Title: Managing Risk at Solystic
1(No Transcript)
2Managing Risk at Solystic
3Workshop Introduction
- Opening by Frédéric Badier
- Learning Objectives
- Workshop Overview
- Participant Introductions
- Participant Expectations
4Learning Objectives
- The purpose of this workshop is to provide
participants with a solid understanding of Risk
Management principles, approach, techniques and
best practices
5Learning contents
- Develop your skills to
- Understand what is risk
- Anticipate risk before it arises
- Set up action plan to eliminate anticipated risks
- Set up action plan to recover situation when
risks arise - Use a common Solystic Risk Management methodology
to be integrated into your project plan
6Why a Risk Management Methodology ?
- A Risk Management methodology
- For the Operation department to be in a better
position to face the rapid changes in the market
and a growing competition - To address needs expressed by Northrop
- To be in line with strategic customers
expectation - To make life of Project Managers and Chargé
dAffaires easier through better planning,
being more proactive than reactive - To better cope with the shortening of the overall
production cycle
7The proposed methodology
8Learning Approach
- Diverse learning methods
- Business related case studies
- Balance between theory and practice
- Leverage knowledge and experience of participants
- Balance individual and course goals
9Workshop Overview
- Module 1 - Project Risk Management
- Module 2 - Risk Identification
- Module 3 - Risk Analysis
- Module 4 - Risk Avoidance and Mitigation
- Module 5 - Risk Monitoring and Control
- Module 6 - Risk Management Implementation
- Module 7 - Risk Management Tips and Tricks
- Module 8 - Cost Effectiveness of Risk Mgt
Day 1
Day 2
10Indicative Schedule
Day 1
Day 2
Start 8.30 am
Start 10 am
Break 10.45
Break 11.30
Lunch 13.00-14.30
Lunch 12.30-14.00
Break 16.00
Finish 16.30
Finish 18.30
11Introduction and experience sharing
- Experience in leading Risk Management and Project
Management workshops at Nissan, Microsoft across
Europe, Cisco, Coca-Cola, SUEZ - Teaching Project and Risk Management at INSEAD,
MBA EM Lyon, Milano Catholic University - Having implemented SAP projects European-wide at
Procter Gamble and rolled-out in North America
12Networking and experience sharing
- Further to the questionnaire you filled in
- What is your current position ?
- Which key project are you currently working on ?
- In these projects, what are, according to you,
the Key Success Factors ? - What kind of barriers have you identified ?
- What are the reasons for potential failures you
have identified ?
13Project andProject Risk Management
- Project
- Project Risk
- Project Success Failures
- Risk Processes
- Risk Management
- Risk Management Planning
14Overview
15What Is A Project?
- According to you
- What is a project ?
16What Is A Project?
- A project is a temporary endeavor undertaken to
create a unique product, service or result - Source Project Management Institute (PMI)
17What Is A Project?
- A project is a temporary endeavor undertaken to
create a unique product, service or result - A project balances business financial benefits
against risk cost - Source Project Management Institute (PMI)
18What is sound Project Management ?
- Project management is the art to run and
coordinate human and material resources - All along project life cycle
- Using specific techniques
- To meet objectives of time, cost quality and
aiming thus at total customer satisfaction
19What is sound Project Management ?
20What is sound Project Management ?
