements

13
The Gaymark Decision
  • The Facts
  • The Contractor failed to complete by the Date of
    Completion because of Employers Delays
  • The Contractor had an obligation to comply with
    strict time limits which the Contractor did not
    do
  • The Employer claimed liquidated damages for delay
  • The Contractor argued that the Prevention
    Principle applied. The Employers acts prevented
    the Contractor from completing on time

14
The Gaymark Decision
  • The Decision
  • The Prevention Principle applies
  • The contract between the parties fails to
    provide for a situation where the Employer
    caused actual delays to the Contractor
    achieving practical completion coupled with the
    failure by the Contractor to comply with the
    notice provisions.

15
City Inn v Shephard Construction
  • The Facts
  • The Contract included a condition precedent
    requiring the Contractor to notify the architect
    if any instruction was likely to delay the Works
    within 14 days
  • The Contractor argued that there was an
    architects instruction which entitled it to an
    extension of time
  • The Contractor did not comply with this clause
    and completed late

16
City Inn v Shephard Construction
  • The Contractors Argument
  • That the condition precedent acted as a penalty
    as the failure to comply results in liquidated
    damages
  • The Decision
  • The liability for liquidated damages stems from
    the failure to complete late not from the failure
    to comply with the notification clause

17
How to Claim
  • Causation
  • Leyland Shipping v Norwich Union - competing
    causes
  • The torpedoes
  • Hitting the side of the dock
  • The decision of the harbour master to have the
    ship towed out of the harbour
  • The effect of two days of hitting the ground
  • The storm

18
Causation and Concurrency
  • Main Test proximate or dominant cause (Leyland
    Shipping v Norwich Union)
  • Laing v Doyle (2004) usual rules of causation
    apply to construction contracts
  • Henry Boot v Malmaison importance of critical
    path
  • Royal Brompton Hospital concurrent claims

19
Global Claims
  • Origins Crosby v Portland
  • A lump sum award is proper, provided that there
    is no duplication
  • Wharf v Eric Cumine
  • The fact that there are evidential problems is
    not a sufficient reason to strike out the claim
  • However a delay of seven years in detailing a
    claim meant that the claim was embarrassing and
    should be struck out

20
Global Claims Laing v Doyle
  • Common Sense Approach
  • Generally the Contractor must show a causal link
  • If the Contractor can show that all of the loss
    stems from delays which are all the
    responsibility of the Employer, a causal link is
    unnecessary
  • A global claim cannot succeed where any of the
    causes is the responsibility of the Contractor
  • If the global claim fails, the Contractor might
    still be able to use the dominent cause approach
    to claim for some losses

21
Conclusion
  • When drafting the contract take great care.
    Keep the Prevention Principle in mind. Small
    mistakes can be costly
  • When making claims, ensure that you can show
    cause and effect
  • Ultimately many claims are won or lost not on the
    law but on the evidence. Ensure that you keep
    good records and if you want to claim, get an
    expert at an early stage
Write a Comment
User Comments (0)
About PowerShow.com