Title: Information Services Board Presentation on ProviderOne
1Information Services BoardPresentation on
ProviderOne
2Introductions
- Robin Arnold-Williams Secretary, DSHS
- Doug Porter Assistant Secretary, DSHS Health and
Recovery Services Administration - Heidi Robbins Brown Deputy Asst. Secretary, DSHS
Health and Recovery Services Administration - John Anderson Project Manager, ProviderOne
Project - Shailesh Patel Director, Project Management
Office, CNSI - Gena Cruciani Deputy Project Manager,
ProviderOne Project
3Agenda
- Project Status (scope/schedule/budget/success
factors) - Assessment Results Related to Schedule Delays
- Release Strategy
- High Priority Issues and Risks
- Quality Assurance (QA) Recommendations
- Next Steps
4Project Status
- Scope
- No change requests impacting scope approved to
date - Schedule
- Project 10-week delay as previously reported
- 10 design complete vs. 20 planned
- 5 development complete vs. 5 planned
Legend Green low risk Yellow elevated risk,
assessment reqd Red high risk, action
reqd Trend indicators - (worsened),
(improved), (no change)
5Budget
- Positive variance of 5.4 M through 11/30/05
- Primary cause of variance - 5 delayed
deliverables (2 approved in December)
6Success Factors
- Overall Rating 79
- Scored 2 of the 12 Success Factors a 1
- Reliable Estimates Requirements Verification
estimates were not reliable. Revised design
estimates have proved to be too aggressive for
some functional teams and realistic for others.
Estimates are continuing to improve. - Implementation Not a project inadequacy rather
the tool does not consider downstream
deliverables. Future Implementation Plan
deliverables include - Provider Readiness Plan
- Implementation Plan
- Provider Training Plan
- Staff Training Plan
- Business Cultural Change Plan
- Business Transition Plan
7Assessment Results Related to Schedule Delay
- Tasks completed since November ISB
- Examined task dependencies
- Scrutinized original estimates
- Incorporated incremental development approach
- Evaluated test strategies
- Investigated staggered implementation
8Assessment Results Related to Schedule Delay
- Assessment yielded no gain in schedule delays
Still projecting a 10 week delay in go live for
main event - Staggered implementation assessment led to
development of a preliminary Release Strategy
9Preliminary Release Strategy
Draft
- Decommission ACS System
- System Certifiable by CMS
10Release Strategy - Next Steps
- Complete Analysis
- Analyze impact to work plan based upon release
strategy - Develop detailed cost estimates for new work in
each release - Identify cost savings and specific benefits
associated with each release - Verify components of each release
- Obtain DSHS and ISB Approval of Release Strategy
- Communicate Release Strategy to DSHS staff and
provider communities
11High Priority Issues/Risks
12Subcontractor Update
- DSHS formally approved Sun to perform Data Center
Operations 11/05 - CNSI executed contract with
SUN 1/06 - CNSI requested a change in imaging subcontractors
from Coastal to HTC Global Services DSHS
evaluated the proposal and has approved the
requested change. Executed contract expected from
CNSI in 1/06. - CNSI using HTC resources on design tasks pending
contract execution - CNSI negotiating with Printing for Systems,
original proposed vendor for magnetic ID cards
no short term impact on project tasks
13Quality Assurance (QA) Recommendations
14Next Steps
- Continue with Design Phase Activities
- Monitor and report progress against Design Phase
checkpoints - Complete Release Strategy Analysis
- Update development estimates after completion of
each interim design work product - Refine work plan/schedule again at end of Design
and Development Phases - Monitor vendor resource utilization
- Begin iterative development work
15Questions?
Visit the MMIS Re-Procurement Internet http//maa
.dshs.wa.gov/mmis