Scope
Scope
Scope
21Characteristics of a Project
- Clearly defined and agreed deliverables
- Set of activities performed once
- Planned stages reflecting milestones
- Active Risk management
- Approved and fixed budget
- Team assembled for the purpose
- Clearly defined Benefits to be delivered
- Clearly identified Pitfalls
22Project Risk
- Risk is a measure of a project's inability to
achieve its objectives - It comprises two components
- the probability of failing to achieve particular
objectives - the consequences of failing to achieve those
objectives
23Project Success and Failures
- The factors influencing the outcome
24Reasons for project failures (Source Gartner
2005)
25Project Success
- A project is successful when
- It is completed according to scope and schedule
- The costs do not exceed the project budget
- The solution fits with the needs
- Aligns with Business Strategy
- Meets Customer Business Requirements
- Realizes the Business Case
- Ensures Organizational Readiness
- Although there are varying degrees of failure, a
project fails if any of the above criteria are
not met
26Critical Success Factors
- Formal and smart objectives needs clearly
defined and signed off - A stable project scope
- Identified risks and mitigation plan
- Sponsorship and empowerment from management
- Adequate human resources, budget and logistics
- Efficient business leader-project leader
co-management - Strong project methodology, clear and common
approach - Rigorous acceptance tests
- Continuous communication detect risk and alert
system (problems are getting worse with time !) - Change impact has been identified and taken care
of
27 Be SMARTon Objectives
- S PECIFIC
- M EASURABLE
- A GREED
- R EALISTIC
- T IME BOUND
SMART !
28Risk Management
- Risk management is the practice of controlling
risk, this process includes - Identifying and tracking risk areas
- Developing Risk avoidance plan
- Developing Risk mitigation plans
- Monitoring risks i.e. performing risk assessments
to determine how risks have changed
29Risk Management
- Effective Risk Management is an on going process
- Effective risk management is a critical
component of any winning management strategy in
the market - If properly designed, effective risk management
allows an organization to actually take on some
additional risks, provided they are carefully
managed and balanced with extra-value
30Risk Management Process
3. Qualitative Risk Analysis
2. Risk Identification
1. Risk Management Planning
4. Quantitative Risk Analysis
Risk Management Process
6. Risk Monitoring and Control
5. Risk Avoidance Planning
31The IPECC Process Groups based on PMI
Process Groups
Initiating
Planning
Executing
Controlling
Closing
32The IPECC Process Groups Sequence
The process groups help to manage the project
lifecycle
33Initiating Projects
34Project Initiation System View
Input
- Objectives
- Description of project deliverables
- Information/learning from prior projects
- Identification of key users and stakeholders
Output
End Results
- Project proposal
- Preliminary Project
- Scope Statement
- Risk Management Plan
- Rough cost/benefits
- assessment
- Assumptions/constraints
- Go/No go review with Management
- Formal agreement
- to go
- Budget released or CER approved
- Project team appointed
35 Project Initiation
- Getting started
- Defining rough scope and objectives
- Checking alignment with overall strategy and
organisation or department priorities - Designing a statement of work
- Identifying all key players and stakeholders
36 Project Initiation
- At Macro-level i.e. roughly
- Assess feasibility based on clients requirements
- Prepare a rough schedule and preliminary scope
- Prepare a first Risk Management Planning
- Run a rough Cost Benefit
37Defining Preliminary Scope Statement
- An important step in the Initiation phase is to
define the Scope of the project - In the methodology you will find the terms SOW
i.e. Statement Of Work
38Scope Statement Tip
- The Scope
- Defines the project boundaries
- What is IN and what is OUT
- Remember to be SMART
39Define Scope Carefully
- How many modules?
- How many legacy systems ?
- How much legacy data conversion ?
- How many systems to interfaces ?
Pan European ERP Project
What you don't know hurts you!
40Project Proposal Go or No Go ?
- The Project Proposal is submitted to Management
for approval - The end result is
- a Go or No Go
41Exercise on Risk Identification Reasons for
failure
- Work in teams
- Subject Replacement of Mechanized Letter
Sorting Systems in Hong Kong - Identify Risk Areas and link them with potential
reason for failures - Prepare the exercise in team (30 min)
- Elect a presenter (s) to feedback to the main
group (10 min. max)
42 Risk Management Planning
- Within the Project Management methodology, we
will now focus on Risk Management Planning - In the context of Solystic, we start from T0 i.e.
at the beginning of the Execution phase
43Risk Management Lifecycle
Stage Initiation
Project Initiation
Throughout Stage
3
Identification Documentation
1
2
6
7
4
Establish Strategy
Initiate Risk Log
Tracking Reporting
Closing
Assignment Review
5
Analysis Mitigation
44Risk Management Planning
- The purpose of Risk Management is to assure that
the risks to the success of the project are
identified and avoidance and mitigation plans are
developed - The Risk Management Plan includes
- Risk Identification Assessment
- Risk Avoidance Plan
- Risk Mitigation Plan execution
- Monitoring Risk Assessments
45Risk Management Planning
- The 5 fundamental questions to be
asked/addressed in both Project AND Risk
Management Planning are - WHAT / WHY?
