New Mississippi River Bridge Project Overview - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

New Mississippi River Bridge Project Overview

Description:

New Mississippi River Bridge Project Overview – PowerPoint PPT presentation

Number of Views:137
Avg rating:3.0/5.0
Slides: 32
Provided by: lagem
Category:

less

Transcript and Presenter's Notes

Title: New Mississippi River Bridge Project Overview


1
New Mississippi River Bridge Project Overview
  • Greg Horn, MoDOT Project DirectorBrooks
    Brestal, IDOT Deputy Project Director

2
Why is the MRB needed?
  • Poplar Street Bridge carries 3 interstates
  • PSB is 40 years old, needs future rehabilitation
  • 115,000 and 125,000 vehicles daily
  • By 2030, increases to 150,000 vehicles daily

3
How It Helps
  • Reduces traffic congestion
  • Enhances safety
  • Promotes economic growth in the region
  • Provides alternate routes

4
Project History
  • 1990 - Discussions began
  • 1991 - EIS started
  • 1997 - Location selected
  • 2001 - Record Of Decision issued

5
Project History
  • 2005 1.6 billion project not feasible
  • 2005 239 million authorized by Federal
    Transportation Bill
  • 2006 New estimate of 1 billion
  • 2006 to 2008 MO and IL discuss solutions

6
  • MO IL governors sign
  • agreement for 640 million
  • February 28, 2008

7
Comparison
  • Original Concept
  • 2 bridges, 8 lanes
  • MO Connection
  • I-70 West
  • city at Tucker
  • I-55/44 South
  • IL Connection
  • I-55/64 Tri-level
  • I-70 East
  • New Concept
  • 1 bridge, 4 lanes (6 lanes)
  • MO Connection
  • I-70 West
  • city at Cass
  • IL Connection
  • I-55/64/70 Tri-level

8
(No Transcript)
9
(No Transcript)
10
Missouri Phase I
11
Missouri Phase II
12
Illinois Phase I
13
Illinois Phase II
14
Funding
15
Funding Breakdown
  • Federal Funding- 239 million
  • Illinois Funding - 313 million
  • Missouri Funding - 88 million

16
MRB design team members
  • Mississippi River Bridge - HNTB
  • Illinois Connector - TENG
  • Illinois Tri-Level I-55/64/70- CTE
  • Missouri Interchange - CMT

17
Whats going on now?
  • Co-located offices in St. Louis City
  • Preliminary design work
  • Purchasing right-of-way
  • Drilling in river
  • Begin contractor involvement process

18
Contractor Involvement Process
  • Only includes Mississippi River Bridge and
    approaches
  • Missouri North I-70 interchange will incorporate
    something similar
  • Will NOT be used for Illinois relocated I-70
    roadways or the tri-level interchange

19
Contractor Involvement Process
20
Contractor prequalification process
  • Round 1 Prequalify to bid (ATC process)
  • RFQ advertised by October 24, 2008
  • SOQ due by November 21, 2008.
  • Approved by November 26, 2008
  • Round 2 Prequalify to bid (Base Plans)
  • Readvertise RFQ by July 13, 2009
  • SOQ due by August 10, 2009
  • Approved by August 17, 2009

21
Prequalification process
  • Contractors prequalified based on
  • Previous experience
  • Major projects
  • Bridges on major rivers
  • Experience of key personnel
  • Available bonding capacity and backlog
  • Diversity experience and proposals
  • Other requirements to be determined
  • Prequalification is pass/fail, not point-based

22
Alternate Technical Concepts
  • Qualify ATC contractors by Nov. 26, 2008
  • Engage one-on-one contractor/MRB Team
    confidential discussions
  • MRB team evaluates proposed concepts
  • Baseline design
  • Minor changes
  • Major changes (change of scope)

23
ATC Minor changes
  • MRB Team develops approved concepts into
    contractor specific bid package
  • Complete ATC process by April 17, 2009
  • MRB Team completes contractor-specific final
    plans (bid packages) by July 9, 2009

24
ATC Major Changes
  • Contractor team develops approved concepts into
    plans
  • MRB team incorporates these plans into
    contractor-specific bid package
  • Complete ATC process by April 17, 2009
  • Final plans (bid packages) completed by July 9,
    2009

25
Construction bidding
  • All plans developed by July 9, 2009
  • Minor ATC (MRB team develops)
  • Major ATC (Contractor/MRB team develops)
  • Base plans (MRB team develops)
  • Qualify contractors by August 17, 2009
  • Advertise to qualified bidders September 2009
  • Bids due October 2009

26
Construction bidding
  • Contract awarded to lowest bidder November 2009
  • Construction to proceed January 2010
  • Does not preclude value engineering proposals
    during construction process

27
Federal Highway approval
  • Part of the MRB team
  • FHWA has approved the MRB ATC process
  • Special Experimental Projects No. 14 Alternate
    Contracting (SEP-14)
  • All regular Federal-aid construction contract
    provisions apply

28
DBE and WFU plan process
  • Meeting DBE and Work Force Utilization goals is
    extremely important to MoDOT and IDOT
  • MoDOT/IDOT reviews project for DBE Goals
  • October 2008 November 2008
  • Caucusing and Round Table Discussions for WFU
  • FebruaryApril 2009

29
DBE and WFU plan process
  • Complete Partnering Agreement
  • May 2009
  • Include Partnering Agreement Goals and Objectives
    in Construction Contract
  • June August 2009
  • Advisory Committee Mtgs/Community Updates
  • August 2009-Life of Project

30
Schedule
  • Construction Begins 2010
  • Construction complete2014-2016

31
www.newriverbridge.org MRB Project Director
Greg Horn, (314) 236-2930gregory.horn_at_modot.mo.g
ovMRB Deputy Project DirectorBrooks Brestal,
(618) 346-3175brooks.brestal_at_illinois.gov
Write a Comment
User Comments (0)
About PowerShow.com