- HOW?
- WHO?
- WHEN?
- HOW MUCH?
46Inputs to Risk Management Planning
- Project Proposal
- Organizational Policies
- Analysis of Stakeholder Tolerances
- Planning Meetings and Agenda
47Outputs of Risk Management Planning
- Risk Management Plan
- Scope
- Schedule
- Deliverables
- Activities
- Team
- Cost
RISK
48Risk Identification
- Risk Identification
- Risk Categories
- Risk Statements
49Inputs for Risk Identification
- Project and Risk Management plans
- Performance/Quality issues
- Technical issues
- Organizational environment
- Business environment
- Financial constraints
- Regulatory issues
- Historical information
50Techniques
- Interviews
- Brainstorming
- Programmatic Dependency Analysis
- SWOT Analysis
- Nominal Group Technique
- Pert Estimating
- Checklists
51Programmatic Dependency Analysis
QA / QC
Upper Management
Project Requestor/ End-User
Project Manager
Vendors/ Contractors
Legal
Marketing
R D
Team
Production
52Risk Identification Outputs
- Risk Statements
- Sources of Risk
- Risk Situation
- Risk Description
- Risk Triggers/Events
53Stating a Risk
Risk
Impact
Situation
- Describe cause and effect relationship
- Understand the nature of impact
- Consider the audience
- Avoid using might, may, or could
- Consider multiple effects
- Do not quantify/qualify severity of Risk
54Risk Categories
- Business Imperative
- Technical
- External environment
- Environmental
- Organizational
- Regulatory
- Project Structure and Management
- People
55Important Project Risks
56Linking Risk Management and Project Planning
57Risk Management PM Methodology
- A solid Risk Management needs to be fully
integrated into the Project Life Cycle - Link the different steps in Managing your Risks
to the IPECC stages
58Linking Risk with IPECC stages
- Initiating stage Risk focus areas
- Stakeholders, especially customers, expectations
- as per TC
- Feasibility of technical expected performance
objectives - Assessment on rough cost vs. benefit study
- Feasibility to meet final deadline
- and deliver milestones on time
- Reaction of competition on prices technology
59Linking Risk with IPECC stages
- Planning stage Risk focus areas
- Assessment of the feasibility of your
plan/schedule - Assessment of different alternative scenarios
- Check on regulatory constraints or
- deregulation opportunities
- Likelihood of total cost of your plan
- Likelihood of getting or not getting the required
resources (people technology)
60Linking Risk with IPECC stages
- Executing stage Risk focus areas
- Identification of remaining execution risks
- Assessment of impact from change in the Plan
- during Execution
- Overspending vs. original cost budget estimates
- in the course of the Execution
61Linking Risk with IPECC stages
- Controlling stage Risk focus areas
- Assessment of potential problems in technical
solution prior to Site Acceptance Test - Time slippage in in the course of Controlling
stage - and impact on final completion deadline
- Diagnose any difficulty or unrealistic
commitment leading for change in the original
Plan. Better act now than in the Closing stage
62Linking Risk with IPECC stages
- Closing stage Risk focus areas
- Feasibility of final delivery schedule
- Feasibility in fulfilling Key Performance
Indicators expected by the client - Likelihood of fast response if emerging
difficulty in the Site Acceptance Test and final
delivery - Reliability of Site Acceptance Test in reflecting
the on going reality - Assessment of potential need for future
liabilities and post installation support to the
client - Reliability in assessment of final profit
delivered in the overall project taking the full
cost picture
63Exercise on Risk Management Planning
- Work in teams
- Subject iLSM supply to Royal Mail and/or Flats
Automation Program Phase II - Identify - Risk Output
- - Risk Categories
- - Cause and effect relationship
- Prepare the exercise in team (30 min)
- Elect a presenter (s) to feedback to the main
group (10 min. max)
64Risk Analysis
- Qualitative and Quantitative Risk Analysis
- Risk Scoring
- Risk Register
- Risk Profile
- Decision Matrix
65Estimating Risk Probability
66Severity of Impact
67Risk Impact
- Critical an event that, if it occurred, would
cause program failure (inability to achieve
minimum acceptable requirements). - Serious an event that, if it occurred, would
cause major cost and schedule increases.
Secondary requirements may not be achieved. - Moderate an event that, if it occurred, would
cause moderate cost and schedule increases, but
important requirements would still be met. - Minor an event that, if it occurred, would cause
only a small cost and schedule increase.
Requirements would still be achieved. - Negligible an event that, if it occurred, would
have no effect on program.
68Inputs for Qualitative Risk Analysis
For Characterizing Probability
For Characterizing Severity
- Estimates from individual contributors
- Project plans
- Lessons-learned files
- Range estimating for cost
- PERT estimating
- Resource constraints
- Complexity of the project
69Decision Matrix
PROBABILITY
High
Medium
Low
Catastrophic
High
SEVERITY
Medium
Low
70Decision Matrix Solystic perspective
PROBABILITY
High
Medium
Low
Catastrophic
Direct impact on Customer contract e.g Site
Acceptance Test issue
High
SEVERITY
Technical Risk with unlikely solution e.g.
Validation for roll-out
Medium
Technical Risk with solution e.g. Mock-up Design
Low
71What Can Be Measured?
Quantity how many?
Quality how well?
Cost how much?
Time how long?
72Risk Assessment
- In terms of Impact (what is the potential for
harm) and Probability (how likely is it to occur)
High
IMPACT
Medium
Low
Low
Medium
High
PROBABILITY
73Risk Scoring
74Exercise on Risk Analysis
- Work in teams
- Subject iLSM supply to Royal Mail and/or Flats
Automation Program Phase II - Run a full Risk analysis, by Risk category
- - Assess Probability
- - Assess Severity
- - Prepare a decision matrix
- Prepare the exercise in team
- (40 min)
- Elect a presenter (s) to feedback to the main
group
75Reminder on Project Planning Link with Risk
Management
76Risk Management Project Planning
- A solid Risk Management cannot stand alone
- But needs to be part of an integrated Project
Management methodology
77Planning tasks using Work Breakdown Structure
tool
78Work Breakdown Structure WBS
- Based on the agreed scope
- A method to decompose the tasks down to the level
of execution
79Work Breakdown Structure
- The Work Breakdown Structure (WBS) is a way to
graphically present the project using
flowcharting - The WBS represents the project in terms of the
hierarchy of tasks and deliverables it will
produce - The WBS starts with a single box at the top which
represents the whole project
80Decomposition
- The project is then broken down into its
components with lower level boxes - Level 1 Project Name
- Level 2 Key Deliverables or Work Packages
- Level 3 Tasks
- Level 4 Subtasks
81Work Breakdown Structure WBS
82Guidelines to build a WBS
- Start from the agreed Scope
- Start with a heading box at Level 1 indicating
the Project Name - Identify the major deliverables which will be
form the basis of the Level 2 i.e. Key
Deliverables or Work Package
83Guidelines to build a WBS
- Drill down your Scope design vertically for each
Key Deliverable to a Level 3 i.e. Tasks level - If necessary, drill further down at a Level 4
i.e. Subtasks level, until all the subtasks can
be costed and scheduled
84WBS Types
- There are many types of WBS, including
- phase organized
- component oriented
- functional
- contractual
85WBS Example (Phased)
Level 1
Make Dinner
Level 2
Prepare Food
Wine
Cook Food
Lay Table
Serve Dinner
Select Wines
Level 3
Prepare
Cook
Serve
Starter
Starter
Starter
Open bottles
Prepare Main
Cook
Serve Main
Course
Main Course
Course
Prepare
Serve
Dessert
Dessert
Level 4
86WBS Example (Component)
87WBS Example (Functional) en annexe
88Planning organisation structure Organisation
Breakdown Structure tool
89Organisation Breakdown Structure (OBS)
- The Organisation Breakdown Structure
- A functionally oriented structure indicating
organizational relationships and used as the
framework for the assignment of work
responsibilities - A project organization arranged so as to relate
Key Deliverables or Work Packages to
organizational units
90Guidelines to build an OBS
- Start from your WBS chart
- Assign names at the Level 2 i.e. Key Deliverables
or Work Packages level - Assign names further down at the Tasks level and
at the Subtasks level
91RACI Matrix
92 Assigning responsibility and accountability
- Roles and responsibilities assignment to
- Project team members
- Users
- Stakeholders
- Sponsors
-
93Project Management Governance rules
- It is critical to have clearly identified
- Who will be responsible for what
- Who will be accountable for what
94The RACI Matrix A tool for clear roles
assignment
- R who is responsible for doing the task
- A who is accountable for approving the task
- C who should be consulted about the task
- I who should be informed about the task
95The RACI Matrix An illustration
96Risk Avoidance and Mitigation
- Proactive and Reactive Risk Response Planning
- Risk Register
- Risk Aversion
- Risk Symptoms
- Contingency Planning
97Risk Retention
- The organization expects that taking the risk,
value will exceed costs - The exposure ("potential loss") is too small
- The odds of success are more than 50-50
- There appears to be a small number of
alternatives - A contingency plan for recovery is in place
98Expected Value
- EXPECTED VALUE REWARD x PROBABILITY OF SUCCESS
LOSS x PROBABILITY OF FAILURE
99Risk Response Planning
- Developing options and determining actions to
enhance opportunities and reduce threats to the
project objectives
100Risk Response Plans Include
- The strategy applied to address the Risk
- Specific steps to be carried out
- Schedule for when these steps will be carried out
- Assignment of responsibilities
- Additional resources or outside assistance, if
required
101Proactive Risk Reduction
- Avoidance
- When feasible, this approach consists in taking
action step ahead of the identified risk to have
it eliminated
102Other Risk Reduction approach
- Mitigation
- Reduce Probability of Occurrence
- And
- Reduce Severity of Impact
103Risk Symptoms
A trigger should be
- Objectiveclear to everyone
- Appropriaterelated to key causes of Risk
- Timelyprovide clear early warning that steps
need to taken
- Document/distribute risk response plans
- Inform parties if its necessary to employ
reactive strategies - Add cost of strategies to project cost
104An existing application at Solystic the NSC
Program
- Under the NSC program for Belgium
- (New Sorting Centers)
- An effective Risk Management methodology has been
set up from beginning to completion - Very interesting learning can be drawn from this
experience - The Risk Management methodology used for NSC is a
positive application, with room for flexibility
in adaptation to larger project
105(No Transcript)
106(No Transcript)
107(No Transcript)
108(No Transcript)
109(No Transcript)
110Exercise on Risk Analysis
- Work in teams
- Subject iLSM supply to Royal Mail and/or Flats
Automation Program Phase II - Design a Risk management log based on the NSC
methodology - Feel free, in each team, to simplify the template
- Keeping the items your team regards as critical
- Prepare the exercise in team
- (45 min)
- Elect a presenter (s) to feedback to the main
group
111Risk Monitoring and Control
- Risk Watch List
- Risk Response Plan Execution
- Effectiveness Assessment
- Post-mortem Lessons Learned
- Triggers for Contingency Activation
112Risk Monitoring and Control
- Keeping track of identified risks, monitoring
residual risks, and identifying new risks
113Why Reassess Risks?
- Changes in personnel
- Changes in the project environment
(organizational climate) - Changes in customer requirements
- Technological developments
- Business factor fluctuations
- Corrections
114Risk Watch List
Responsible Party ______ ______ ______ ______ ____
__
Current Status _______ _______ _______ _______ ___
____
Previous Priority ______ ______ ______ ______ ____
__
Risk ________ ________ ________ ________ ________
Priority 1 2 3 4 5
115Before Leaving the Project
- Did the tasks performed produce the desired
deliverable on time and within the allotted
budget? - Was this the best (i.e., most efficient,
effective and/or least expensive) way to produce
that deliverable? - Did the deliverable fulfill the needs for which
it was designed? (And, if not, why not?) - What lessons did we learn?
116Risk Management Implementation
- Implementation Strategy and Approach
- Roles and Responsibilities
- Risk Management Maturity Stages
117Maturity Stages
Strategy
Culture
Policy
Repeatable
Ad Hoc
118Implementation Approach
- Obtain Senior Management support for the
initiative - Develop a Risk Profile
- Integrate Risk Management into Existing Project
Management Processes - Practice Integrated Risk Management
- Enable Continuous Risk Management Learning
119Risk Profile
120Roles
- Risk Owner
- Risk Action Manager
121Risk Management Tips and Tricks
- Project Risk Wheel
- Supporting Tools and Templates
- Best Practices
122Risk Wheel
- Formalized project charter and roll-out planning
- Procedures for progress tracking and scope
management - Benefits Realization Tracking
- Communications program
- Knowledge Transfer to Competence Center
Clear Objectives
- Use of accelerators and productivity tools
- Backfilling
- System testing standards procedures
- Post go-live support
- Clear roles responsibilities
Minimal Business Disruption
Joint IT Business Ownership
- Involve global process owners
- Involve business representatives
- Executive alignment
- Communication to the organization
- Address the needs of different stakeholder groups
- Assess change impact
- on current organization
- Early end-user involvement
- Job specific training
- HR process alignment
Ongoing ChangeManagement
Flexible Approach
- Multicultural, experienced teams
- Clear procedures and policies
- Adherence to industry standards
- Alignment Corporate
- strategy with Regional/Local
- requirements
Capable Project Team
Strong Project Management
- Tracking of progress against plan
- Effective methodologies and tools
- Quality, risk and issue management
- Governance model / decision making process
- Validation after each phase of the project
- Experienced implementation partners
- High standards for team
- Right balance team members
- Key project roles full-time
- Team on-boarding and training programs
- Team incentives
123Tools and Templates
- Brainstorming
- SWOT Analysis
- Sample Risk List
- Risk Template
- PERT Estimating
- Prioritized Risk Ranking
- Risk Response Form
- Program Risk Management Evaluation
- Procedure Risk Management
- Procedure Risk Prioritization
124Best Practice
- Set Goals for Risk Management Maturity
- Promote Risk Management Culture and Attitude
- Set up a Risk Management Function
- Track Risk Management Performance
- Provide Risk Management Training
- Adopt unified Approaches, Tools and Metrics
125Cost effectiveness of Risk Management
- Cost of Risk Response Plans
- Probability of Attaining Project Objectives
- Cost Effectiveness Assessment
126Cost of Risk Response
- Acquisition cost
- Development cost
- Testing cost
- Deployment cost
- Training cost
- Communication cost
- Monitoring cost
- Support cost
127Benefits
- Achievement of Objectives
- Anticipation of problems
- Reduced problem solving/trouble shooting
- Learning from errors of the past
- Strengthening of Project Management
- Increased accountability
- Improved overall Management capability
- Higher value creation
128Budget Control
129Budget Baseline (S-Curve)
The budgeted cost of the work scheduled is known
as the Planned Value or PV for short
130Budget Burndown Chart
131Cost Effectiveness
- Disproportionality Rule
- (cost of incidents and recovery)
- (cost of proactive risk response)
132Conclusion
-
- Dont forget that Risk Management is above all
a search for further opportunities
133THANKS TO ALL OF YOU !